QUESTIONS - Responses.pdf
PDF 95 KB Posted
- Solicitation number
- 12905B24Q0218
About this file
This document is a set of Questions and Responses related to a Request for Quotation (RFQ) for Evaporation Pond Maintenance and Cleaning in Maricopa, AZ. The RFQ, identified as Solicitation Number 12905B24Q0218, is a 100% Small Business Set-Aside with a required 30-day completion period after award. The RFQ includes a Statement of Work and requires quotes to be submitted by August 15, 2024. Key details include: the client agency is the USDA Agricultural Research Service's Pacific West Area, the project involves cleaning and maintaining an evaporation pond, water is available on-site, and the pond contents have been tested and approved for landfill disposal. A site visit is scheduled for August 7, 2024. Overall, this document provides responses to questions regarding the contract requirements, logistics, and timeline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Additional Information.docx | DOCX document | |
| Questions - Answers Adendum w-Photo.pdf | ||
| Attachment III - Contractor RFI FORM.pdf | ||
| Attachment IV - Past Performance Questionnaire (PPQ).doc | DOC document | |
| Fraud Warning to Contractors.pdf | ||
| 12905B24Q0218 with T-n-Cs and Attach I - II.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS/REPONSES
RFQ #12905B24Q0218
Evaporation Pond Maintenance and Cleaning Maricopa AZ
1- What date is award of RFQ anticipated? for the 30-day completion requirement.
Award date is anticipated within a week of the RFP closure date.
2- Does ALARC own the land 2200' north of settling pond? if so can material be dumped there?
NO, material needs to be sent to the landfill for documentation.
3- Has settling pond been probed for sludge depth?
NO the pond is empty except for sediment.
4- Is potable/irrigation water available for contractor at ALARC facility, up to 2000gal/day?
Water is available (approximately 350' from the water to the pond).
5- Will ALARC dewater pond prior to contractor work start date?
The pond is dry.
6- Does ALARC have a anticipated magnitude for project?
This is a service requirement, not a construction requirement therefore not subject to FAR
36.204 requiring a published magnitude.
7- Have contents of pond been tested for hazardous chemicals/fertilizer residue/pesticides?
YES, Results sent to Arizona Department of Environmental Quality, they responded that the material can be sent to the landfill.
8- Does ALARC know when last pond liner inspection was completed?
It has never been inspected.