TIME CALCULATIONS

View the file

Other files for this federal contract opportunity

Other files attached to WRP - Restoration Improvements, newest first.
File Type Posted
Falconite_EoF_design.pdf PDF
Guthrie_and_Falconite_EoF_bidsheet.pdf PDF
12FPC119Q0029_Guthrie_and_Falconite.pdf PDF
Guthrie_and_Falconite_EoF_Specs.pdf PDF
Guthrie_eof_design.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Time The period of performance is calculated as follows, with Total Calendar Days rounded up to nearest day.

Site 1: Guthrie Length of Work Day: 8 hrs

Item No. Work/Material Quantity Unit

Rate of Completio n (units/hr)

Total Time for Completion (hrs) Days

Days Coincident w/other items

Days Allowed for Completion

1 Clearing 0.5 acres 1 0.5 0.1 0.1 2 Seeding and Mulching 0.32 acres 0.25 1.28 0.2 0.2 3 Mobilization and Demobilization 1 Job 1.0 4 Diversion 1 95 CY 28 3.39 0.5 0.5 4 Diversion 2 11.6 CY 28 0.41 0.1 0.1 4 Diversion 3 129.3 CY 28 4.62 0.6 0.6

Total Days: 2.5 Days in Work Week: 5

Calendar Days: 2.5 Estimated inclimate weather days during POP: 2

Total Calendar Days: 5

The units and rate of completion (units/hr) above are base upon past projects completed under federal contract.

Site 2: Falconite Length of Work Day: 8 hrs

Item No. Work/Material Quantity Unit

Rate of Completio n (units/hr)

Total Time for Completion (hrs) Days

Days Coincident w/other items

Days Allowed for Completion

5 Clearing 0.5 acres 1 0.5 0.1 0.1 6 Seeding and Mulching 0.1 acres 0.25 0.4 0.1 0.1 7 Mobilization and Demobilization 1 Job 1.0 8 Diversion 1 37.2 CY 28 1.3 0.2 0.2 8 Diversion 2 43.9 CY 28 1.6 0.2 0.2 8 Diversion 3 4.5 CY 28 0.2 0.1 0.1 8 Diversion 4 23.8 CY 28 0.9 0.2 0.2 9 GSS: Rock Chute 50 Ton 12.5 4.0 0.5 0.5

10 Stream Crossing 77 ton 12.5 6.2 0.8 0.8 Total Days: 3.2

Days in Work Week: 5 Calendar Days: 3.2

Estimated inclimate weather days during POP: 2 Total Calendar Days: 6

The units and rate of completion (units/hr) above are base upon past projects completed under federal contract.

Weekends (Saturdays and Sundays) 4 Holidays 0

Total Calendar Days Guthrie and Falconite EoF: 15

Performance Time