12837120Q0155

1. REQUEST NO.

5a. ISSUED BY

NAME

a. NAME

c. STREET ADDRESS

d. CITY

10. PLEASE FURNISH QUOTATIONS TO

THE ISSUING OFFICE IN BLOCK 5a ON

OR BEFORE CLOSE OF BUSINESS (Date)

2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.

UNDER BDSA REG. 2

AND/OR DMS REG.1

RATING

6. DELIVERY BY (Date)

7. DELIVERY

9. DESTINATION

a. NAME OF CONSIGNEE

b. STREET ADDRESS

PAGE OF PAGES

5b. FOR INFORMATION CALL: (No collect calls)

TELEPHONE NUMBER

AREA CODE NUMBER

8. TO:

b. COMPANY

e. STATE f. ZIP CODE

c. CITY

d. STATE e. ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

THIS RFQ

REQUEST FOR QUOTATION

(THIS IS NOT AN ORDER)

IS IS NOT A SMALL BUSINESS SET ASIDEX

08/18/2020 997823

1 1

333 BROADWAY SE

ALBUQUERQUE NM 87102

SOUTHWESTERN REGION

11/05/2020

USDA FOREST SERVICE

COCONINO NATIONAL FOREST SO

1824 S THOMPSON ST

FLAGSTAFF

AZ 86004

602 225-5350DAVID WATSON

09/04/2020 1600 PT

FOB DESTINATION

OTHER

(See Schedule)X

ITEM NO.

(a)

SUPPLIES/SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

PITTMAN VALLEY WC - TANK CLEANING OR NEW TANK

The objective of this project is to award either the BASE BID or the OPTIONAL BID. The BASE BID consists of cleaning and completing minor maintenance to one (1) 6,000-gallon steel, potable water storage tank at the Pittman Valley Work Center, on the Williams Ranger District on the Kaibab National Forest.

Period of Performance: 09/21/2020 to 11/05/2020

0001 2020-PITTMAN VALLEY WC - TANK CLEANING OR NEW TANK

Delivery: 11/05/2020

12. DISCOUNT FOR PROMPT PAYMENT

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations

13. NAME AND ADDRESS OF QUOTER

b. STREET ADDRESS

c. COUNTY

d. CITY e. STATE f. ZIP CODE

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

16. SIGNER

a. NAME (Type or print)

c. TITLE (Type or print)

a. NAME OF QUOTER

AREA CODE

NUMBER

15. DATE OF QUOTATION

b. TELEPHONE are are not attached

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition not usable

STANDARD FORM 18 (REV. 6-95)

Prescribed by GSA - FAR (48 CFR) 53.215-1(a)

SITE VISIT: August 26, 2020 10:00 AM Address Location: 1782, Forest Service Rd 74, Williams, AZ 86046

KAIBAB NATIONAL FOREST – WILLIAMS RANGER DISTRICT

2020 – PITTMAN VALLEY WORK CENTER – POTABLE WATER STORAGE TANK

CLEANING WITH OPTIONAL BID TO REPLACE EXISTING TANK

Kaibab National Forest, Williams Ranger District Page 2

SECTION 1 – SCHEDULE OF ITEMS

Item No. Item Description Method of

Measurement Unit Qty Unit Cost Amount

Base Bid Items:

01601(01) Mobilization LSQ LS 1

02570(01) Cleaning - 6,000 Gallon Potable Water Tank LSQ LS 1

02570(02) New Filter Installation LSQ LS 1

* LS = Lump Sum, LSQ = Lump Sum Quantity Base Bid Total:

Item No. Item Description Method of Measurement Unit Qty Unit

Cost Amount

Optional Bid Items:

01601(02) Mobilization LSQ LS 1

02120(01) Demolition LSQ LS 1

05100(01) New 6,000-Gallon Tank Incl.

Gravel Pad Improvement LSQ LS 1

Total Optional Bid

* LS = Lump Sum, LSQ = Lump Sum Quantity Optional Bid Total:

CLEANING WITH OPTIONAL BID TO REPLACE EXISTING TANK

Kaibab National Forest, Williams Ranger District Page 1

Table of Contents

SECTION 1 – SCHEDULE OF ITEMS

SECTION 2 – GENERAL

2.01 INTRODUCTION

2.02 PROJECT LOCATION

2.03 PROJECT REQUIREMENTS – BID ITEMS (BASE BID / OPTIONAL BID)

2.04 EXISTING TANK FEATURES

2.05 GENERAL SITE CONDITIONS, FACILITIES AND TEMPORARY CONTROLS

2.06 USE OF PREMISES

2.07 CONSTRUCTION SCHEDULE

2.08 PROVISIONS FOR SAFETY AND PUBLIC ACCESS

2.09 PROVISIONS FOR PROTECTION OF NATURAL RESOURCE

2.10 APPLICABLE CODES AND STANDARDS

SECTION 3 - SPECIFIC PROJECT REQUIREMENTS

3.01 BASE BID – CLEANING – ITEM NO 02570(01)

3.02 BASE BID – NEW FILTER INSTALLATION – ITEM NO. 02570(02)

3.03 OPTIONAL BID – NEW TANK

3.04 EQUIPMENT

3.05 COMPETENT PERSON

SECTION 4 – PHOTOGRAPHS AND SITE PLAN

4.01 EXISTING 6,000-GALLON TANK – INTERIOR / EXTERIOR

DIVISION 1 – GENERAL REQUIREMENTS

01103 – MEASUREMENT AND PAYMENT

01300 – SUBMITTALS

01601 – MOBILIZATION

DIVISION 2 – SITE WORK

02120 – SELECTIVE DEMOLITION

DIVISION 5 – METALS

05100 – WATER STORAGE TANK CONSTRUCTION

DIVISION 9 – FINISHES

09920 – PAINTING OF WATER TANK

CLEANING WITH OPTIONAL BID TO REPLACE EXISTING TANK

Kaibab National Forest, Williams Ranger District Page 3

SECTION 2 – GENERAL

2.01 INTRODUCTION

The objective of this project is to award either the BASE BID or the OPTIONAL BID.

The BASE BID consists of cleaning and completing minor maintenance to one (1) 6,000-gallon steel, potable water storage tank at the Pittman Valley Work Center, on the Williams Ranger District on the Kaibab National Forest.

This water system supports an administrative heliport site which consists of an office, (2) two modular quarters, two (2) RV pads, and a warehouse for the helitack wildland fire fighters. The existing water source is from a well that produces minimal flow and normally is supplemented with hauled water from a regulated water source by a potable water deliverer. Contractor shall be responsible for providing potable water throughout the project for cleaning and amount necessary to disinfect and re-fill the tank. There are local certified water haulers to provide this service, if necessary.

Work shall include coordination with the COR to allow timely notifications to be made to the residents and employees for any disruptions to the water service and availability.

The OPTIONAL BID item is for complete replacement of the existing 6,000-gallon water storage tank. Contractor will be responsible for all plumbing disconnects, removal, and disposal of the existing 6,000-gallon steel water tank and providing new tank, as approved, placement, and reconnection to the existing connection. Other related work includes providing and placing new compacted gravel into the existing gravel ring and providing potable hauled water to clean, disinfect, and re-fill prior to returning the tank back into operation.

The Contractor shall be responsible for providing all labor, materials, equipment, accessories, certification, permits, and all other incidentals necessary for properly cleaning the interior of the tank, or the complete replacement of the existing tank. All work shall be in accordance with local, federal, and any applicable rules and/or codes.

2.02 PROJECT LOCATION

The Pittman Valley Work Center is located on the Williams Ranger District on the Kaibab National Forest and can easily be accessed off Interstate 40. From Flagstaff, travel west on I-40 for approximately 19 miles and exit 171, then turn north onto Cool Pines Road for approximately 0.3 mile, then turn west onto County Road 74 for approximately 1 mile, then turn left into destination. From Williams, AZ, travel east on I-40 for approximately 8 miles, then turn on exit 171. Coordinates for the Pittman Valley Work Center are N35.277013 W-112.062307.

2.03 PROJECT REQUIREMENTS – BID ITEMS (BASE BID / OPTIONAL BID)

A. Base Bid – This bid item includes cleaning the interior of the tank, pressure washing the interior, removing loose interior surface coating, and removing all sedimentation.

CLEANING WITH OPTIONAL BID TO REPLACE EXISTING TANK

Kaibab National Forest, Williams Ranger District Page 4

Contractor shall be responsible for protection of all equipment and materials intended for use in the work. Contractor is responsible for purchasing and re-filling the tank with potable hauled water from a certified provider by the Coconino County Health Service Department. All work performed shall adhere to the ADEQ and ADWR guidelines and regulations.

B. Optional Bid – The optional bid item includes removing and disposing the existing 6,000-gallon steel potable water tank and replace with new 6,000-gallon steel, epoxy coated, interior and exterior for potable water storage. Pre-fabricated tank is acceptable. Work also includes providing and placing new aggregate, compacted, to provide improvement to the existing gravel pad.

2.04 EXISTING TANK FEATURES

The 6,000-gallon tank is an above ground steel tank having dimensions of approximately 10-ft high x 10-ft diameter. The tank is equipped with a 2-ft diameter shoebox style manway lid; 24-inch shell manway; 3-inch screened vent; two (2) 4-inch overflow lines with screened outlets located 16-inches and 42-inches above grade; and a float type water level indicator. The tank has a combined 2-inch inlet/outlet line from well, and a separate 4-inch floor drain line. Photographs of the existing tank can be found at the end of this document.

The tank can be isolated from the distribution system while the submersible pump can supply water directly to the distribution system through two pressurized hydropneumatics tanks for the site, if well has adequate supply.

2.05 GENERAL SITE CONDITIONS, FACILITIES AND TEMPORARY CONTROLS

A. The site can be made available to the Contractor for staging and storage during the duration of the project and will be located by the COR at the beginning of work. Any damage resulting from the Contractor’s use of this site will be repaired or replaced at the Contractor’s expense at the direction of the COR.

B. All temporary services and use areas shall be completely removed and the use areas shall be restored upon completion of use.

C. Transportation to and from the work site for the Contractor’s personnel and materials will be provided at the Contractor’s expense.

D. The Contractor shall take reasonable measure to secure equipment and contract work against theft and vandalism. Any security shall be furnished by the contractor at his/her expense and shall be removed at end of project. The Forest Service is not responsible for the theft and/or vandalism of any materials or equipment left at the project site.

E. The work zones shall be delineated and marked adequately to warn the visitors, government contractors and all government employees of equipment operations and other hazardous conditions. The Contractor is responsible for providing barrier materials and maintaining barriers such as temporary barricades, barrier tape, curbs, etc.

at all work zones.

F. The Contractor shall remove all temporary facilities and restore the site to its prior condition as a part of the project closeout procedures. Any damage to existing

Kaibab National Forest, Williams Ranger District Page 5 improvements shall be repaired at the Contractor’s expense according to the direction of the COR.

G. No Government furnished supplies will be provided.

2.06 USE OF PREMISES

A. Driveways, Walkways, and Entrances: Keep driveways, walkways and entrances serving premises clear and available to emergency vehicles and pedestrians. Do not use these areas for parking or storage of materials, unless approved by the COR.

B. Smoking is not permitted within any government building, or within 25 feet of any entrance or window.

C. Confine storage of materials to areas as approved by the COR.

D. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.

E. Water will be available prior to start of work. After work begins, water will no longer be available.

F. Sanitary facilities will be available.

G. Cell phone capability may be available.

2.07 CONSTRUCTION SCHEDULE

A. If base bid is awarded, the work shall be completed within 30 days after notice to proceed is issued. Pre-work meeting shall be immediately scheduled with the C.O. and COR to assess the current situation of occupying residents and employees to coordinate the start of work.

B. If optional bid is awarded, the work shall be completed within 45 days after notice to proceed is issued.

2.08 PROVISIONS FOR SAFETY AND PUBLIC ACCESS

A. Contractor shall operate in compliance with AWWA C652 (Disinfection of Water Storage Facilities) as it relates to equipment and personnel, safety and disinfection requirements for equipment and personnel at all times.

B. Contractor shall abide by OSHA standards safety regulations for storage water tanks.

2.09 PROVISIONS FOR PROTECTION OF NATURAL RESOURCE

A. Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2.10 APPLICABLE CODES AND STANDARDS

A. All work shall conform to the latest editions of the National Sanitation Foundation, International Building Code, International Plumbing Code, American Water Works Association, National Electric Code, and the American Institute of Steel Construction.

Kaibab National Forest, Williams Ranger District Page 6

SECTION 3 - SPECIFIC PROJECT REQUIREMENTS

3.01 BASE BID – CLEANING – ITEM NO 02570(01)

The purpose of this project is to clean the 6,000-gallon potable water storage tank located on the Kaibab National Forest.

A. Tank Cleaning – Cleaning shall be performed in accordance to ADEQ and ADWR standards. No process or materials shall be employed in such a manner that they will introduce additional hazards on the project site.

1. The Contractor shall clean all horizontal surfaces and tank walls to remove bio growths, sediment, sludge, debris, loose paint chips, and build up. Water used for high-pressure water washing shall be clean and free from oil, acid, alkali, organic matter or other deleterious material. The water shall be equal to potable water in physical and chemical characteristics.

2. All cleaning compounds must be EPA, FDA and NSF approved. The use of cleaning materials containing chlorine such as bleach solutions or any other hazardous material is not allowed to the significant risk posed to workers. The Contractor shall use environmentally preferred products whenever available.

3. The COR shall designate an area as an appropriate discharge point for water, sediment and other waste materials collected. All waste materials removed from the tanks shall be disposed of in accordance with all applicable federal, state and local requirements including any de-chlorination requirements.

4. The Contractor shall adhere to all Confined Space requirements and provide a safe environment in accordance with the sections on Confined Space Procedures, OSHA and other applicable safety requirements.

5. The Contractor shall isolate all water storage tanks from the distribution system without causing an adverse loss in pressure in the distribution system. If pressure is lost in the distribution system, the Contractor shall immediately notify the COR.

6. The tank shall be drained in accordance with ADEQ and ADWR standards.

7. The government will collect and submit bacteriological samples after tank has been disinfected, flushed, and refilled prior to returning the tank back into service.

B. MINOR MAINTENANCE

1. It is unknown if there are any leaks in the tank interior walls or floor. If holes are found, the Contractor shall immediately notify the COR. Authorization from the CO is required prior to any kind of maintenance or repair initiated by the Contractor.

2. The Contractor shall patch with a circular piece of steel plate, compatible with the existing steel, one-fourth inch and 5/16” thick, by 8 to 10 inches in diameter along the curved walls and the middle band, respectively.

3. The patch plate must be circular and shaped to fit snugly to the tank surface. The plate(s) shall be shop cut or if field cut, the cut shall be at right angles to the plate surface (visual inspection) and ground smooth.

Kaibab National Forest, Williams Ranger District Page 7

4. Grind existing welds, if necessary, so the patch plate fits snugly against the tank wall.

5. Blast clean the area to be patched in accordance with SSPC-SP6, Commercial Blast Cleaning, prior to welding the patch.

6. Blast clean the plate(s).

7. Weld the patch with a 1/4-inch fillet weld all around. Welding shall be done by

AWS certified welders. A copy of their certification must be given and approved by the COR prior to doing any welding.

8. After blast cleaning and welding, the Contractor shall patch any pitted or rough surface areas of the tank interior with an epoxy filler.

3.02 BASE BID – NEW FILTER INSTALLATION – ITEM NO. 02570(02)

A. New Filter

1. The Contractor shall provide a filter and install in pumphouse at entry point of distribution system.

2. Filter system shall be submitted for review and approval to COR prior to ordering.

A recommended system is the Nelsen Filtration Cartridge System, or an approved equal.

3. New system shall be installed per manufacturer’s recommendation with a bypass line for future maintenance.

4. Cartridge filter shall be provided and installed prior to placing in operation.

5. Contractor is responsible for providing an extra cartridge for next replacement.

6. Pressure gauges shall be installed before and after the filtering system as recommended by the manufacturer for maintenance.

3.03 OPTIONAL BID – NEW TANK

A. The specifications for the new tank and improvement to the existing gravel pad are included within these specifications with the “DIVISION” titles.

B. Contractor shall submit proposal to remove and replace the existing tank in an efficient manner to minimize disruption to the residents and employees on site.

C. Contractor shall provide all labor, materials, equipment, tools, potable hauled water, and all incidentals to complete the work.

3.04 EQUIPMENT

A. The Contractor shall supply all the necessary vehicles, potable water tank, equipment, materials, hauled water from regulated source, and personnel for work as defined.

B. The staging of equipment and supplies will be accomplished in such a manner as to allow safe movement of personnel.

C. The Contractor shall at all times keep debris, equipment and accumulation of waste materials within the staging areas.

D. Cleaning of equipment shall not be conducted in any lakes, streams or rivers nor shall resultant cleaning runoff or other debris be allowed to enter drainages or watersheds.

Kaibab National Forest, Williams Ranger District Page 8

3.05 COMPETENT PERSON

A. A competent person must be on site as defined by 29 CFR 1926.62(b).

SECTION 4 – PHOTOGRAPHS AND SITE PLAN

4.01 EXISTING 6,000-GALLON TANK – INTERIOR / EXTERIOR

“East” View of Tank

Kaibab National Forest, Williams Ranger District Page 9

“West” View of Tank

Existing View of Bottom of Tank

Kaibab National Forest, Williams Ranger District Page 10

Kaibab National Forest, Williams Ranger District Page 11

Typical areas of loose, rust coating

View of Site Plan

Kaibab National Forest, Williams Ranger District Page 12

Kaibab National Forest, Williams Ranger District Page 13

DIVISION 1 – GENERAL REQUIREMENTS

01103 – MEASUREMENT AND PAYMENT

PART 1 – GENERAL

1.1 – Requirements:

Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered incidental to and included in the payment of the pay items in the SCHEDULE

OF ITEMS.

1.2 – Measurement Terms and Definitions:

Unless otherwise specified, the following terms are defined as follows:

Each. One entire unit. The quantity is the actual number of units completed and accepted.

Linear foot. As applicable, measure the work along its length from end-to-end; parallel to the base or foundation; along the top; along the front face; or along the invert. Do not measure overlaps.

Lump sum. Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item. The quantity is designated as "1." Estimated quantities of lump sum work shown in the contract are approximate.

Square yard. 9 square feet. Longitudinal and transverse measurements for area computations will be made horizontally. No deductions from the area computation will be made for individual fixtures having area of 9 square feet or less.

1.3 – Units of Measurement

Payment will be by units defined and determined according to U.S. Standard measure.

END OF SPECIFICATION 01103

Kaibab National Forest, Williams Ranger District Page 14

01300 – SUBMITTALS

PART 1 - GENERAL

1.1 – Requirements

It will be the Contractor's responsibility to submit all items with such promptness as to cause no delay in the work. Approvals must be obtained before starting work which involves the item. Contractor shall allow ten (10) days for processing of submittals by the Government.

Submittals may also be referred to as SHOP DRAWINGS.

1.2 - Manufacturer's Literature and Shop Drawings

Submit two (2) copies to the Engineer for approval on the items required herein.

Submittal specifications are to be submitted in the following format:

A. The specifications and salient qualities of the item specified in the contract.

B. The specifications and salient qualities of the submittal item.

C. A listing of the differences and a comparison between the two, including but not limited to the structural qualities, operational qualities, any modifications necessary to accomplish installation of unit, and guarantee and warranty.

D. A cost comparison between the specified and submitted item(s) with the cost reduction benefit to the government or adequate justification for a cost increase to the government.

E. Shop drawings of submitted item(s) including wiring or layout diagrams.

If there are any modifications necessary to facilitate installation, a set of drawings showing installation of specified item and a set showing how the submittal item will be installed shall be submitted to the C.O.R.

Submittals will be waived if Contractor furnishes exact item used for design when manufacturer's model, size, etc. are shown in the contract.

Submittals are required for, but not limited to, the following:

Kaibab National Forest, Williams Ranger District Page 15

A. The Contractor shall submit within 10 days after Notice to Proceed:

1. A comprehensive work schedule

2. 09920 – Painting - Manufacturer's technical data and certification stating NSF approval of the paint for use in potable water.

3. 05100 – Shop or Fabrication drawing of the new tank.

4. Letter of certification from paint manufacturer stating that the selected paint and thickness to be applied to the new interior and exterior surfaces of the tank and all proper surfaces preparation is approved by the applicator.

5. Operating procedures and personnel training records for work in confined spaces and in toxic environments as per OSHA. Confined Space Certification.

6. Material Safety Data Sheets for paints/solvents.

7. A detailed procedure describing the proposed blast cleaning operation, abrasive capture and containment techniques, and safety measures to avoid the contamination of the natural environment of surrounding structures.

8. Select fill material to be used to replace the existing foundation of the tank. Material to be added to fill, compact, and re-grade the material in the gravel ring.

9. New accessories for the new tank including, but not limited to, gaskets, screens, and camlock assembly.

10. Float and Board type of water level indicator – submit to COR for review and approval prior to ordering.

11. Welders Certification

12. Electrical components including conduit, boxes, fittings, and any other related components to replace the electrical lines above grade and to the new water level probes.

13. Water level probes – Contractor shall submit product literature to COR for review and approval prior to ordering.

B. Contractor shall not begin work, unless instructed otherwise by the COR, before these submittals have been received and accepted by the COR.

C. The acceptance of any of the above by the COR does not relieve the Contractor from responsibility to comply with the requirements of the specification.

PART 4 – MEASUREMENT AND PAYMENT

Kaibab National Forest, Williams Ranger District Page 16

4.1 Measurement

The work specified herein will not be measured for payment.

4.2 Payment

This work is incidental to other items in this contract and direct and separate payment will not be made.

END OF SPECIFICATION 01300

Kaibab National Forest, Williams Ranger District Page 17

01601 – MOBILIZATION

1.1 - Description This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.

PART 2 – PRODUCTS

None

PART 3 – EXECUTION

None

4.1 – Measurement

Progress payments will be made as follows:

The Contractor can request payment for performance and payment bonds. The amount of the premium, including coinsurance and reinsurance agreements, will be paid upon receipt of evidence of full payment to the surety. When separate payment for bonding cost is made, the bonding cost will be subtracted from the total contract amount for this pay item and the balance paid in accordance with the progress payment schedule outlined below.

(a) When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.

(b) When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.

(c) Upon completion of all work on the project, any unpaid amount for mobilization will be paid.

Any bonding costs in excess of the total contract amount of this pay item will be paid under one or more other pay items under this contract as determined by the Contracting

Kaibab National Forest, Williams Ranger District Page 18

Officer. In no circumstance will the total amount of this contract be increased as a result of bonding costs exceeding the total contract amount of this pay item.

The total of all payments shall not exceed the original contract amount for this item.

4.2 – Payment

Payment will be made under:

BASE BID

PAY ITEM DESCRIPTION PAY UNIT

01601(01) Mobilization for Tank Cleaning LS

OPTIONAL BID

PAY ITEM DESCRIPTION PAY UNIT

01601(02) Mobilization for New Tank LS

END OF SPECIFICATION 01601

Kaibab National Forest, Williams Ranger District Page 19

DIVISION 2 – SITE WORK

02120 – SELECTIVE DEMOLITION

1.1 DESCRIPTION

This section includes removing and disposing of existing 6,000-gallon steel water tank.

Existing plumbing connections shall be carefully disconnected. The existing tank shall be removed and properly disposed of from the administrative site.

1.2 SECTION REQUIREMENTS

A. All existing plumbing connections will be re-used to reconnect to the new steel storage tank, if condition of connection is acceptable. Carefully detach from existing plumbing and electrical connections, in a manner to prevent damage, place any necessary temporary seal(s) and protect the open end(s). Include any miscellaneous fittings, gaskets, fasteners or brackets needed for reattachment.

B. It is not expected that hazardous materials will be encountered in the Work. If hazardous materials are encountered, do not disturb; immediately notify COR and the Forest Service. Hazardous materials will be removed by the Forest Service under a separate contract.

PART 2 – PRODUCTS

2.1 PEFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with all federal, state, and local regulations.

B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.

PART 3 – EXECUTION

3.1 DEMOLITION

A. Existing tank shall be secured and properly disposed at an appropriate landfill facility.

Measurement will be based on careful utility disconnections, placing temporary seal, fittings, and any attached components necessary to remain to reconnect to the new tank. Any associated removal and disposal such as the gravel in the gravel pad shall be included in this pay item.

Kaibab National Forest, Williams Ranger District Page 20

Payment will be for the contract unit price, Lump Sum (LS). Payment will be made if OPTIONAL BID is awarded for new tank installation under:

Pay Item Description Pay Unit

02120(01) Demolition LS

END OF SPECIFICATION 02120

Kaibab National Forest, Williams Ranger District Page 21

DIVISION 5 – METALS

05100 – WATER STORAGE TANK CONSTRUCTION

PART I – GENERAL

1.01 Description:

This section of the specifications covers performing all operations for the construction and painting of water storage reservoirs and all accessories including foundation, inlet-outlet lines, drain, vent, overflow lines, splash pad, screens, gaskets, lockable camlock assemblies, and all other items as described for this project. All materials and workmanship shall conform with all applicable requirements of AWWA D-100 Standard for “Welded Steel Tanks for Water Storage” as joint adopted by the American Water Works Association and the American Welding Society in the latest version.

1.02 Related Work Specified Elsewhere

09920 – Painting of Water Tank

1.03 Submittals

A. Welder’s Certification

PART II – MATERIALS

2.01 – Existing Tank Description – General

The 6,000-gallon tank is an above ground steel tank having dimensions of approximately 10-ft high x 10-ft diameter. The tank is equipped with a 2-ft diameter shoebox style manway lid; 24-inch shell manway; 3-inch screened vent; two (2) 4-inch overflow lines with screened or camlock outlets located 16-inches and 42-inches above grade; and a float and board type water level indicator. The tank has a combined 2-inch inlet/outlet line from well, and a separate 4-inch floor drain line. Photographs of the existing tank can be found at the end of this document.

2.02 Epoxy Filler:

Catalyzed epoxy filler compatible with the finish coatings by the selected manufacturer and their recommendations.

2.03 Select Fill for Gravel Pad:

Kaibab National Forest, Williams Ranger District Page 22

Select fill for foundation shall be as recommended by tank manufacturer for the existing gravel ring. Contractor shall provide select fill material and place, compact, and properly grade in the gravel ring prior to tank placement.

Provide any technical information on the select fill to the COR for review and approval prior to ordering. The new material infill shall be compatible with the existing material.

PART III - EXECUTION

3.01 – New Steel Water Storage Tank

A. Characteristics:

New tank shall match the existing locations of its current features as best as possible.

Contractor is responsible for providing and installing all new electrical and plumbing components and reconnecting all utilities.

1. New Components:

a. Electrical Junction Box – Provide and install all new conduit, new boxes, fittings to install the new water level probes. make the connections if the new tank openings do not match the existing plumbing.

b. Float and Board Type Water Level Indicator – Contractor shall provide and install per manufacturer’s recommendations. Contractor shall check the assembly after installation for proper operation.

c. Gaskets – Contractor shall provide and properly install all new gaskets for all connections and openings.

d. Screens – Contractor shall provide and properly install and secure all new screens for all vents, drains and overflow pipes.

e. Lockable camlock and plug – Contractor shall provide a lockable camlock assembly for one (1) overflow pipe for filling. Forest Service will provide government padlock.

Contractor shall carefully measure all locations of the openings, any threaded openings, location of vents, overflow pipe, manways, and any existing accessories to fabricate the new tank.

B. Interior Surface Preparation

Interior surfaces shall be blast cleaned as per the requirement of SSPC-SP10, Near-White Abrasive Blast Cleaning with a minimum angular anchor profile of 2.0 mils.

The height of profile of the anchor pattern produced on the surface shall be limited to a maximum height that will not be detrimental to the life of the paint film and shall be as per paint manufacturer's recommendations. If the maximum particle sizes specified produces an anchor pattern that is too high or too rough for the paint system, the abrasive must be sized to produce the paint manufacturer's recommendation. The height of the anchor

Kaibab National Forest, Williams Ranger District Page 23 pattern can be determined by grinding a flat spot on the blasted surface until the bottom of the pits are almost reached.

Compressed air shall be free of detrimental amounts of water or oil. Adequate separators and traps shall be used.

The interior surface shall be cleaned by vacuum for the purpose of removing any traces of sediment, blast products from the surface, and also for the removal of abrasive from pockets and corners.

C. Exterior Surface Preparation

Exterior surfaces and appurtenances shall include full removal of existing system. SSPC SP6 Commercial Abrasive Blast Cleaning with a minimum angular anchor profile of 2.0 mils.

3.02 – Tank inspection:

A. On-site construction: Remove all chalk, dirt, spent abrasive, debris and other contaminants cleaned from the tank, after the blast cleaning is complete. Then inspect the tank interior for defective welds or other defects that should be patched. The COR or a designated representative must accompany the Contractor during the inspection. The Contractor shall provide a safe environment in accordance with the sections on Confined Space Procedures, OSHA and other applicable safety requirements.

9. Off-site Construction: If tank will be fabricated in a controlled facility, all data prior to fabrication shall be submitted to COR for approval prior to ordering.

3.03 – Competent Person:

A competent person must be on site at all times as defined by 29 CFR 1926.62(b).

Measurement will be based on complete tank fabrication, interior/exterior painting, materials, labor, equipment, new tank placement, providing and installing new plumbing and electrical lines to new tank, plumbing/electrical reconnections, splash pad installations, all screens (vent/overflows), gravel pad installation, water level indicator installation, gaskets, lockable camlock assembly, and removing and disposing of existing tank.

Payment will be for the contract unit price, Lump Sum (LS). Payment will be made if OPTIONAL BID is awarded for new tank installation under:

Kaibab National Forest, Williams Ranger District Page 24

Pay Item Description Pay Unit

05100(01) New 6,000-Gallon Tank Incl. LS Including Gravel Pad Improvement

END OF SECTION 05100

Kaibab National Forest, Williams Ranger District Page 25

DIVISION 9 – FINISHES

09920 – PAINTING OF WATER TANK

1.1 – Scope:

This section specifies the painting of all interior and exterior surfaces of the water tank. All field surface preparation shall be in accordance with these specifications and the cited specifications of the Steel Structures Painting Council (SSPC).

This work includes, all surfaces of the new steel water tank including all openings for connections, all areas and any appurtenances such as overflow pipes, inflow and outflow pipes, support brackets, float type tank level indicator, and hatches, etc. All work shall be performed in accordance with OSHA, EPA, and State requirements. This shall include the collection of all spent abrasive, paint and paint particles generated during the preparation phases into containers approved for storing and transporting such waste.

1.2 – Submittals

A. The Contractor shall submit within 10 days after Notice to Proceed:

1. A comprehensive schedule of work

2. Manufacturer's technical data and certification stating NSF approval of the paint for use in potable water, paragraph 2.1, Paint Materials.

3. Letter of certification from paint manufacturer stating that the selected paint and thickness to be applied to the new interior and exterior surfaces of the tank and all proper surfaces preparation is approved by the applicator.

4. Material Safety Data Sheets for paints/solvents.

B. Contractor shall not begin work, unless instructed otherwise by the COR, before these submittals have been received and accepted by the COR.

C. The acceptance of any of the above by the COR does not relieve the Contractor from responsibility to comply with the requirements of the specification.

PART 2 – PRODUCTS

2.1 – Paint Materials

A. All paint materials to be used for the tank interior shall be certified to meet NSF/ANSI standard 61, latest edition. Certification shall be a signed written statement by the paint

Kaibab National Forest, Williams Ranger District Page 26 manufacturer. Certification shall be delivered to the Engineer prior to delivery of the paint to the site.

B. The approved materials shall be delivered to the job site in their original unopened containers bearing the manufacturer's name, number and batch number.

C. All paint shall be products of Tnemec or an approved equal, unless the Engineer approves a substitute as outlined hereafter. Equivalent materials of other manufacturer's may be substituted upon written approval of the Engineer. Request for substitution of materials shall include the manufacturer's literature for each product stating name, generic type, descriptive information, solids by volume, performance criteria, recommended film thickness and a list of projects in Arizona where each product has been used and rendered satisfactory service for at least three years. No request for substitution shall be considered that would decrease film thickness and/or number of coats or proposes a change in the type of coating specified.

INTERIOR STEEL TNEMEC (or approved equal) DRY FILM THICKNESS

(DFT) MILS

PRIME COAT SERIES 91 H20 HYDROZINC, 1 COAT 2.5 – 3.5 mils

FINISH COATS SERIES N140 (N140F for cold weather) POTAPOX PLUS, 2 COATS 5.0 – 7.0 mils per coat

TOTAL DFT = 12.5 – 17.5 .

EXTERIOR STEEL TNEMEC (or approved equal)

DRY FILM

THICKNESS (DFT)

MILS

PRIME COAT SERIES N140 (N140F for cold weather) POTAPOX PLUS, 1 COAT 5.0 – 7.0 mils

FINISH COAT SERIES 1095 ENDURASHIELD, 1 COAT 2.5 – 3.5 mils TOTAL DRY FILM THICKNESS = 7.5 – 10.5 mils

* For Full Removal of System, Surface Preparation shall follow SSPC SP^, Commercial Abrasive Blast Cleaning with a minimum angular anchor profile of 2.0 mils.

PART 3 – EXECUTION

3.1 – Paint Application

A total of 3 coats shall be applied to the interior to avoid sagging and meet the final thickness. The second coat applied shall be a different color from the first and third coats to verify uniform coverage. First coats or prime coats should be applied within 12 hours after blast or mechanical cleaning, but always, before any visible rust blooms develop. If rust

Kaibab National Forest, Williams Ranger District Page 27 blooms develop, within any time frame, before a prime coat is applied, that area must be blast or mechanically cleaned again to the appropriate standard before painting.

Interior coatings shall be applied in accordance with the manufacturer's recommendations for immersion service. Exterior coatings must be applied in accordance with the manufacturer's recommendations.

Paint shall be applied during good painting weather. Air and surface temperature shall be within limits as prescribed by the manufacturer for the coating being applied and work areas shall be reasonably free of airborne dust at the time of application and while the coating is drying.

All surfaces to be painted shall be thoroughly dry before next coat application. No paint shall be applied under conditions of rain, fog, mist or when the relative humidity exceeds 85%, or when the steel surface is less than 5 degrees Fahrenheit above dew point.

Materials shall be mixed, thinned and applied according to the manufacturer's printed instructions.

Allow each coat to dry thoroughly before applying the next coat. Provide adequate ventilation for tank interior to carry off solvents during drying phase.

Finish coats shall be uniform in color sheen without streaks, laps, runs, sags, or missed areas.

Paint shall be applied at the specified minimum mil thickness described. Coverage rates shall not be used as an acceptance standard.

The dry paint film thickness above the peaks of the profile should equal the thickness known to be needed over a smooth surface for the desired protection. If it is not possible to use an abrasive sized small enough to produce a desirable height of profile, the dry paint film thickness should be increased to provide adequate thickness above the peaks.

3.2 – Quality Assurance and Inspection

The Contractor shall holiday detect the interior substrates using a low voltage holiday detector. The tank interior shall be holiday free, and any repair areas shall be prepared and coated according to the manufactures’ instructions.

Contractor shall be recommended by the manufacturer as being a qualified applicator of the specified product and shall use individual trades qualified to perform the work required by this specification.

All work and materials shall be accessible to the inspector and the COR. All scaffolding, rigging or other means necessary to gain adequate access to any areas shall be provided by

Kaibab National Forest, Williams Ranger District Page 28 the Contractor. The Contractor shall correct such work as is found defective under this specification.

3.3 – Acceptance

Contractor shall provide copies of results of holiday testing, paint mil thickness, and any other tests. The tank shall be filled and tested for leaks prior to delivery to the site. The site will have no water for testing. The tank shall hold water with no leakage for at least 24 hours for acceptance.

3.4 – Confined Space Procedures

The Contractor shall be responsible for the safety of the workers, Forest Service personnel, subcontractors and inspectors. The following sections are provided as a guide, and not intended as an all inclusive rigid safety plan for the Contractor.

Contractor shall establish written operating procedures for work in confined spaces as well as in toxic environments. Contractor shall use NIOSH and OSHA guidelines for working in confined spaces for work activities inside tanks, as appropriate. The procedures shall incorporate provisions covering at least, but not limited to, the following subjects:

1. Pre-entry atmospheric testing for oxygen deficiency and toxic or explosive gasses where appropriate.

2. Periodic atmosphere monitoring when work processes generate hazardous air contaminants.

3. Forced air ventilation.

4. Training of employees specific to working in confined spaces, and toxic environments.

5. Provide Class B respiratory protection for all workers entering tank as well as protective clothing. All equipment and clothing must be decontaminated upon exiting tank.

6. Communication methods and standby personnel.

7. Safety equipment, clothing, and protection in accordance with OSHA standards.

8. Special hazards of planned work activities. See OSHA standards 29 CFR 1910.94 "Ventilation"; 29 CFR 1926.103, and 29 CFR 1910.134 "Respiratory Protection";

29 CFR 1926.353 "Ventilation and Protection in Welding, Cutting and Heating"; 29 CFR 1910.146 "Permit Required Confined Space."

9. Confined Space entry check list.

10. A Confined Space Data Sheet must be filled out daily.

Kaibab National Forest, Williams Ranger District Page 29

Before entry into the tank each work day, the Contractor must evaluate the hazards or potential to which the workers will be exposed. The Contractor must fill out the "Confined Space Data Sheet" daily and file this with daily reports to be given to the Engineer. These include:

1. The physical characteristics of the tank (i.e. head bumpers, tripping, falling, footing etc.)

2. The current and past uses of the tank which may affect the oxygen level toxicity or flammability of the atmosphere in the space, or which may have left a residue of material which could fall on, engulf, or otherwise injure the worker

3. Any special hazards arising from the location of the tank (i.e., relative to other operations, processes or structures) which may endanger personnel inside the tank.

4. Any operations or processes that are to be carried out in, or which involve, the tank while workers or inspectors are inside.

5. For any hot work such as welding, a reading of 10% LEL (Lower Explosive Limit) or 10% LFL (Lower Flammable Limit) as determined by atmospheric monitoring will classify the tank as a Confined Space and is subject to prohibitions or restrictions.

No entry into tank shall occur without monitoring of the atmosphere, using a gas detector each morning before work begins or whenever there is a three hour period where workers were not within the tank.

If the gas detector is not in proper operating condition, then entry shall not be allowed.

At each confined space entry, an employee shall be designated as the Confined Space Attendant. The primary duty of the attendant, when employees are inside the confined space, is to maintain communication with the employees inside the confined space and monitor their status. The Confined Space Attendant will not be assigned any other employees inside the confined space or take the attendant away from the entrance to the confined space. In the event of an emergency inside the space, the attendant shall make all emergency notifications and wait outside the confined space for relief person. The attendant shall not enter the confined space until he or she is properly relieved of attendant duties. At that point, the attendant may enter the confined space to perform a rescue. The rescuer must don the SCBA unit for rescue entry unless communication with workers inside the space clearly indicates that the emergency is not due to air quality.

Kaibab National Forest, Williams Ranger District Page 30

CONFINED SPACE ENTRY PERMIT

Date______________ Time _____________ Job ________________________________

Location _______________ Contact Person _____________________ Title ________________

Are Physical Hazards Secured? (circle each one)

Mechanical yes/no Electrical yes/no Pneumatic yes/no Hydraulic yes/no

Are There Atmospheric Hazards? yes/no Name of Product ____________________________

Vapor or Gas Pre-Entry Testing: %02 ________ %LEL ________ Tox. ________ppm

CO ________ppm (carbon monoxide) H2S _______ppm (hydrogen sulfide)

Name of Person(s) Testing Atmosphere: ____________________________ Time: __________

Meter Type _____________________ Model # _____________________ Equip # __________

Type of Ventilation to be used: positive_______ negative_______ pressure

No ENTRANTS BACK-UP TEAM ATTENDANTS

Equipment: 1) SCBA/SABA _________ 4) PPE _________ 7) Harness ________

2) Escape Pak __________ 5) Personal Atmosphere Monitor ________

3) Communication ________ 6) Retrieval System _________

NO ENTRANTS TIME IN TIME OUT

ATMOSPHERIC MONITORING LOG

TIME OXYGEN

FLAMMABILITY (%LEL) TOXICITY

PPM

Kaibab National Forest, Williams Ranger District Page 31

3.5 – Additional Safety Requirements and Precautions

Nozzle blast operators exposed to blast dust shall wear a U.S. Bureau of Mines approved helmet connected to a source of clean air. Respiratory protection shall comply with OSHA regulations 29 CFR 1910.94, 29 CFR 1910.103, and 29 CFR 1910.134.

Class B SCBA respirators shall be worn by all who are exposed to blast dust environment.

Adequate protection for personnel from flying particles shall be provided in any blasting operation, Respiratory protection shall comply with OSHA regulations 29 CFR 1926.103 and

29 CFR 1910.134.

Safety goggles shall be worn by all persons near any blasting operation.

Blast hose shall be grounded to dissipate static charges.

Contractor shall provide all safety equipment and workers will use full protection in accordance with OSHA regulations for construction industry 29 CFR 1926.

The work specified herein will not be measured for payment. This work is incidental to other items in this contract and direct separate item payment will not be made.

END OF SPECIFICATION 09920

PROVISIONS AND CLAUSES

B - SECTION B - Supplies or Services and Prices/Costs Schedule of Items C - SECTION C - Description/Specifications/Statement of Work D - SECTION D - Packaging and Marking E - SECTION E - Inspection and Acceptance F - SECTION F - Deliveries or Performance G - SECTION G - Contract Administration Data H - SECTION H - Special Contract Requirements I - SECTION I - Contract Clauses J - SECTION J - List of Documents, Exhibits, and Other Attachments K - SECTION K - Representations, Certifications, and Other Statements of Offerors L - SECTION L - Instructions, Conditions, and Notices to Offerors or Respondents M - SECTION M - Evaluation Factors for Award

B - SECTION B - Supplies or Services and Prices/Costs Schedule of Items

C - SECTION C - Description/Specifications/Statement of Work

D - SECTION D - Packaging and Marking

E - SECTION E - Inspection and Acceptance

52.246-1 Contractor Inspection Requirements. (APR 1984)

52.252-2 Clauses Incorporated by Reference. (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): [Insert one or more Internet addresses]

(End of clause)

F - SECTION F - Deliveries or Performance

G - SECTION G - Contract Administration Data

H - SECTION H - Special Contract Requirements

I - SECTION I - Contract Clauses

52.204-7 System for Award Management. (OCT 2018)

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015)

52.219-6 Notice of Total Small Business Set-Aside. (MAR 2020)

52.222-3 Convict Labor. (JUN 2003)

52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in…

This is the start of the file's text. The full file is on GovTribe.