12FPC219B0008

x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

NRCS-OK-121212

USDA-NRCS Stillwater Watershed Office 2600 S. Main Suite D.

Stillwater OK 74074

WASHINGTON DC 20250

FPAC-HQ-12FPC2

RM 6801-S

1400 INDEPENDENCE AVE SW

Operations Branch-Section 2 FPAC Acquisition Division

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE

09/02/2019

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/02/2019

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Pilot Grove 64A - Remedial Watershed Repair

The purpose of this amendment is to incorporate the revised Specification 94 - Contr4actor

Quality Control into the solicitation. The following questions were asked and answered at the site showing and are being provided for information. The sign in sheet for the site showing is attached to this amendment.

QUESTIONS & ANSWERS

Q1. Is a Disadvantage Business Enterprise (DBE) set-aside apart of this project?

A1. The solicitation for this project is a Total Small Business Set-Aside only.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

SHARLA K. GOFORTH

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 14

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12FPC219B0008/0001

Q2. Is lime treated earthfill mixed in place?

A2. No; the lime processing area is shown on page

1 of the drawings and as specified in

Construction Specification 28 ¿ Lime-Treated

Earthfill

Q3. Will the landowner continue to use the private drive during the construction period?

A3. Yes

Q4. Are the two trees located in the lime processing area to remain in place?

A4. Follow up will be needed after discussion with the landowners.

Q5. Is all the needed information concerning this project available to the contractors?

A5. Yes; the solicitation, with all appurtenant documentation, is available at www.fbo.gov by searching for solicitation # 12FBC219B0008.

Q6. If silt fence has to be removed for any reason during the construction process will the contractor receive compensation for this?

A6. The silt fence is to be installed at the locations as designated on the construction drawings. If additional silt fence is needed in locations of relocated or additional disturbed areas, a modification will be processed for the additional length.

Q7. Will the sprigging still be in season if completion of the job falls towards the end of

November or into December?

A7. Construction Specification 6 ¿ Seeding, Sprigging, Mulching specifies the sprigging window between January 15th ¿ April 15th and

August 15 ¿ September 30th. Alternative revegetation will be discussed if the project is near completion outside of these dates.

Q8. Once the earthfill is processed with lime, how soon does placement occur?

A8. Placement of the lime-treated earthfill shall be within the same work day as it is mixed as specified by Construction Specification 28 ¿

Lime-Treated Earthfill.

Q9. Will there be a required gradation of the earthfill after lime treatment is complete?

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

3 14

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12FPC219B0008/0001

A9. The gradation requirements for the lime-treated earthfill are included in

Construction Specification 28 ¿ Lime-Treated

Earthfill. The minimum passing 2-inch sieve is

100% and the minimum passing No. 4 sieve is 60%.

Q10. Are 1pt curves required for earthfill?

A10. Yes; the requirements for the one-point method are described in Construction

Specification 94 ¿ Contractor Quality Control.

Q11. How many one-point curves are required per lift?

A11. Construction Specification 94 requires full time inspection of earthfill and lime-treated earthfill. At least one one-point test shall be conducted for every three in-place moisture density tests that are taken. More frequent tests shall be required if compaction requirements are not being obtained.

Q12. What is the availability of water if there is none in the reservoir?

A12. The Contractor is responsible for obtaining a source of water for all construction activities that require the use of water.

Q13. Can a portion of the concrete private drive be removed where the construction access road crosses over it and then be replaced at the end of the project?

A13. Construction Specification 8 ¿ Mobilization and Demobilization and the construction drawings state the residential road is to be protected during construction. Full access for the landowners shall be maintained. Considerations will be made to the proposed protection from the

Contractor.

Q14. Where will the temporary livestock fence be installed?

A14. All temporary fencing shall be capable of turning livestock and preventing its access to the construction area as specified in

Construction Specification 8 ¿ Mobilization and

Demobilization.

Q15. How many control points are there on the site?

A15. All control points are listed on page 1 of

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

4 14

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12FPC219B0008/0001

the construction drawings and include 2 horizontal controls and 2 vertical controls.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

(210-VI-NEH, January 2009) 94-1

Construction Specification 94—Contractor Quality Control

1. Scope The work consists of developing, implementing, and maintaining a quality control system to ensure that the specified quality is achieved for all materials and work performed.

2. Equipment and materials Equipment and material used for quality control shall be of the quality and condition required to meet the test specifications cited in the contract. Testing equipment shall be properly adjusted and calibrated at the start of operations and the calibration maintained at the frequency specified. Records of equipment calibration tests shall be available to the engineer at all times. Equipment shall be operated and maintained by qualified operators as prescribed in the manufacturer's operating instructions, the references specified, and as specified in section 10 of this specification. All equipment and materials used in performing quality control testing shall be as prescribed by the test standards referenced in the contract or in section 10.

All equipment and materials shall be handled and operated in a safe and proper manner and shall comply with all applicable regulations pertaining to their use, operation, handling, storage, and transportation.

3. Quality control system Method 1—The contractor shall develop, implement, and maintain a system of quality control to provide the specified material testing and verification of material quality before use. The system activities shall include procedures to verify adequacy of completed work, initiate corrective action to be taken, and document the final results. The identification of the quality control personnel and their duties and authorities shall be submitted to the contracting officer in writing within 15 calendar days after notice of award.

Method 2—The contractor shall develop, implement, and maintain a system adequate to achieve the specified quality of all work performed, material incorporated, and equipment furnished before use. The system established shall be documented in a written plan developed by the contractor and approved by the contracting officer. The system activities shall include the material testing and inspection needed to verify the adequacy of completed work and procedures to be followed when corrective action is required.

Daily records to substantiate the conduct of the system shall be maintained by the contractor. The quality control plan shall cover all aspects of quality control and shall address, as a minimum, all specified testing and inspection requirements. The plan provided shall be consistent with the planned performance in the contractor's approved construction schedule. The plan shall identify the contractor's onsite quality control manager and provide an organizational listing of all quality control personnel and their specific duties. The written plan shall be submitted to the contracting officer within 15 calendar days after notice of award. The contractor shall not proceed with any construction activity that requires inspection until the written plan is approved by the contracting officer.

All methods—The quality control system shall include, but not be limited to, a rigorous examination of construction material, processes, and operation, including testing of material and examination of manufacturer's certifications as required, to verify that work meets contract requirements and is performed in a competent manner.

(210-VI-NEH, January 2009) 94-2

4. Quality control personnel Method 1—Quality control activities shall be accomplished by competent personnel. A competent person is: One who is experienced and capable of identifying, evaluating, and documenting that materials and processes being used will result in work that complies with the contract; and, who has authority to take prompt action to remove, replace, or correct such work or products not in compliance. Off-site testing laboratories shall be certified or inspected by a nationally recognized entity. The Contractor shall submit to the Contracting Officer, for approval, laboratory certification or inspection information. The Contractor shall submit to the Contracting Officer, for approval, the names, qualifications, authorities, certifications, and availability of the competent personnel who will perform the quality control activities.

Method 2—Quality control activities shall be accomplished by competent personnel who are separate and apart from line supervision and who report directly to management. A competent person is one who is experienced and capable of identifying, evaluating, and documenting that material and processes being used will result in work that complies with the contract, and who has authorization to take prompt action to remove, replace, or correct such work or products not in compliance. Offsite testing laboratories shall be certified or inspected by a nationally recognized entity. The Contractor shall submit to the Contracting Officer, for approval, laboratory certification or inspection information. The contractor shall submit to the contracting officer, for approval, the names, qualifications, authorities, certifications, and availability of the competent personnel who will perform the quality control activities.

5. Post-award conference The contractor shall meet with the contracting officer before any work begins and discuss the contractor's quality control system. The contracting officer and the contractor shall develop a mutual understanding regarding the quality control system, including procedures for correcting quality control issues.

6. Records The contractor's quality control records shall document both acceptable and deficient features of the work and corrective actions taken. All records shall be on forms approved by the contracting officer, be legible, and be dated and signed by the competent person creating the record.

Unless otherwise specified in section 10 of this specification, records shall include:

a. Documentation of shop drawings including date submitted to and date approved by the contracting officer, results of examinations, any need for changes or modifications, manufacturer's recommendations and certifications, if any, and signature of the authorized examiner.

b. Documentation of material delivered including quantity, storage location, and results of quality control examinations and tests.

c. Type, number, date, time, and name of individual performing quality control activities.

d. The material or item inspected and tested, the location and extent of such material or item, and a description of conditions observed and test results obtained during the quality control activity.

e. The determination that the material or item met the contract provisions and documentation that the engineer was notified.

f. For deficient work, the nature of the defects, specifications not met, corrective action taken, and results of quality control activities on the corrected material or item.

(210-VI-NEH, January 2009) 94-3

7. Reporting results The results of contractor quality control inspections and tests shall be communicated to the engineer immediately upon completion of the inspection or test. Unless otherwise specified in section 10, the original plus one copy of all records, inspections, tests performed, and material testing reports shall be submitted to the engineer within one working day of completion. The original plus one copy of documentation of material delivered shall be submitted to the engineer before the material is used.

8. Access The contracting officer and the engineer shall be given free access to all testing equipment, facilities, sites, and related records for the duration of the contract.

9. Payment

Method 1—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds, after presentation by the contractor of invoices showing related costs and evidence of charges by suppliers, subcontractors, and others for furnishing supplies and work performed.

If the total of such payments is less than the lump sum contract price for this item, the remaining balance is included in the final contract payment. Payment of the lump sum contract price constitutes full compensation for completion of the work.

Payment is not made under this item for the purchase cost of material and equipment having a residual value.

Method 2—For items of work for which lump sum prices are established in the contract, payment is prorated and paid in equal amounts on each monthly estimate. The number of months used for prorating shall be the number estimated to complete the work. The final month's prorate amount is made with the final payment. Payment as described above constitutes full compensation for completion of the work.

Payment is not made under this item for the purchase cost of material and equipment having a residual value.

All methods—Compensation for any item of work described in the contract, but not listed in the bid schedule, is included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 10.

10. Items of work and construction details

NRCS –1/05/2019

TX – PILOT GROVE CREEK 64A REPAIR

94-4

10. Items of work and construction details

In section 3, Quality control system, Method 2 shall apply.

In section 4, Quality control personnel, Method 2 shall apply.

In section 9, Payment, Method 2 shall apply.

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 13, Contractor Quality Control

(1) This item shall consist of furnishing all equipment, tools, materials, and labor and performing all work to accomplish the work defined in section 1 of this specification.

(2) The burden of proof that work performed meets contract requirements rests upon the Contractor. Quality assurance inspections and tests by the Government are for the sole benefit of the Government. The use of such words as "as approved by the Engineer or Contracting Officer" and words of like import in the specifications or drawings which refer to approval by the Contracting Officer are considered to be a part of the Government's Quality Assurance program and do not relieve the Contractor in any part for the Contractor's Quality Control Responsibilities as specified.

(3) Quality Control is defined as a rigorous examination and inspection of construction materials, processes and operations to verify that the work being performed meets contract requirements and shall be performed by a qualified Inspector employed by or under contract to the Contractor.

(4) The Contractor's quality control system shall be approved and operational before commencement of work. The Contractor’s Quality Control Personnel shall submit to the on-site NRCS Inspector Daily Quality Control Reports, for each day the Contractor is on site performing work.

(5) Quality control tests shall be conducted in accordance with the standard test methods identified in the specifications. The Contractor shall provide all equipment required to perform all quality control tests. Testing equipment shall meet the requirements as specified by ASTM test methods and be properly calibrated and serviced.

(6) All mention of inspection or Inspector in (7) and (8) below is referring to work performed by the Contractor's Quality Control Personnel unless otherwise noted.

(7) The degree of quality control specified shall be defined as:

(a) Periodic review or inspection is defined as the intermittent presence of the Inspector to observe construction operations and/or perform tests and take measurements as needed to determine and document that the work being performed complies with the specifications.

(b) Full time inspection is defined as the full time presence of the Inspector to observe one or more construction operations and/or perform tests and take measurements at critical points in various operations to determine and document that the work being performed complies with the

94-5 specifications and to be available for consultation in case of emergency or changes in work conditions.

(c) Continuous inspection is defined as the continuous presence of the Inspector to observe one construction operation and/or perform tests and take measurements at critical points in the operation to determine and document that the work being performed complies with the specifications and to be immediately available for consultation in case of emergency or changes in work conditions.

(8) The Contractor's inspection system shall include the following items of work that will require the Contractor's quality control. Any item of work not listed below shall be performed or constructed as shown on the drawings and as specified in the construction and material specifications.

(a) The Contractor's inspection on all items not listed in (b) through (f) below shall consist of periodic review of those items to assure that all contract specifications are being met and that the items are being properly installed or carried out.

(b) Seeding, Sprigging, and Mulching - Quality control shall consist of determining that the vegetative materials supplied comply with the specifications; that the areas to be vegetated are properly prepared, smoothed and graded; and that sprigging is performed as specified. Full time inspection shall be required.

(c) Excavation - Quality control shall consist of full time inspection to determine that all excavation is being accomplished as specified and that the specified excavation has removed all required or unsuitable materials and that grades are properly documented. The Inspector shall determine that all materials selected for use in backfill of the specified works are free of undesirable materials and that all materials are placed in the designated waste, stockpile or fill areas.

(d) Lime-Treated Earthfill - Quality control shall consist of full time inspection of lime-treated earthfill placement. The Inspector shall select materials from the required excavations, stockpiles and/or borrow area(s) to insure the completed lime treated earthfills are constructed in accordance with the drawings and specifications.

The Inspector shall select and obtain representative samples of the materials and have moisture-density curves made (according to ASTM D-698 test procedures) of each Unified Soil Classification material to be placed in the specified earthfills. Moisture density curves shall be completed as necessary to provide data needed when lime-treated earthfill operations begin. A “One-Point Family of Curves Method” (hereafter referred to as the one point method) shall be employed to determine the optimum moisture and maximum density values for the lime-treated earthfill materials. A “One-Point Family of Curves Method” (hereafter referred to as the one point method) shall be employed to determine the optimum moisture and maximum density values for all lime-treated earthfill materials. The procedure for performing the one-point method is as follows:

94-6

(1) construct a family of curves using compaction test data compiled on soil samples tested in accordance with the procedure set forth in ASTM D-698, (2) make a one-point compaction test specimen from soil material representing the lime-treated earthfill material that is being placed, (3) plot the one-point moisture-density values, obtained from the test, on the family of curves, (4) using the curves above and below the plotted point as a guide, draw a new compaction curve through the plotted point, (5) use this curve as the control for the moisture and density of the material being placed. Unless otherwise approved by the Engineer, at least one one-point test shall be conducted for every three in-place moisture density tests that are taken.

More frequent tests shall be required if compaction requirements are not being obtained; if compaction requirements are not being met or if lime-treated earthfills are being placed in critical areas such as conduit and concrete backfills. In these instances, continuous inspection shall be required during all lime-treated earthfill placement to determine that foundation conditions are satisfactory; that the lime is properly incorporated into the earthfill materials and are free of undesirable materials; that proper compaction and moisture requirements are being maintained; and that hand and mechanical compaction are being accomplished as specified.

(e) Furnishing and Handling Lime, Quicklime - Quality control shall consist of continuous inspection during handling and processing the quicklime.

The Inspector shall assure that the proper amount and type of quicklime is delivered to the site. The Inspector shall ensure precautions are taken to protect workers from dangers associated with handling quicklime and to ensure the lime remains dry until applied and incorporated into the soil being treated. The Inspector shall ensure the specified amount of quicklime is uniformly applied to and incorporated into the proper volume of soil before processing. The Inspector shall also assure that the specified percentage of lime is mixed with the soil thoroughly. The Inspector shall select a representative sample of the soil lime mixture of not less than five pounds for submittal to a qualified geotechnical lab for Atterberg Limits and pH testing. If the Atterberg Limits test results in a Plasticity Index of 20 or less or the pH is 12.4 or more, no adjustment of the application rate of quicklime will be required. If nether of those criteria are met, the amount of quicklime shall be increased 1% upon approval of the Project Engineer and the soil lime mixture re-tested.

This sequence of testing and increases will continue until either one of the criteria have been met or the percentage change in the results have become insignificant. The final rate used shall be the application rate for the project.

(f) Site preparation – Quality control shall consist of full time inspection of all earthfill required under the bid item for Site Preparation. The Inspector shall select materials from the required excavations, stockpiles, and/or borrow area(s) to insure the completed earthfills and topsoil geometries and thicknesses are constructed in accordance with the drawings and specifications. The Inspector shall route the various materials to the proper zones and determine suitability of each type of

94-7 material for a particular zone. Quality control tests for moisture and density shall be required.

The Inspector shall select and obtain representative samples of the materials and have moisture-density curves made (according to ASTM D-698 test procedures) of each Unified Soil Classification material to be placed in the specified earthfills. Moisture density curves shall be completed as necessary to provide data needed when earthfill operations begin. A “One-Point Family of Curves Method” (hereafter referred to as

94-8 the one point method) shall be employed to determine the optimum moisture and maximum density values for all earthfill materials. A “One-Point Family of Curves Method” (hereafter referred to as the one point method) shall be employed to determine the optimum moisture and maximum density values for all earthfill materials. The procedure for performing the one-point method is as follows: (1) construct a family of curves using compaction test data compiled on soil samples tested in accordance with the procedure set forth in ASTM D-698, (2) make a one-point compaction test specimen from soil material representing the earthfill material that is being placed, (3) plot the one-point moisture-density values, obtained from the test, on the family of curves, (4) using the curves above and below the plotted point as a guide, draw a new compaction curve through the plotted point, (5) use this curve as the control for the moisture and density of the material being placed. Unless otherwise approved by the Engineer, at least one one-point test shall be conducted for every three in-place moisture density tests that are taken.

More frequent tests shall be required if compaction requirements are not being obtained; if compaction requirements are not being met or if earthfills are being placed in critical areas such as conduit and concrete backfills. In these instances, continuous inspection shall be required during all earthfill placement to determine that foundation conditions are satisfactory; that the earthfill materials are of the type selected for placement and are free of undesirable materials; that proper compaction and moisture requirements are being maintained; and that hand and mechanical compaction are being accomplished as specified.

(9) The skills, knowledge, abilities and experience needed by the Contractor's quality control personnel to perform the quality control shall be as follows:

(a) Must have the ability to maintain communications with the landowners, the Contracting Officer and the Contractor.

(b) Knowledge of cut and grade staking and earthwork installation.Knowledge of soils, including foundation conditions, density and classifications.

(c) Knowledge of sampling of soils and determination of density of in-place soils.

(d) Knowledge of working with Quicklime, lime processing and lime-treated earthfill.

(e) When applicable, must have knowledge of acceptable moisture-density test methods and the ability to satisfactorily perform the tests.

(f) Have the ability to interpret survey notes and to prepare quantity computations.

(g) Have the ability to maintain adequate files and records of construction inspection work.

(h) Have the ability to interpret construction drawings and specifications.

94-9

(i) Must have knowledge of the United Soil Classification System and the ability to interpret soil classification requirements from the construction drawings.

(j) Quality control personnel shall also be responsible for maintaining a record of progress with photographs. Construction activities shall be documented with 3 megapixels or greater digital photography in a JPEG file format. Photographs of daily construction work, problems encountered, and unique construction practices shall be taken to insure full coverage of all work performed. The photographs shall be numbered, date and time imprinted and indexed with documentation explaining construction activities shown, and must be submitted with the request for final payment.

Specification 94 - Contractor Quality Control.pdf
1. Scope
1. Scope
2. Equipment and materials
2. Equipment and materials
3. Quality control system
3. Quality control system
4. Quality control personnel
4. Quality control personnel
5. Post-award conference
5. Post-award conference
6. Records
6. Records
7. Reporting results
7. Reporting results
8. Access
8. Access
9. Payment
9. Payment
10. Items of work and construction details
10. Items of work and construction details