Question and Answer Sheet #1.pdf

PDF 71 KB Posted

Attached to
Millcreek Guard Station Electrical Service Upgrade Federal contract opportunity
Solicitation number
1284N820Q0010
Issued by
Department of Agriculture Forest Service

View the file

Other files for this federal contract opportunity

Other files attached to Millcreek Guard Station Electrical Service Upgrade, newest first.
File Type Posted
INSTRUCTIONS AND FILL-INS WITHOUT CLAUSES.pdf PDF
FULL SOLICITATION.pdf PDF
SITE VISIT SIGN IN.pdf PDF
FULL SOLICITATION.pdf PDF
SPECIFICATIONS.pdf PDF
Wage Determination.pdf PDF
INSTRUCTIONS AND FILL-INS WITHOUT CLAUSES.pdf PDF
MillCreekElectricalService_Drawings_signed (1).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Millcreek Electrical Upgrade Question and Answer Sheet #1

1. How much of the requirements will be covered by Rocky Mountain Powers fee associated with request #650- 4096? Are they to install a new power pole and junction box? The Forest Service will directly pay Rocky Mountain Power for any of the work performed by their crews or any other fees that they may asses. Most likely they will only be installing the primary wires to the meter once all of the work is done. There will not be a new power pole, for now we will be using the existing pole.

2. Has the boring under the road already been installed? If not, where do we connect the new 3 and 2 inch conduit to the existing conduits "already installed by FS"? The boring has not been completed, nor has the junction box been installed. The conduit installed by the Forest Service ends about 20 feet uphill from where the junction box will be installed and has been capped. The trench is still mostly open on that end and the connection is just a matter of gluing more conduit on to the existing.

File details come from the government source that posted it. Updated .