Solicitation 1282A720R0009 Fort Simcoe Job Corps Center Site Paving Improvements.pdf
PDF 592 KB Posted
- Attached to
- Fort Simcoe Job Corps Center Paving Center Roads
- Solicitation number
- 1282A720R0009
- Issued by
-
Department of Agriculture Forest Service
About this file
This draft request for proposal and pre-solicitation notice seeks contractors to perform site paving improvements at the Fort Simcoe Job Corps Center. The scope of work includes demolishing and removing existing asphalt pavement, reconditioning underlying roadbeds, and placing new hot asphalt surfacing totaling approximately 4,200 square yards of removal/reconditioning and 1,100 tons of new pavement. The period of performance is July 7 through December 11, 2020. Interested contractors must submit any comments on the draft documents by June 12, 2020 to the contracting officer and engineer listed. The final solicitation is expected to be issued on or about May 14, 2020 using best value evaluation of price, experience, and past performance. The work location is the Fort Simcoe Job Corps Center facility in White Swan, Washington.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA Forest Service Fort Simcoe Job Corps Center
Site Paving Improvements Solicitation Number: 1282A720R0009
Request for Proposal
Disclosure of the magnitude of construction project – Between $500,000 and $1,000,000
Project location: The project is located at the Fort Simcoe Job Corps Center. The facility address is 40 Abella Lane, White Swan, WA, 98952.
On Site Scheduling: Between 8:00 AM-4:30 PM Monday through Friday.
Contact: Miranda Olson at miranda.olson@usda.gov 509-874-8908to schedule a site visit, concerning project, location and site conditions.
Potential offerors are strongly encouraged to visit the site on their own and evaluate the work outlined in this solicitation and attachments
Start Work: It is estimated that the work can begin on July 20th, 2020.
Performance Period: All work must be completed and accepted by October 30th, 2020.
Return the following documents with your proposal to be considered responsive:
1. Signed SF-1442 with any Amendment acknowledgements in block 19 of the SF 1442
2. Section B Pricing
3. Technical Proposal
Section B – SUPPLIES OR SERVICES & PRICES
NOTES:
Offerors must submit pricing on all items to be considered responsive. Round to the nearest cent
Optional Item 0002 Notice to Offeror(s): Funds are not presently available for
Optional Item 0002. No award will be made for Optional Item 0002 until funds are available.
Item
No
Description
Method of
Measurement
Unit
Quantity Total
Fort Simcoe Job
Corps Center
Site Paving
Improvements
LSQ
Lump
Sum
Job
Optional
Fort Simcoe Job
Corps Center
Additional Site
Paving
Improvements
LSQ Lump
Sum
Job
Schedule of Items
Fort Simcoe Job Corps – Site Paving
ITEM
NUMB
ER
DESCRIPTION
METHO
D OF
MEAS.
UNI
T
QT
Y.
UNIT
PRICE
TOTAL
Base Items
151(01)a Mobilization (Base Items) LSQ LS 1
203(04)a
(BA-01)
Removal of Asphalt Pavment &
Concrete, disposal method – Remove from project
CQ SY 2,840
203(04)b
(BA-02)
Removal of Asphalt Pavment &
Concrete, disposal method – Remove from project
CQ SY 1,070
303(09)a
(BA-01)
Roadway Reconditioning, compaction method (a)
CQ SY 2,840
303(09)b
(BA-02)
Roadway Reconditioning, compaction method (a)
CQ SY 1,070
303(09)c
(BA-03)
Roadway Reconditioning, compaction method (a)
CQ SY 260
403(04)a
(BA-01)
Asphalt Concrete, WA State DOT, Type I
AQ TN 762
403(04)b
(BA-02)
Asphalt Concrete, WA State DOT, Type I
AQ TN 242
403(04)c
(BA-03)
Asphalt Concrete, WA State DOT, Type I
AQ TN 70
609(05)b Paved Ditch, Concrete V-Pan, 4’ wide, 6” thick
AQ LF 428
TOTAL
ITEM
NUMB
ER
DESCRIPTION
METHO
D OF
MEAS.
UNI
T
QT
Y.
UNIT
PRICE
Optional Items
151(01)b Mobilization (Optional Items) LSQ LS 1
203(04)a
(OA-01)
Removal of Asphalt Pavment &
Concrete, disposal method – Remove from project
CQ SY 1,230
203(04)b Removal of Asphalt Pavment & CQ SY 2,640
(OA-02) Concrete, disposal method – Remove from project
203(04)c
(OA-03)
Removal of Asphalt Pavment &
Concrete, disposal method – Remove from project
CQ SY 2,250
303(09)a
(OA-01)
Roadway Reconditioning, compaction method (a)
CQ SY 1,230
303(09)b
(OA-02)
Roadway Reconditioning, compaction method (a)
CQ SY 2,640
303(09)c
(OA-03)
Roadway Reconditioning, compaction method (a)
CQ SY 2,250
403(04)a
(OA-01)
Asphalt Concrete, WA State DOT, Type I
AQ TN 339
403(04)b
(OA-02)
Asphalt Concrete, WA State DOT, Type I
AQ TN 725
403(04)c
(OA-03)
Asphalt Concrete, WA State DOT, Type I
AQ TN 620
LSQ = Lump Sum Quantity
CQ = Contract Quantity
AQ = Actual Quantity
Price proposal furnished by:
Business
Name: Phone: ( )
Address:
E-mail:
DUNS #:
Estimated start work date:
Section C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
GENERAL SPECIFICATIONS:
Construction shall conform to the specifications in the “Standard Specifications For Construction of Roads and Bridges on Federal Highway Projects, U. S. Customary Units” publication FP-14, 2014 edition. This publication may be obtained from:
Headquarters, Washington D. C.
David K Green
Construction Standards Engineer
Email: david.green@fhwa.dot.gov
Federal Highway Administration
HFPD-3
400 Seventh Street, SW
Washington D.C. 20590
TECHNICAL SPECIFICATIONS:
See Specifications for Construction of Roads and Bridges on Federal Highway Project
Specification List
SPECIAL PROJECT SPECIFICATIONS – EXISTING/SPECIAL CONDITIONS:
The Contractor shall conduct his operations to ensure the least inconvenience to employees and students. The Contractor shall limit stored materials to areas as approved by the CO in advance.
The Contractor shall submit their proposed construction schedule at least 14 days in advance for approval by the Forest Service. The Contractor shall minimize disturbance of all undisturbed areas.
Specifications for Construction of Roads and Bridges on Federal Highway Projects
Specification List
Applicable sections of the Standard Specifications For Construction of Roads and Bridges on
Federal Highway Projects, FP-14, U.S. Customary Units will vary depending on the final engineering design selected, however, the Government expects some or all of the following sections will be incorporated into the final engineering design prepared by the Contractor. It is the Contractor’s responsibility to identify applicable specifications, develop additional SCRs as required, and delete inapplicable specifications (as approved by the CO) Other specifications mailto:david.green@fhwa.dot.gov referred to within these specifications (even though not specifically listed herein) are also fully applicable to this project.
101 Terms, Format, and Definitions
104 Control of Work
105 Control of Materials
106 Acceptance of Work
107 Legal Relations and Responsibility to the Public
108 Prosecution and Process
109 Measurement and Payment
153 Contractor Quality Control
154 Contractor Sampling and Testing
155 Schedules for Construction Contracts
156 Public Traffic
203 Removal of Structures and Obstructions
204 Excavation and Embankment
303 Road Reconditioning
400 Asphalt Pavements and Surface Treatments
700 to 725 Materials (All applicable materials sections)
452.211-72 Statement of Work/Specifications. (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities
(except as otherwise specified), to perform the Statement of Work/Specifications referenced in
Section J.
452.211-73 Attachments to Statements of Work/Specifications. (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
Section E - INSPECTION AND ACCEPTANCE
52.246-1 Contractor Inspection Requirements. (APR 1984)
52.246-12 Inspection of Construction. (APR 1996)
Section F - DELIVERIES OR PERFORMANCE
52.242-14 Suspension of Work. (APR 1984)
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than December 11th, 2020.
The time stated for completion shall include final cleanup of the premises.
Section G - CONTRACT ADMINISTRATION DATA
452.215-73 Postaward Conference. (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled with the successful contractor after the date of contract award.
Invoicing/Payments. All payments are processed using The Invoice Processing Platform (IPP).
This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm. Please make sure that your company has registered at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account.
The IPP Customer Support Desk is available to assist users Monday through Friday (excluding
Federal holidays) from 8 a.m. to 6 p.m. ET, to answer questions related to accessing IPP or completing the registration process. Their toll-free number is 1-866-973-3131 or they can be reached at IPPCustomerSupport@fms.treas.gov. If you have any additional questions or concerns, please contact the Controller Operations Division Help Desk at 1-877-243-3072 or cod.help@usda.gov.
Section H - SPECIAL CONTRACT REQUIREMENTS
452.236-72 Use of Premises. (NOV 1996)
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the
Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the
Contractor.
(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.
Section I - CONTRACT CLAUSES
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/far/ http://www.dm.usda.gov/procurement/policy/agar.html
52.203-3 Gratuities (APR 1984)
52.203-5 Covenant Against Contingent Fees (MAY 2014)
52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006)
52.203-7 Anti-Kickback Procedures (MAY 2014) mailto:cod.help@usda.gov
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform
Employees of Whistleblower Rights
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY
2011)
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors
Debarred, Suspended, or Proposed for Debarment. (OCT 2015)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT
2018)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)
52.211-18 Variation in Estimated Quantity. (APR 1984)
52.219-6 Notice of Total Small Business Set-Aside. (NOV 2011)
52.219-14 Limitations on Subcontracting (MAR 2020)
52.222-3 Convict Labor. (JUN 2003)
52.222-4 Contract Work Hours and Safety Standards —Overtime Compensation (MAY
2018)
52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (MAY 2014)
52.222-6 Construction Wage Rate Requirements. (MAY 2014)
52.222-7 Withholding of Funds. (MAY 2014)
52.222-8 Payrolls and Basic Records. (MAY 2014)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)
52.222-11 Subcontracts (Labor Standards). (MAY 2014)
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance With Construction Wage Rate Requirements and Related
Regulations. (MAY
2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (MAY 2014)
52.222-21 Prohibition of Segregated Facilities. (APR 2015)
52.222-26 Equal Opportunity. (SEP 2016)
52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)
52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction
Contracts.
(SEP 2013)
52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)
52.223-6 Drug-Free Workplace. (MAY 2001)
52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)
52.228-2 Additional Bond Security. (OCT 1997)
52.228-5 Insurance-Work on a Government Installation (JAN 1997)
52.228-11 Pledges of Assets. (JAN 2012)
52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)
52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014)
52.232-23 Assignment of Claims. (MAY 2014)
52.232-27 Prompt payment for construction contracts. (JAN 2017)
52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL
2013)
52.233-1 Disputes. (MAY 2014)
52.233-3 Protest after Award. (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)
52.236-2 Differing Site Conditions. (APR 1984)
52.236-5 Material and Workmanship. (APR 1984)
52.236-6 Superintendence by the Contractor. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.236-8 Other Contracts. (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements.
(APR 1984)
52.236-10 Operations and Storage Areas. (APR 1984)
52.236-11 Use and Possession Prior to Completion. (APR 1984)
52.236-12 Cleaning Up. (APR 1984)
52.236-13 Accident Prevention. (NOV 1991)
52.236-16 Quantity Surveys. (APR 1984)
52.236-17 Layout of Work. (APR 1984)
52.236-21 Specifications and Drawings for Construction. (FEB 1997)
52.236-26 Preconstruction Conference. (FEB 1995)
52.236-28 Preparation of Proposals—Construction (OCT 1997)
52.243-4 Changes (JUN 2007)
52.244-6 Subcontracts for Commercial Items. (NOV 2017)
52.245-1 Government Property. (JAN 2017)
52.246-21 Warranty of Construction. (MAR 1994)
52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form).
(APR 1984)
52.249-10 Default (Fixed-Price Construction). (APR 1984)
52.249-14 Excusable Delays (APR 1984)
452.232-70 Reimbursement for Bond Premiums - Fixed-Price Construction Contracts.
(NOV 1996)
452.236-71 Prohibition Against the Use of Lead-Based Paint. (NOV 1996)
452.236-72 Use of Premises. (NOV 1996)
452.236-73 Archaeological or Historic Sites. (FEB 1988)
452.236-74 Control of Erosion, Sedimentation, and Pollution. (NOV 1996)
452.236-76 Samples and Certificates (FEB 1988)
52.217-7 Option for Increased Quantity-Separately Priced Line Item. (MAR 1989)
The Government may require the delivery of the Optional Item 0002, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days from contract award.
Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
52.219-28 Post-Award Small Business Program Rerepresentation. (JUL 2013)
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it ___ is, ___ is not a small business concern under NAICS Code
237310 Highway, Street, and Bridge Construction assigned to contract number.
(End of clause)
52.225-9 Buy American - Construction Materials. (MAY 2014)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item- (1) Means any item of supply (including construction material) that is-
(i) A commercial item (as defined in paragraph (1) of the definition at FAR
2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph
(1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of construction material.
Domestic construction material means-
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if-
(i) The cost of its components mined, produced, or manufactured in the United
States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material. United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a
COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph
(b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the
Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph
(b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the
Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy
American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of
Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of Quantity Price measure (dollars)*
Item 1:
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
Item 2:
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
52.228-15 Performance and Payment Bonds-Construction (OCT 2010)
(a) Definitions. As used in this clause-
“Original contract price” means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25A). The penal amount of payment bonds at the time of contract award shall be
100 percent of the original contract price.
(3) Additional bond protection. (i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury
Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with
52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to
(1) conditions bearing upon transportation, disposal, handling, and storage of materials;
(2) the availability of labor, water, electric power, and roads;
(3) uncertainties of weather, river stages, tides, or similar physical conditions at the site;
(4) the conformation and conditions of the ground; and
(5) the character of equipment and facilities needed preliminary to and during work performance.
The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
(b) The Government assumes no responsibility for any conclusions or interpretations made by the
Contractor based on the information made available by the Government. Nor does the
Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
Section J - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
J-1 Specifications 1282A720R0009 Fort Simcoe Job Corps Center Site Paving Improvements
J-2 Drawings 1282A720R0009 Fort Simcoe Job Corps Center Site Paving Improvements
J-3 Construction Wage Determination 1282A720R0009 Fort Simcoe Job Corps Center Site
Paving Improvements
J-4 Submittal Log 1282A720R0009 Fort Simcoe Job Corps Center Site Paving Improvements
Section K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS
OF OFFERORS
OR RESPONDENTS
52.209-7 Information Regarding Responsibility Matters (OCT 2018)
52.204-8 Annual Representations and Certifications. (NOV 2017)
(a)(1) The North American Industry classification System (NAICS) code for this acquisition is
_237310_.
(2) The small business size standard is _$39.5 million_.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certification in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
[X] (i) Paragraph (d) applies.
[_] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated: (i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal
Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal
Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(vii) 52.209-5; Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony
Conviction under any Federal Law. This provision applies to all solicitations.
(ix) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast
Guard.
(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal
Opportunity.
(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA- designated items.
(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—
Representation. This provision applies to solicitations that include the clause at 52.204-7.
(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xx) 52.225-4, Buy American--Free Trade Agreements--Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225- 3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its
Alternate I applies.
(C) If the acquisition value is $50,000 or more but is less than $77,533, the provision with its
Alternate II applies.
(D) If the acquisition value is $79,507 or more but is less than $100,000, the provision with its
Alternate III applies.
(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--
Certification. This provision applies to all solicitations.
(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or
Transactions Relating to Iran—Representation and Certification. This provision applies to all solicitations.
(xxiv) 52.226-2, Historically Black College or University and Minority Institution
Representation.
This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(2) The following representations or certifications are applicable as indicated by the Contracting
Officer:
[Contracting Officer check as appropriate.]
___ (i) 52.204-17, Ownership or Control of Offeror.
___ (ii) 52.204-20, Predecessor of Offeror.
___ (iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
___ (iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to
Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Certification.
___ (v) 52.222-52 Exemption from Application of the Service Contract Labor Standards to
Contracts for Certain Services--Certification.
___ (vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for
EPA-Designated Products (Alternate I only).
___ (vii) 52.227-6, Royalty Information.
___ (A) Basic.
___ (B) Alternate I.
___ (viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The offeror has completed the annual representations and certifications electronically via the
SAM Web site accessed through https://www.acquisition.gov . After reviewing the SAM database information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date].
These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR Clause Title Date Change
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
52.223-1 Biobased Product Certification (MAY 2012)
As required by the Farm Security and Rural Investment Act of 2002 and the Energy Policy Act of 2005 ( 7 U.S.C. 8102(c)(3)), the offeror certifies, by signing this offer, that biobased products
(within categories of products listed by the United States Department of Agriculture in 7 CFR part 3201, subpart B) to be used or delivered in the performance of the contract, other than biobased products that are not purchased by the offeror as a direct result of this contract, will comply with the applicable specifications or other contractual requirements.
452.219-70 Size Standard and NAICS Code Information. (SEP 2001)
The North American Industrial Classification System Code(s) and business size standard(s) describing the products and/or services to be acquired under this solicitation are listed below:
Contract line item(s): All
- NAICS Code 237310 Highway, Street, and Bridge Construction
- Size Standard $39.5 million
Section L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS
52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
52.204-7 System for Award Management (OCT 2018)
52.215-1 Instructions to Offerors - Competitive Acquisition. (JAN 2017)
52.228-1 Bid Guarantee (SEPT 1996)
52.236-27 Site Visit (Construction) (FEB 1995)
52.216-1 Type of Contract. (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment
Opportunity for Construction. (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action
Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the
Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for Minority Participation for Each Trade
9.7 %
Goals for Female Participation for Each Trade
6.9 %, Nationwide
These goals are applicable to all of the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance
Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in
41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance
Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for
Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation.
The notification shall list the-
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
Yakima County Washington.
52.225-10 Notice of Buy American Requirement - Construction Materials. (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material,"
"domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials"
(Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the
Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR
52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers. (1) When an offer includes foreign construction material not listed by the
Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs
(c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested-
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
52.233-2 Service of Protest (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government
Accountability Office (GAO), shall be served on the Contracting Officer (addressed as indicated in Section 8 of the SF 1442) by obtaining written and dated acknowledgment of receipt from the
Contracting Officer.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
452.204-70 Inquiries. (FEB 1988)
Inquiries and all correspondence concerning this solicitation should be submitted in writing to the Contracting Officer. Offerors should contact only the Contracting Officer issuing the solicitation about any aspect of this requirement prior to contract award.
452.215-71 Instructions for the Preparation of Technical and Business Proposals (SEP
1999)
(a) General Instructions. Proposals submitted in response to this solicitation shall be furnished in the following format with the numbers of copies as specified below.
(1) The proposal must include a technical proposal and price proposal. Each of the parts shall be separate and complete so that evaluation of one may be accomplished independently from evaluation of the other. The technical proposal must not contain reference to cost; however, resource information (such as data concerning labor hours and categories, materials, subcontracts, etc.) must be contained in the technical proposal so that the contractor's understanding of the statement of work may be evaluated.
(2) Offerors shall not submit alternate proposals or proposals which deviate from the requirement.
(3) The Government will evaluate proposals in accordance with the evaluation criteria set forth in Section M of this RFP.
(4) Offerors shall submit their proposal(s) in the following format:
• Proposals shall be e-mailed to the following e-mail address:
trevor.b.mattson@usda.gov to the attention of the Contracting Officer Trevor
Mattson.
(b) Technical Proposal Instructions. The technical proposal will be used to make an evaluation and arrive at a determination as to whether the proposal will meet the requirements of the
Government.
Therefore, the technical proposal must present sufficient information to reflect a thorough understanding of the requirements and a detailed description of the techniques, procedures and programs for achieving the objectives of the specifications/statement of work. Proposals which merely paraphrase the requirements of the Government's specifications/statement of work, or use such phrases as "will comply" or "standard techniques will be employed" will be considered mailto:trevor.b.mattson@usda.gov unacceptable and will not be considered further. As a minimum, the proposal must clearly provide the following:
1. Technical capability to perform.
• Organization: Provide an experience statement that provides a description of comparable projects performed by the organization. Proposals shall include a list of key personnel for work on the project, including the project manager and other key employees, as well as proposed subcontractors to be assigned to the project, and detail their relevant licenses, certifications, and experience in the type of work to be done under this contract.
• Plan of Operations: Provide a narrative that describes how the work will be organized and managed so that all activities are completed in accordance with contract specifications and within the allotted contract time. At a minimum, provide a general plan for the sequence of work across the project, including all work items.
• Quality Control: Identify or describe your quality control and self-inspection procedures that will ensure objectives are being met during operations. The discussion of quality control should include the inspection system used to satisfy the requirements of the contract.
2. Past Performance: Offeror shall submit 3 references for projects of similar size, scope and dollar value (completed in the past 5 years) including company names and points of contact with current/verified telephone numbers and e-mail addresses.
(c) Price Proposal Instructions.
(1)Complete and submit price proposal per Section B – Schedule of Items.
452.237-71 Pre-Bid/Pre-Proposal Conference. (FEB 1988)
(a) The Government may host a pre-bid/pre-proposal conference upon request by proponents.
(b) Offerors shall submit all questions in writing at least fourteen days prior to the response due date. An amendment to the solicitation containing an abstract of the questions and answers will be disseminated within ten days of the due date. Questions shall be sent to Contracting Officer
Trevor Mattson at trevor.b.mattson@usda.gov and Program Engineer Cary Pence at cary.j.pence@usda.gov
(c) N/A.
(d) The Government assumes no responsibility for any expense incurred by an offeror prior to contract award.
(e) Offerors are cautioned that all terms and conditions of the solicitation remain unchanged unless they are changed by amendment to the solicitation. If the answers to questions, or any solicitation amendment, create ambiguities, it is the responsibility of the offeror to seek clarification prior to submitting an offer.
Section M - EVALUATION FACTORS FOR AWARD
52.217-5 Evaluation of Options (July 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
Award Determination
Award will be made to the Respondent whose proposal represent the best value to the government. Factors to be considered in determining the best value include such matters as price, experience and past performance.
Price is of equal importance compared to experience and past performance; however, the importance of price may become greater as the difference between experience and past mailto:trevor.b.mattson@usda.gov mailto:cary.j.pence@usda.gov performance decrease. Where experience and past performance are determined to be substantially equal, price may control the award.
The following factors and documents will be used for evaluation:
• Price – using Section B (Price Proposal)
• Past Performance (Technical Proposal)
• Experience – (Technical Proposal)
File details come from the government source that posted it. Updated .