United States Department of Agriculture Agricultural Research Service
TECHNICAL STATEMENT OF WORK
REPAINT of BUILDINGS 21, 23, 28C, 40, 41, 43, 44, 45, 47, 116, 117, 118, and 119.
USDA ARS SALINAS, CA.
SALINAS CROP IMPROVEMENT AND PROTECTION
RESEARCH BUILDINGS
DATE: 19 July 2021
STATEMENT OF WORK
TABLE OF CONTENTS
1.0 Project Information
2.0 Project Contact Persons
3.0 Scope of Services
4.0 Technical Project Requirements
5.0 Background and Site Description
6.0 Bid Schedule
7.0 Base Item
8.0 Government Furnished Equipment
9.0 General Requirements
1.0 Project Information:
A. Project Number: TBD
B. Project Title: REPAINT of BUILDINGS 21, 23, 28C, 40, 41, 43, 44, 45, 47, 116, 117, 118, and 119.
C. Project Location: 1636 E. Alisal St. Salinas Ca. 93905
2.0 Project Contact Persons:
A. RESEARCH PROGRAM REPRESENTATIVES (RPR):
Dr. William Wintermantel
USDA, ARS, PWA
Crop Improvement and Protection Research Salinas, California 93905 Phone: (831) 755-2824 Email: Bill.Wintermantel@usda.gov
B. LOCATION ADMINISTRATIVE OFFICER (LAO):
Janet Krugle
USDA, ARS, PWA
Crop Improvement and Protection Research
Salinas, California 93905 Phone: (831) 755-2812
Email: Janet.Krugle@usda.gov
C. MAINTENANCE CONTACT:
Doug Mesman
USDA, ARS, PWA
Crop Improvement and Protection Research Salinas, California Phone: (831) 755-2816 Email: Douglas.Mesman@usda.gov
D. MAINTENANCE CONTACT:
John Mosher
USDA, ARS, PWA
Crop Improvement and Protection Research Salinas, California Phone: (831) 755-2816 Email: John.Mosher@usda.gov
3.0 Scope of Services:
The Contractor shall provide all professional services necessary for the accomplishment of the contract project and such required services shall be in accordance with requirements as described herein.
A. The Contractor shall provide services for the following tasks marked by an “X”:
[X] Provide a cost proposal to complete the project as per project requirements.
[X] Provide and install all material to complete the project as per project requirements.
mailto:Bill.Wintermantel@usda.gov
4.0 Technical Project Requirements:
The Contractor shall furnish a cost proposal to provide services for all of the following requirements. Repaint and repair the outside of buildings 21, 23, 28C, 40, 41, 43, 44, 45, 47, 116, 117, 118, and 119. The Contractor will work with site personnel to ensure project is accomplished in a timely manner.
A. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e.: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
B. This project falls under the DAVIS BACON Wage Act.
5.0 Background & Site Description:
Buildings 21, 23, 28C, 40, 41, 43, 44, 45, 47, 116, 117, 118, and 119 are part of the Crop Improvement and Protection Research USDA ARS facility in Salinas CA. The buildings vary in material type and are of different sizes and dimensions. The approximated paintable exterior surfaces for each building are as follows:
A. Building 21 4800 ft2 B. Building 23 2550 ft2 C. Building 28C 1750 ft2 D. Building 40 4000 ft2 E. Building 41 2100 ft2 F. Building 43 2000 ft2 G. Building 44 4000 ft2 H. Building 45 4000 ft2 I. Building 47 4000 ft2 J. Building 116 1900 ft2 K. Building 117 1900 ft2 L. Building 118 1350 ft2 M. Building 119 1600 ft2 N. Remove exterior trim and gutters as needed and paint those items as well. Reinstall trim and gutters. All exterior surfaces besides the roof and windows will require painting.
6.0 Bid Schedule: Base Bid only, no Add Options.
7.0 Base Item
A. Properly prepare all surfaces of building before repair/painting
1. Ensure all surfaces are clean, dry, sound, and free of dirt, grease, oil, and other contaminants that might interfere with adhesion of the paint.
B. Repair all unsound areas including but not limited to blisters, delaminating, deterioration, excessive moisture content, excessive UV exposure, edge cracks, areas of ponding, etc.
1. Around all non-foamed surfaces (windows, chimneys, vents, lights etc..) insure waterproof seal between roofing material
2. Reinforce and coat all damaged areas using brush-on acrylic caulk and appropriate mesh fabric
3. All cracks, splits, voids, or holes shall be filled and leveled using brush-on acrylic caulk and appropriate mesh fabric
C. Reseal and topcoat exterior surface according to manufactures guidelines
1. Apply primer as needed
2. Apply 2 coats of the proper acrylic based semi-gloss paint for the building material.
D. Show color samples to LAO and RPR for approval E. Ensure weather tight seal between siding and man doors, roll up doors, and foam covering.
8.0 Government Furnished Equipment\Services
A. The Government does not anticipate the need in this project, but the Government will be available to assist with the identification of possible other underground utilities but does not guarantee location of all utilities.
B. The Government will furnish a reasonable amount of electricity and water.
9.0 General Requirements:
A. Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
B. Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disturbances that might jeopardize on-going operations and research. Owner reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Owner prior to starting demolition operations. Contractor shall legally dispose of any materials removed that will not be retained.
C. Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the LOA for immediate resolution.
D. Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the LOA for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government.
Contractor is responsible for any costs incurred for equipment ordered without prior approval.
E. Quality Control: The work performed under this contract shall be subject to continuous audit by the LAO. Quality control is the exclusive responsibility of the Contractor.
F. Protection of Work and Property/Safety Requirements:
1. Contractor shall furnish a Site Specific Safety Plan (SSSP) 10 days after contract award.
SSSP shall be approved by the Government before construction work commences.
2. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the LAO.
3. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
4. Contractor is responsible for verifying location of any underground utility and is responsible for any damaged caused to such utilities.
G. Temporary Facilities:
1. Temporary utilities (water and electricity) may be furnished to the Contractor by the
Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.
2. Should the Contractor require any power or utility shutdowns during construction, the Contractor shall obtain approval for such shutdown from the LAO seven working days prior to the need.
H. Materials and Equipment:
1. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
2. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the LOA.
3. Government will not furnish any labor or equipment to unload or move materials or supplies.
I. Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the LOA.
J. Warranty:
1. Submit data concerning the standard one year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.
2. Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.
K. Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO FINAL PAYMENT (other documents may also be required):
1. General contractors minimum one (1) year warranty on work.
2. Operation and Maintenance Data
3. Release of liens.
4. Final Invoice
L. PROJECT SCHEDULE: The Contract time for this project is 90 calendar days.