Project Specifications

View the file

Other files

File Type Posted
12850818R0009_Amend_01.pdf PDF
12850818R0009_Final.pdf PDF
Memo_for_Solicitation.pdf PDF
CO23.pdf PDF
MBRTB_AOP_2018_DRAWINGS.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Road 500 Mile Post 1.69 & Road 550 Mile Post 4.32 Crossing Replacements Forest Service Supplemental Specifications (FSSS) to FP-14

Medicine Bow-Routt National Forest & Thunder Basin National Grassland

Hahns Peak-Bears Ears Ranger District

Road 500 Mile Post 1.69 Crossing

Road 550 Mile Post 4.32 Crossing

Table of Contents Preface

101 - Terms¸ Format¸ and Definitions

101.01 Meaning of Terms

101.03 Abbreviations

101.04 Definitions

102 - Bid¸ Award¸ and Execution of Contract

Delete Section 102

103 - Scope of Work

Delete Subsections 103.02, 103.03, 103.04, 103.05

104 - Control of Work

Delete Subsections 104.01, 104.02, 104.04

104.06 Use of Roads by Contractor

105 - Control of Material

105.02(a) Government-provided sources

105.02(c) Contractor-located sources

106 - Acceptance of Work

106.01 Conformity with Contract Requirements

106.02 Visual Inspection

107 - Legal Relations and Responsibility to the Public

Delete Subsection 107.05

108 - Prosecution and Progress

Delete Section 108

109 - Measurement and Payment

Delete Subsections 109.06, 109.07, 109.08, 109.09

109.02 Measurement Terms and Definitions

153 - Contractor Quality Control

153.02 Qualifications

153.07 Records and control charts

155 - Schedules for Construction Contracts

Delete Section 155

156 - Public Traffic

Section 156. – PUBLIC TRAFIC

157 - Soil Erosion and Sediment Control

157.04 General

201 - Clearing and Grubbing

201.04(d) Clearing

201.06 Disposal

203 - Removal of Structures and Obstructions

203.05 Disposing of Material

208 - Structure Excavation and Backfill for Selected Major Structures

208.07 Dewatering

209 - Structure Excavation and Backfill

209.07 Dewatering

209.10 Compacting

302 - Minor Crushed Aggregate

302.04 Placing Crushed Aggregate

603 - Structural Plate Structures

603.03 General

603.04 Erecting

648 - Stream Simulation

Section 648. — STREAM SIMULATION

680 - Temporary Detour Road

Section 680. — Temporary Detour Road

705 - Rock

705.08 Streambed Simulation Rock

Preface Preface_wo_03_19_2018

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.

101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016

Add the following paragraph to Subsection 101.01:

101.01 Meaning of Terms.

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_National_11_9_2016

Add the following to Subsection 101.03:

101.03 Abbreviations.

(a) Acronyms.

AGAR — Agriculture Acquisition Regulations

AFPA — American Forest and Paper Association

FSAR — Forest Service Acquisition Regulations

MSHA — Mine Safety and Health Administration

NESC — National Electrical Safety Code

WCLIB — West Coast Lumber Inspection Bureau

(f) Miscellaneous unit abbreviations.

MP — milepost location ppm — parts per million volume

STA station location

101.04_National_11_9_2016

Make the following changes to Subsection 101.04:

101.04 Definitions.

Delete these definitions and replace the following:

Bid Schedule — The Schedule of Items.

Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.

Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.

Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.

Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.

Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.

Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.

Add the following definitions:

Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line — A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road — Temporary construction access built along the route of the project.

Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.

Utilization Standards — The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

Page intentionally left blank.

102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016

Delete Section 102 in its entirety.

Delete Section 102.

103 - Scope of Work 103.00_National_11_9_2016

Delete all of Section 103 except Subsection 103.01 Intent of Contract.

Delete Subsections 103.02, 103.03, 103.04, 103.05.

104 - Control of Work 104.00_National_11_9_2016

Delete Subsections 104.01, 104.02, and 104.04.

Delete Subsections 104.01, 104.02, 104.04.

104.06_National_11_9_2016

Add the following to Subsection 104.06:

104.06 Use of Roads by Contractor.

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material 105.02_National_11_1_2016

Add the following to Subsection 105.02(a):

105.02(a) Government-provided sources.

Government-provided sources for this project are identified as follows:

(1) Government-provided mandatory sources.

Pay Item Description Material source number or name

302.01 Footing bedding material &

road surface aggregate compaction method 1 (Subsections 204.11(a)(1) and 209.10(a)(1))

550 Road Pit at the intersection of roads 500 and 550.

(2) Riprap Source- It is anticipated that existing inlet and outlet armoring on both sites will provide sufficient material.

(3) Backfill and Unclassified fill Borrow Source- Suitable native material shall be used for all backfill, and unclassified fill.

(4) Stream Simulation and Rock Feature Material- Suitable material shall be sorted from excavated material.

(5) Waste Site- A waste site for excess and unsuitable material will be located at the aggregate material source, or onsite as designated by the C.O. This site is to be utilized for the disposal of unsuitable or excess excavated material only. All other materials designated for removal must be disposed of in accordance with all rules and regulations off of Forest Service land.

105.02_National_11_1_2016

Add the following to Subsection 105.02c:

105.02(c) Contractor-located sources.

All material (e.g., soil, gravel, sand, borrow, aggregate, etc.) transported onto National Forest System land or incorporated into the work shall be weed-free. The Contracting Officer may request written documentation of methods used to determine the weed-free status of any and all materials furnished by the contractor. Contractor-provided expertise and methods to establish weed-free status must be appropriate for the weeds of concern in the local area.

Page intentionally left blank.

106 - Acceptance of Work 106.01_National_7_18_2017

Delete Subsection 106.01 and replace with the following:

106.01 Conformity with Contract Requirements.

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.

The Government may inspect, sample, or test all work at any time before final acceptance of the project.

When the Government tests work, copies of test reports are furnished to the Contractor upon request.

Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive.

The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.

Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work;

providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

1. Sampling method;

2. Number of samples;

3. Sample transport;

4. Test procedures;

5. Testing laboratories;

6. Reporting;

7. Estimated time and costs; and

8. Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

1. Have the work accepted at a reduced price; or

2. Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.02_National_11_9_2016

Delete Subsection 106.02 and replace with the following:

106.02 Visual Inspection.

Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.

107 - Legal Relations and Responsibility to the Public 107.05_National_7_18_2017

Delete Subsection 107.05.

Delete Subsection 107.05.

108 - Prosecution and Progress 108.00_National_11_9_2016

Delete Section 108 in its entirety.

Delete Section 108.

109 - Measurement and Payment 109.00_National_11_9_2016

Delete Subsections 109.06, 109.07, 109.08, and 109.09:

Delete Subsections 109.06, 109.07, 109.08, 109.09.

109.02_National_11_9_2016

Add the following sentence to Subsection 109.02(b):

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

153 - Contractor Quality Control 153.02_National_11_1_2016

Delete Subsection 153.02 and replace with the following:

153.02 Qualifications.

Submit the following for approval with the quality control plan:

(a) Quality control manager (QCM). Furnish a QCM who has at least 2 years’ experience in construction, inspector, quality control and material testing on construction projects of similar type and scope.

153.07_National_11_1_2016

Delete Subsection 153.07 and replace with the following:

153.07 Records and control charts.

Maintain complete testing and inspection records by pay item number and make them accessible to the

CO.

155 - Schedules for Construction Contracts 155.00_National_11_9_2016

Delete Section 155 in its entirety.

Delete Section 155.

156 - Public Traffic 156.00_National_11_4_2016

Delete Section 156 in its entirety and replace with the following:

Section 156. – PUBLIC TRAFFIC Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Construction sign panels 633

Traffic Signing and Marking Material 718

Concrete Barriers and Precast Guardwalls 618

Temporary plastic fence 710.11

Construction Requirements

156.03 General. Accommodate traffic according to MUTCD, approved traffic control plan and this section. Perform work in a manner that ensures safety and convenience of the public. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Accommodate public traffic on roads adjacent to and within the project until the project is accepted according to Subsection 106.07(b).

Submit traffic control plan at least 30 days prior to intended use. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved.

Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM 7100-15. All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.

Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.

Table 156-1 Temporary Road Closures

Road Number

From Terminus

To Terminus

Maximum Consecutive Days of Closure

Minimum Consecutive Days Open

550 MP 4.1 MP 7.3 45 NA

* An alternate route via road 503.1 is available from CR 129 to Road 550 North of the road 550 project.

*A temporary detour road shall be constructed to provide public and timber sale traffic to pass through the road 500 project anytime the 500 road is not passable.

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Payment for contract work is provided indirectly. See Subsection 109.05.

157 - Soil Erosion and Sediment Control 157.04_National_11_1_2016

Delete Subsection 157.04 and replace with the following:

157.04 General.

Thirty (30) days prior to the start of construction, submit a written De-watering and Soil Erosion and Sediment Control Plan according to subsection 104.03 with all necessary permits that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control without approval.

When erosion control measures are not functioning as intended, immediately take corrective action to eliminate or minimize pollutants in storm water discharges from the project.

201 - Clearing and Grubbing

201.02 Material:

Delete Tree wound dressing material reference.

201.03 General:

Delete the last sentence.

201.04_Forest_10_30_2017

Delete and replace Subsection 201.04(d) with the following:

201.04(d) Clearing.

(d) Trim tree branches that extend over the road surface and shoulders to attain a clear height of < 14 > feet. Trim tree limbs as near flush with the trunk as practicable.

201.04 Clearing.

Add the following:

(e) Do not cut vegetation less than 3 feet in height and less than 3 inches in diameter that is within the clearing limits but beyond the roadway and not in a decking area and that does not interfere with sight distance along the road unless otherwise designated.

201.06_National_2_22_2018

Delete the first sentence of Subsection 201.06 and replace the following:

201.06 Disposal.

Merchantable timber is Government property.

203 - Removal of Structures and Obstructions 203.05_National_11_8_2016

Add the following to Subsection 203.05:

203.05 Disposing of Material.

(f) Scattering. Scatter construction slash in designated areas without damaging trees. Limb all logs.

Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations. When scattering for erosion control, place construction slash as flat as practicable on the completed slope.

(i) Decking. Remove brush from designated log deck areas. Limb and top logs.

Logs not meeting the Utilization Standards described in Subsection 201.04(c) shall be cut to lengths less than 30 feet and decked in designated log deck location.

Merchantable timber not associated with an existing timber sale shall be cut to length meeting the Utilization Standards described in Subsection 201.04(c).

Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.

208 - Structure Excavation and Backfill for Selected Major Structures

208.07_National_11_8_2016

Add the following to Subsection 208.07:

208.07 Dewatering.

Construct diversions according to Subsection 157.10 Diversions. Submit dewatering plans according to Subsection 104.03.

209 - Structure Excavation and Backfill 209.07_Forest_10_31_2017

209.07 Dewatering.

Add the following:

Do not pump water from foundation excavations directly into live streams or marine waters. Pump water into settling areas as specified in the contract.

209.10_National_7_17_2017

Delete Subsection 209.10 and replace with the following:

209.10 Compacting.

Compact the embankment using one of the following methods as specified.

(a) Compaction Method 1. Use AASHTO T 27 to determine the quantity of material retained on a No. 4 (4.75-millimeter) sieve. Compact as follows:

(1) More than 80 percent retained on a No. 4 (4.75-millimeter) sieve. Adjust the moisture content to a level suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Use compression-type rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet (1 meter) per second. Compact each layer of material full width with one of the following and until there is no visible evidence of further consolidation:

(a) Four roller passes of a vibratory roller having a minimum dynamic force of 40,000 pounds (180 kilonewtons) impact per vibration and a minimum frequency of 1000 vibrations per minute;

(b) Eight roller passes of a 20-ton (20-metric ton) compression-type roller; or

(c) Eight roller passes of a vibratory roller having a minimum dynamic force of 30,000 pounds (130 kilonewtons) impact per vibration and a minimum frequency of 1000 vibrations per minute.

Increase the compactive effort for layers deeper than 12 inches (300 millimeters) as follows:

• For each additional 6 inches (150 millimeters) or fraction thereof, increase the number of roller passes in Subsection 209.10(a)(1)(a), by four passes; or

• For each additional 6 inches (150 millimeters) or fraction thereof, increase the number of roller passes in Subsection 209.10(a)(1)(b) and (c), by eight passes.

(2) 50 to 80 percent retained on a No. 4 (4.75-millimeter) sieve. Classify the material according to AASHTO M 145. Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content. Use AASHTO T 99 to determine the optimum moisture content of the portion of the material passing a No. 4 (4.75-millimeter) sieve. Multiply this number by the percentage of material passing a No. 4 (4.75-millimeter) sieve, and add 2 percent to determine the optimum moisture content of the material.

Use nonvibratory rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet(1 meter) per second. Compact each layer of material full width according to Subsection 209.10(a)(1).

(3) Less than 50 percent retained on a No. 4 (4.75-millimeter) sieve. Classify the material according to AASHTO M 145. For material classified A-1 or A-2-4, determine the maximum density according to AASHTO T 99, Method C..

Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content.

Use compression-type or vibratory rollers. Compact each layer of material full width to at least 95 percent of the maximum density. Determine the in-place density and moisture content according to AASHTO T 310 or other approved test procedures. When required, use AASHTO T 224 to correct for coarse particles.

(b) Compaction Method 2. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Operate roller compaction equipment over the full width of each layer until there is no visible evidence of further consolidation or, if when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes. Use compression-type rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet (1 meter) per second. Ensure rollers meet the following requirements:

(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than 250 pounds per inch (4.5 kilogram/millimeter) of width of the compression roll or rolls.

(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum dynamic force of 30,000 pounds (130 kilonewtons) impact per vibration, specifically designed to compact the material on which it is used.

(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi (550 Kilopascals).

(4) Sheepsfoot, tamping, or grid rollers capable of exerting a force of 250 pounds per inch (4.5 kilogram/millimeter) of width of roller drum.

(c) Compaction Method 3. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Operate hauling and spreading equipment uniformly over the full width of each layer until there is no visible evidence of further consolidation. Make at least three complete passes.

(d) Compaction Method 4. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Operate hauling and spreading equipment uniformly over the full width of each layer.

(e) Compaction Method 5. Adjust the moisture content of the material to a moisture content suitable for compaction. Compact the complete surface with a bucket of an excavator larger than 39,000 pounds (18 metric ton) Gross Vehicle Weight using a minimum of three blows.

Overlap compaction by ½ width of bucket.

(f) Compaction Method 6. Adjust the moisture content of the material to a moisture content suitable for compaction. Compact using an approved mechanical tamper for a minimum of three complete passes.

When compacting with rollers or hauling and spreading equipment is not practical, use approved mechanical tampers for a minimum of three complete passes.

302 - Minor Crushed Aggregate 302.04_National_7_18_2017

Add the following to Subsection 302.04 and 302.04(a)

302.04 Placing Crushed Aggregate.

Written approval of the surface is required before placing aggregate.

(a) Roadway aggregate.

For pit run or grid-rolled material, furnish material smaller than the maximum size, no gradation will be required otherwise. After processing on the road, remove all oversize material from the road and dispose as directed by the CO.

603 - Structural Plate Structures 603.00_National_11_8_2016

Add the following to Subsection 603.03.

603.03 General.

Submit design drawings and details with supporting calculations according to Subsection 104.03.

Make the following changes to Subsection 603.04.

603.04 Erecting.

Add to the third paragraph:

Torque all bolts before beginning the backfill.

Delete the seventh paragraph and substitute with the following:

Torque steel bolts and aluminum bolts on 0.1-inch thick and heavier aluminum plates to at least 115 foot-pounds, and a maximum of 130 foot-pounds.

Delete the first sentence of the eighth paragraph and substitute with the following:

Assemble multi-plate structures according to manufacturer’s instructions and in conformance with parts

(a) thru (e).

648 - Stream Simulation 648.00_National_7_18_2017

Add Section 648:

Section 648. — STREAM SIMULATION

Description

648.01 This work consists of placing rock and fill to simulate a natural streambed, profile and cross section though road stream crossings. The placement of channel rock for: fish rest stop, rock bands, rock weirs, stream bank rocks, and other in stream rock structures, is included within this specification.

Material

648.02 Conform to the following Subsections.

Backfill Material 704.03

Stream Bed Simulation Material 705.08

Channel Rock 705.08

648.03 General. Place streambed simulation material on a prepared surface to form a well-graded, low permeability mass, similar in appearance and texture to the natural streambed. Do not drive metal track or rubber tired equipment directly on metal or concrete structure surfaces.

648.04 Placed Streambed Simulation Material and Channel Rock.

(a) Method A, Machine Placed. Place stream simulation material in one or more layers with a layer depth not exceeding 1 ½ times the maximum dimension of stream simulation rock. Place stream simulation material by methods that do not cause segregation or damage to the prepared surface. Place or rearrange individual rocks by mechanical methods to obtain a compact low permeability mass matching streambed simulation details. Fill voids before placing the next lift and compact each layer until there is no visible evidence of further consolidation. Place channel rock, rock bands, rock weirs, stream bank rock, and other in stream rock structures as designated.

(b) Method B, End Dumped. End dump stream simulation rock in one or more layers with a layer depth not exceeding 1 ½ times the maximum dimension of stream simulation rock. Distribute larger rocks throughout the mass of streambed simulation material.

Obtain a uniformly dense, compact, low permeability bed with a surface matching stream simulation bed details. Fill voids before placing the next lift and compact each layer until there is no visible evidence of further consolidation. Place channel rock, rock bands, rock weirs, stream bank rock, and other in stream rock structures as designated.

(c) Method C, Hand Placed. Place stream simulation rock using hand labor. Material may be hand carried, or carried in wheelbarrows and end dumped to obtain its full thickness. Compact each layer using tamping rods or other hand operated mechanical equipment to obtain a uniformly dense, compact, low permeability bed with a surface matching stream simulation bed details. Fill voids before placing the next lift, and compact each layer until there is no visible evidence of further consolidation. Place channel rock, rock bands, rock weirs, stream bank rock, and other in stream rock structures as designated.

648.05 Streambed Surface. Fill all voids in the streambed surface left during placement of channel rock and streambed simulation material with backfill material. Use water pressure, metal tamping rods, and similar hand operated equipment to force material into all surface voids.

648.06 Acceptance. Placing streambed simulation material will be evaluated under Subsections

106.02 and 106.04.

Measurement

648.07 Measure the items listed in the bid schedule according to Subsection 109.02.

Payment

648.08 The accepted quantities, measured as provided in Subsection 109.02, will be paid at the contract unit price per unit of measurement for Section 648 pay items listed in the bid schedule.

Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05

680 – Temporary Detour Road

Add Section 680:

Section 680. — TEMPORARY DETOUR ROAD

Description

680.01 This work consists of constructing, maintaining, and removing the detour roadway as shown on the plans.

This work includes clearing and grubbing, removing and replacing topsoil, excavating and embankment where necessary, grading, and geotextile. Temporary surface aggregate placement is a separate item, 302.01A. This work shall accommodate the stream de-watering temporary bypass channel and include fill over the channel bypass as necessary. Construction of the detour road over the existing stream channel includes fill as required. An old road is currently evident where the temporary detour is planned. When the 500 road is reopened, this work shall include removal of all fill and surfacing and reshaping all ground slopes back to a natural condition matching adjacent contours. Disturbed areas and those where the old road is evident shall be roughened and seeded.

Material

680.02 Conform to the following Subsections.

Excavation and Embankment 204

Minor Crushed Aggregate 302

648.03 General. Construct the detour road alignments to the lines and grades as shown on the plans. Remove the detour roadway and all roadway materials from the project upon completion of the project. Materials may be incorporated into the permanent roadway if approved by the CO.

Reshape the ground under the detour lines to match adjacent natural contours; replace conserved topsoil, and seed.

Furnish and install temporary traffic control devices per Section 635 of the specifications, and in accordance with the Contractor’s Traffic Control Plan. Minimum requirements for traffic control signage are shown in the drawings.

Perform excavation, backfill, and embankment work under Section 204 as needed in areas such as the channel bypass detour road crossing, the existing channel detour road crossing, and where gradients are too steep. Dispose of all debris resulting from operations in accordance with Section 203.

The detour road must have a minimum width of 12’ and a maximum grade of 10%. Surfacing will be required. Provide erosion control measures to prevent runoff from the surface entering directly into the stream.

680.04 Performance. Contractor is responsible for constructing, and maintenance of the detour road so that allows passenger and timber sale traffic to pass through the project anytime the 500 road is impassable. Construct maintain and remove detour road so that no fill enters the stream.

Perform any in-channel work required to construct the detour road within the de-watered section of channel.

680.05 Acceptance. Detour roadway will be evaluated under Subsection 106.02.

Measurement

680.06 Excavation and embankment for the detour road will not be measured.

Payment

680.07 Construction, maintenance, and subsequent removal of the detour road will be paid at the contract price per unit of measurement for the Section 680 pay items listed in the bid schedule.

Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05

705 - Rock 705.08_National_7_18_2017

Add Subsection 705.08:

705.08 Streambed Simulation Rock.

(a) Simulation Material. Furnish a mixture of soil, gravel, cobble, and boulders to simulate a natural streambed. The cobbles and boulders should be hard, durable rock that conforms to test values in 705.02.

Table 705-4 Gradation requirements for Streambed Simulation Material (inches or sieve size)

Bed Class 100% passing 84% passing 50% passing 16% passing 10% passing 2 5 2 3/4 1/4 No. 10 4 10 4 1 3/4 1/2 No. 10 6 14 6 2 1/2 3/4 No. 10 8 22 8 3 1 No. 10

10 24 10 4 1 No. 10 12 30 12 5 1 1/2 No. 10 14 36 14 6 1 3/4 No. 10 16 42 16 7 2 No. 10 20 48 20 8 3 No. 10 24 60 24 10 3 No. 10

36 72 36 14 4 No. 10

48 96 48 18 6 No. 10

(b) Streambed Channel Rock. Furnish hard durable rock that is resistant to weathering and water action, free of organic or other unsuitable material, similar in color to those in the area, and at least as angular as that found in the natural stream channel. Do not use shale, rock with shale seams, or other fissile or fissured rock that may break into smaller pieces in the process of handling and placing. Conform to test values in 705.02.

Table 705-5

Gradation Requirement for Channel Rock (CR)

Class Mass (Pounds) Approximate Cubic Dimension

(inches)

CR - 0 12 - 90 6 - 12

CR - 1 90 - 300 12 - 18

CR - 2 300 - 700 18 - 24

CR - 3 700 - 1350 24 - 30

CR - 4 1350 - 2400 30 - 36

CR - 5 2400 - 3700 36 - 42

CR - 6 3700 - 5500 42 - 48

CR - 7 5500 - 7900 48 - 54

CR - 8 7900 - 10800 54 - 60

Note: Mass / Pounds of channel is based on a sphere of the approximate cubic dimensions composed of granite. Mass will vary with rock type. Inspection should be performed by using the cube root of the A axis * B axis * C axis of each piece.

Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms.
101.03 Abbreviations.
101.04 Definitions.
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102.
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05.
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04.
104.06 Use of Roads by Contractor.
105 - Control of Material
105.02(a) Government-provided sources.
105.02(c) Contractor-located sources.
106 - Acceptance of Work
106.01 Conformity with Contract Requirements.
106.02 Visual Inspection.
107 - Legal Relations and Responsibility to the Public
Delete Subsection 107.05.
108 - Prosecution and Progress
Delete Section 108.
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.02 Measurement Terms and Definitions.
153 - Contractor Quality Control
153.02 Qualifications.
153.07 Records and control charts.
155 - Schedules for Construction Contracts
Delete Section 155.
156 - Public Traffic
Section 156. – PUBLIC TRAFFIC
157 - Soil Erosion and Sediment Control
157.04 General.
201 - Clearing and Grubbing
201.02 Material:
201.03 General:
201.04(d) Clearing.
201.04 Clearing.
201.06 Disposal.
203 - Removal of Structures and Obstructions
203.05 Disposing of Material.
208 - Structure Excavation and Backfill for Selected Major Structures
208.07 Dewatering.
209 - Structure Excavation and Backfill
209.07 Dewatering.
209.10 Compacting.
302 - Minor Crushed Aggregate
302.04 Placing Crushed Aggregate.
603 - Structural Plate Structures
603.03 General.
603.04 Erecting.
648 - Stream Simulation
Section 648. — STREAM SIMULATION
680 – Temporary Detour Road
Section 680. — TEMPORARY DETOUR ROAD
705 - Rock
705.08 Streambed Simulation Rock.