Standard Specifications

881 MOBILIZATION (2/94)

1. DESCRIPTION

This Section consists of one or more mobilizations of personnel, equipment, supplies, and incidentals to the project site, or sites listed in the Schedule of Items.

2. MEASUREMENT

When the contract establishes separate work periods within the contract time any additional mobilization included as a Bid Item will be retained until the actual work period.

3. PAYMENT

a. Progress payments will be made on the basis of the Bid Items contained in the Schedule of Items as follows:

1. When five (5) percent of the estimated contract amount in the work period is earned, fifty (50) percent of the amount of mobilization will be paid.

2. When twenty-five (25) percent of the estimated contract amount in the work period is earned, one hundred (100) percent of the amount for mobilization will be paid.

3. The total sum of all payments under this Section shall not exceed 10% of the total contract amount.

4. The contract amount for mobilization shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals involved in mobilization.

b. Payment will be made under:

Pay Item Pay Unit

881(1) Mobilization Each