S01 Questions and Answers 12FPC125Q0023_ACEP-WRE Wetland Seeding_NRCS_IL.pdf

PDF 45 KB Posted

Attached to
ACEP-WRE Emergent Wetland Seeding for NRCS Illinois State Office (Clark County)
Solicitation number
12FPC125Q0023
Issued by

About this file

This document is a Questions and Answers (Q&A) file for the ACEP-WRE Emergent Wetland Seeding solicitation (12FPC125Q0023) issued by the Natural Resources Conservation Service (NRCS) Illinois State Office for Clark County. The Q&A clarifies key details about the contract, including that it is a new contract with a 45-day performance period, requires contractor-driven site preparation and seeding (with hydroseeding acceptable), and involves emergent wetland seeding. Quality control will be the contractor's responsibility, with NRCS conducting site-by-site inspections, and weather considerations have been factored into the performance timeline. The solicitation specifies that seed rates are detailed in Attachment A, alternative seeds may be necessary as determined by the Contracting Officer, and specific requirements include seed selection, site preparation, and completion criteria.

The solicitation is a 100% small business set-aside under NAICS code 115112 with a $9.5M size standard, anticipating a firm-fixed price purchase order awarded on a Lowest Price Technically Acceptable (LPTA) basis. Contractors must have an active SAM.gov account with completed REPs and CERTs. Critical dates include a question submission deadline of April 8, 2025 (5:00 PM EST) and quote submission deadline of April 15, 2025 (5:00 PM EST), with quotes to be emailed to Ambrea Harris and Sharla Goforth. Fertilizer and mulching are not expected, and contractors will need to follow the seeding specifications provided in the attachment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question # Answer

1 This is a new contract.

2 N/A 3 The period of performance is 45 days from the receipt of the Purchase Order.

4 Contractor 5 The scope of work is detailed in Attachment A - Specifications of the solicitation.

6 Contractor will need to determine best method of site preparation and seeding. Hydroseeding is acceptable.

7 NRCS

8 See question #3 9 Fertilizer is NOT expected.

10 Mulching is NOT expected.

11 Seed rates per acre have been added to seeding list in Attachment A - Specifications.

12 See seeding list in Attachment A - Specifications.

13 Alternative or replacement seed or species maybe necessary as determined by CO.

QC will be required by the contractor. NRCS inspections on a site by site basis will occur. If a site has been determined as planted per specifications by NRCS it will be considered complete. Weather has been factored into the period of performance. If extreme weather events occur any modifications to the period of performance will be made by the CO.

Are the seeds provided by the contractor or the government?

Natural Resources Conservation Service (NRCS) ACEP-WRE Emergent Wetland Seeding

Illinois State Office Solicitation No. 12FPC125Q0023

Clark County Question/Comment/Clarification

Is this a brand new contract OR is (was) an incumbent performing these services?

If there is an incumbent, could you please provide the current / previous contract number?

What is the performance period?

Is it possible for NRCS to provide the expected seed type to contractor for this wetland scope of work?

What is the required grass type to be planted?

Will there be a contingent plan or alternative grass type for this scope if Prairie Cord Grass as shown to be used from the list provided is not available?

How will NRCS determine replant and or quality control in the event of inclement weather during work in progress?

Is there a Scope of Work (SOW/PWS)?

Will this scope of work require Hydroseeding or conventional tillage with mechanical seeding?

Who is responsible for landowner notification prior to property access?

What is the expected start and completion date?

What is the expectation of fertilizer and or not needed?

What is the expectation and form of straw or mulch overlay for seed protection and germination or not needed?