Question regarding Solicitation 1282A720Q0070
Question 1:
On Page 1 it states “Period of Performance: 06/15/2020 to 07/10/2020” On Page 2 it states “Period of Performance: 06/01/2020 to 06/30/2020”
Which period of performance was intended, how was it determined and is it negotiable? But ultimately either period of performance is too short of a time frame for the project. Even if the project was awarded the day the bids are due the current lead time in manufacturing would be 6 weeks minimum and possibly longer.
The period of performance is negotiable. Period of Performance dates or time frames should be included in the quote
Question 2:
On Page 11 it states “Contractor shall complete the work in ten (10) calendar days”
How was this time frame determined and is it negotiable? For the amount of material being included on this project our installation timeframe would have to include more then 10 Calendar days and also take into account any unforeseen issues during the installation process that could extend the number of Calendar days to complete.
Again this was provided by the center, and I am sure that the time frame is negotiable. Period of Performance dates or time frames should be included in the quote