TIME CALCULATIONS
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Falconite_EoF_design.pdf | ||
| Guthrie_and_Falconite_EoF_bidsheet.pdf | ||
| 12FPC119Q0029_Guthrie_and_Falconite.pdf | ||
| Guthrie_and_Falconite_EoF_Specs.pdf | ||
| Guthrie_eof_design.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Time The period of performance is calculated as follows, with Total Calendar Days rounded up to nearest day.
Site 1: Guthrie Length of Work Day: 8 hrs
Item No. Work/Material Quantity Unit
Rate of Completio n (units/hr)
Total Time for Completion (hrs) Days
Days Coincident w/other items
Days Allowed for Completion
1 Clearing 0.5 acres 1 0.5 0.1 0.1 2 Seeding and Mulching 0.32 acres 0.25 1.28 0.2 0.2 3 Mobilization and Demobilization 1 Job 1.0 4 Diversion 1 95 CY 28 3.39 0.5 0.5 4 Diversion 2 11.6 CY 28 0.41 0.1 0.1 4 Diversion 3 129.3 CY 28 4.62 0.6 0.6
Total Days: 2.5 Days in Work Week: 5
Calendar Days: 2.5 Estimated inclimate weather days during POP: 2
Total Calendar Days: 5
The units and rate of completion (units/hr) above are base upon past projects completed under federal contract.
Site 2: Falconite Length of Work Day: 8 hrs
Item No. Work/Material Quantity Unit
Rate of Completio n (units/hr)
Total Time for Completion (hrs) Days
Days Coincident w/other items
Days Allowed for Completion
5 Clearing 0.5 acres 1 0.5 0.1 0.1 6 Seeding and Mulching 0.1 acres 0.25 0.4 0.1 0.1 7 Mobilization and Demobilization 1 Job 1.0 8 Diversion 1 37.2 CY 28 1.3 0.2 0.2 8 Diversion 2 43.9 CY 28 1.6 0.2 0.2 8 Diversion 3 4.5 CY 28 0.2 0.1 0.1 8 Diversion 4 23.8 CY 28 0.9 0.2 0.2 9 GSS: Rock Chute 50 Ton 12.5 4.0 0.5 0.5
10 Stream Crossing 77 ton 12.5 6.2 0.8 0.8 Total Days: 3.2
Days in Work Week: 5 Calendar Days: 3.2
Estimated inclimate weather days during POP: 2 Total Calendar Days: 6
The units and rate of completion (units/hr) above are base upon past projects completed under federal contract.
Weekends (Saturdays and Sundays) 4 Holidays 0
Total Calendar Days Guthrie and Falconite EoF: 15
Performance Time