DORMITORY STOREFRONT REPLACEMENT 001500-1
FRENCHBURG JOB CORPS CCC LIST OF DRAWINGS AND SPECIFICATIONS
SECTION 001500
FRENCHBURG JOB CORPS CCC
DORMITORY STOREFRONT REPLACEMENT
LIST OF DRAWINGS AND SPECIFICATIONS
PART 1 – GENERAL
1.1 DESCRIPTION
A. List of Contract Drawings:
1. Index of Sheets:
SHEET NUMBER SHEET TITLE BUILDING NAME/NUMBER
T1.0 Title Sheet and Sheet Index
A1.1 Floor Plan Dormitory #1 – Building 137
A2.1 Floor Plan Dormitory #2 – Building 135
A3.1 Door and Window Types, Door Schedule, and Code Information
4 TOTAL SHEETS IN CONTRACT
DORMITORY STOREFRONT REPLACEMENT 001500-2
FRENCHBURG JOB CORPS CCC LIST OF DRAWINGS AND SPECIFICATIONS
B. List of Contract Specifications
1. Index of Specifications
DIVISION 1 - GENERAL REQUIREMENTS
Section 001500 List of Drawings and Specifications Section 010150
General Requirements
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
Section 079210
DIVISION 8 - OPENINGS
Section 084113 Section 087100 Section 088000
Joint Sealants
Aluminum-Framed Storefronts Door Hardware Glazing
END OF SECTION 001500
DORMITORY STOREFRONT REPLACEMENT 010150 – 1
FRENCHBURG JOB CORPS CCC GENERAL REQUIREMENTS
SECTION 010150
GENERAL REQUIREMENTS
PART 1 – SUMMARY OF WORK
1.1 DESCRIPTION
A. Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, utilities, miscellaneous items, freight and delivery and all necessary valid licenses and permits for the work summarized as follows:
1. Remove existing window and door storefront assemblies and install new storefront assemblies.
B. This project is located at the Frenchburg Job Corps Center. The campus is located approximately 10 miles from Frenchburg, KY. The address is: 6969 Tarr Ridge Rd, Frenchburg, KY 40322.
1.2 USE OF PREMISES
A. Use of Site: Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Full Government Occupancy: Government will occupy the building during the project.
Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations.
C. Driveways and Entrances: Keep driveways, parking areas, loading areas and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.3 PROJECT SCHEDULING
A. Schedule work to minimize impacts to government and students.
1.4 WORK RESTRICTIONS
A. Nonsmoking Buildings: Smoking is not permitted within the buildings or within 25 feet (8 m) of entrances, operable windows, or outdoor air intakes.
DORMITORY STOREFRONT REPLACEMENT 010150 – 2
1.5 CONTRACTOR’S RESPONSIBILITIES
A. Confine storage of materials to areas as approved by the CO.
B. Provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Minimize disturbance of all undisturbed areas.
1.6 FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
PART 2 – DEFINITION OF ITEMS AND PAYMENT
2.1 DESCRIPTION
A. This section explains what is and what is not included in each pay item; the limits or cut-off points where one item ends and another begins; and basis of payment for work items listed in the Schedule of Items.
B. Payment: For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications, and as shown on the drawings.
2.2 SCHEDULE OF ITEMS
A. Schedule of Items: The project Schedule of Items includes several sections to organize the work into Base Items and Optional Items.
1. Provide pricing for all items listed in the Schedule of Items.
2. Contract award will be made for all Base Items.
3. Optional Items will be awarded based on available project funding.
B. Base Items (BI):
1. Base Item No. 1- Dormitory 1 (Bldg 137) Storefront Replacement
a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, demolition, labor and incidentals to install remove the existing window and door storefront assemblies and install new storefront assemblies.
C. Optional Items (OI):
1. Optional Item No. 1- Dormitory 2 (Bldg 135) Storefront Replacement
a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, demolition, labor and incidentals to install
DORMITORY STOREFRONT REPLACEMENT 010150 – 3
remove the existing window and door storefront assemblies and install new storefront assemblies.
PART 3 – ACCIDENT PREVENTION
3.1 DESCRIPTION
A. This section consists of establishing an effective accident prevention plan and providing a safe environment for personnel and visitors.
3.2 SUBMITTALS
A. Accident Prevention Plan: Before on-site work begins, submit a company approved accident prevention plan. This plan will be posted in the contract file. Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project. Notice to proceed will not be made until the plan is received. As a minimum the plan shall include:
1. Name, position title and contact information of company executive responsible for approving the Accident Prevention Plan.
2. Name and contact information of supervisor responsible to carry out the plan.
3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
4. Contingency plans for emergency situations such as medical, fire, hazard material spills and other contract assessed hazard prevention and abatement requirement needs that apply to this project.
B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
D. Submit a brief report of safety meetings and of inspections.
E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
3.3 QUALITY ASSURANCE
A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions: In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
DORMITORY STOREFRONT REPLACEMENT 010150 – 4
B. Qualifications of Employees: Ensure employees are physically qualified to perform assigned duties in a safe manner.
3.4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 calendar days of a reportable accident, fill out and forward to the CO a CA-1 form, which may be obtained from CO.
B. All Other Accidents: Report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.
3.5 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
3.6 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
3.7 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.8 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition.
Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.9 SAFETY MEETINGS
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
3.10 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. The CO will designate a hard hat area. Post the hard hat area in a manner satisfactory to the CO.
DORMITORY STOREFRONT REPLACEMENT 010150 – 5
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide two hard hats for use by visitors. Change liners before reissuing hats.
3.11 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
PART 4 – SUBMITTAL PROCEDURES
4.1 DESCRIPTION
A. This section includes administrative and procedural requirements for submittals.
4.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Contracting Officer’s (CO's) responsive action.
B. Informational Submittals: Written information that does not require CO's approval.
Submittals may be rejected for not complying with requirements.
4.3 PROCEDURES
A. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 10 working days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 10 working days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
B. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately 2 by 3 inches on label or beside title block to record
Contractor's review and approval markings and action taken by CO.
DORMITORY STOREFRONT REPLACEMENT 010150 – 6
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. Other necessary identification.
C. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
D. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
E. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
F. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
G. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
H. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
I. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
4.4 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit four copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
DORMITORY STOREFRONT REPLACEMENT 010150 – 7
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
4.5 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit two copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
B. Contractor's Construction Schedule: Provide a construction schedule.
C. Cost Breakdown: Following award provide a cost breakdown schedule listing main types of work with associated costs for each bid item.
PART 5 – TEMPORARY FACILITIES AND CONTROLS
5.1 DESCRIPTION
A. This section consists of requirements for temporary facilities and controls, including utilities, support facilities, and security and protection facilities.
5.2 UTILITIES
A. Water Service: Use of Government existing water service facilities will be permitted without metering and without payment of use charges, as long as facilities are cleaned and maintained in a condition acceptable to CO. At Substantial Completion, restore these facilities to condition existing before initial use.
DORMITORY STOREFRONT REPLACEMENT 010150 – 8
B. Sanitary Facilities: Use of Government sanitary facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to CO. At Substantial Completion, restore these facilities to condition existing before initial use.
C. Electric Power and Lighting Service: Use of Government's existing electric power and lighting service will be permitted without metering and without payment of use charges, as long as equipment is maintained in a condition acceptable to CO.
D. Telephone Service: The Contractor is responsible for providing telephone service deemed necessary for the duration of the construction.
5.3 STORAGE AREAS
A. Coordinate on-site storage requirements with the Contracting Officer.
5.4 CONSTRUCTION WASTE DISPOSAL FACILITIES
A. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste.
5.5 SUPPORT FACILITIES INSTALLATION
A. Locate temporary construction and support facilities for easy access.
5.6 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects. Restrict use of noisemaking tools and equipment to hours that will minimize complaints from persons or firms near Project site.
B. Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erecting structurally adequate barricades. Paint with appropriate colors, graphics, and warning signs to inform personnel and public of possible hazard. Where appropriate and needed, provide lighting, including flashing red or amber lights.
C. Fire Protection:
1. Store combustible materials in containers in fire-safe locations.
2. Maintain unobstructed access to fire extinguishers, fire hydrants, fire-protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.
3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.
DORMITORY STOREFRONT REPLACEMENT 010150 – 9
PART 6 – EXECUTION REQUIREMENTS
6.1 DESCRIPTION
A. This section consists of general procedural requirements governing execution of the Work including, but not limited to, the following:
1. General installation of products.
2. Progress cleaning.
3. Protection of installed construction.
4. Correction of the Work.
6.2 EXAMINATION
A. Existing Conditions: Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work.
B. Acceptance of Conditions: Examine areas, and conditions, with Installer. Record observations.
1. Examine roughing-in for electrical systems to verify actual locations of connections before equipment and fixture installation.
2. Proceed with installation only after unsatisfactory conditions have been corrected.
Proceeding with the Work indicates acceptance of surfaces and conditions.
6.3 PREPARATION
A. Field Measurements: Take field measurements as required to fit the Work properly.
B. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO.
Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.
6.4 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
1. Make vertical work plumb and make horizontal work level.
B. Comply with manufacturer's written instructions and recommendations for installing products.
C. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.
6.5 PROGRESS CLEANING
DORMITORY STOREFRONT REPLACEMENT 010150 – 10
A. General: Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.
1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.
2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).
3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.
D. Waste Disposal: Burying or burning waste materials on-site will not be permitted.
Washing waste materials down sewers or into waterways will not be permitted.
6.6 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
6.7 CORRECTION OF THE WORK
A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.
1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.
PART 7 – CLOSEOUT PROCEDURES
7.1 DESCRIPTION
A. This section consists of administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Inspection procedures.
2. Project Record Documents.
3. Final cleaning.
7.2 SUBSTANTIAL COMPLETION
A. Definition of Substantial Completion: The Date certified by the Contracting Officer when construction is sufficiently complete, in accordance with the Contract Documents, DORMITORY STOREFRONT REPLACEMENT 010150 – 11 so the Government can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.
B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.
1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.
2. Advise Contracting Officer (CO) of pending insurance changeover requirements.
3. Submit specific warranties, workmanship bonds, final certifications, and similar documents.
4. Obtain and submit releases permitting Government unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.
5. Prepare and submit Project Record Documents, operation and maintenance manuals, Final Completion construction photographs and photographic negatives, and similar final record information.
6. Complete startup testing of systems.
7. Complete final cleaning requirements, including touchup painting.
8. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.
C. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by CO, that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
2. Results of completed inspection will form the basis of requirements for Final Completion.
7.3 FINAL COMPLETION
A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:
1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.
2. Submit evidence of final, continuing insurance coverage complying with insurance requirements.
3. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.
DORMITORY STOREFRONT REPLACEMENT 010150 – 12
B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
7.4 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.
7.5 PROJECT RECORD DOCUMENTS
A. General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for CO's reference during normal working hours.
B. Record Drawings: Maintain and submit one set of blue- or black-line white prints of Contract Drawings and Shop Drawings.
1. Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.
a. Give particular attention to information on concealed elements that cannot be readily identified and recorded later.
b. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.
2. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location.
3. Note Construction Change Directive numbers, Change Order numbers, alternate numbers, and similar identification where applicable.
4. Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. Organize into manageable sets;
bind each set with durable paper cover sheets. Include identification on cover sheets.
7.6 FINAL CLEANING
DORMITORY STOREFRONT REPLACEMENT 010150 – 13
A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.
B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.
C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:
1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.
2. Remove tools, construction equipment, machinery, and surplus material from Project site.
3. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.
Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.
D. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on Government property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully.
END OF SECTION 010150
DORMITORY STOREFRONT REPLACEMENT 010150 – 14
THIS PAGE IS INTENTIONALLY LEFT BLANK
DORMITORY STOREFRONT REPLACEMENT 079210-1
FRENCHBURG JOB CORPS CCC JOINT SEALANTS
SECTION 079210
JOINT SEALANTS
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes sealants for the following applications, including those specified by reference to this Section:
1. Exterior joints in the following vertical surfaces and nontraffic horizontal surfaces:
a. Joints between different materials indicated.
b. Perimeter joints between materials listed above and frames of windows.
c. Other joints as indicated.
2. Interior joints in the following vertical surfaces and horizontal nontraffic surfaces:
1. Perimeter joints of exterior openings where indicated.
2. Perimeter joints between interior wall surfaces and frames of interior windows.
3. Other joints as indicated.
1.2 PERFORMANCE REQUIREMENTS
A. Provide elastomeric joint sealants that establish and maintain watertight and airtight continuous joint seals without staining or deteriorating joint substrates.
1.3 SUBMITTALS
A. Source Limitations: Obtain each type of joint sealant through one source from a single manufacture.
1.4 QUALITY ASSURANCE
A. Deliver materials to Project site in original unopened containers or bundles with labels indicating manufacturer, product name and designation, color, expiration date, pot life, curing time, and mixing instructions for multicomponent materials.
B. Store and handle materials in compliance with manufacturer's written instructions to prevent their deterioration or damage due to moisture, high or low temperatures, contaminants, or other causes.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Environmental Limitations: Do not proceed with installation of joint sealants under the following conditions:
1. When ambient and substrate temperature conditions are outside limits permitted by joint sealant manufacturer.
DORMITORY STOREFRONT REPLACEMENT 079210-2
2. When ambient and substrate temperature conditions are outside limits permitted by joint sealant manufacturer or are below 40 deg F.
3. When joint substrates are wet.
B. Joint-Width Conditions: Do not proceed with installation of joint sealants where joint widths are less than those allowed by joint sealant manufacturer for applications indicated.
C. Joint-Substrate Conditions: Do not proceed with installation of joint sealants until contaminants capable of interfering with adhesion are removed from joint substrates.
PART 2 – PRODUCTS
2.1 MATERIALS, GENERAL
A. Silicone containing products are not allowed.
B. Compatibility: Provide joint sealants, backings, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by sealant manufacturer based on testing and field experience.
C. Colors of Exposed Joint Sealants: Manufacturer’s standard color that is the closest to the lightest adjacent substrate.
2.2 ELASTOMERIC JOINT SEALANTS
A. Elastomeric Sealant Standard: Comply with ASTM C 920 and other requirements indicated for each liquid-applied chemically curing sealant in the Elastomeric Joint-Sealant Schedule at the end of Part 3, including those referencing ASTM C 920 classifications for type, grade, class, and uses.
1. Multicomponent Nonsag Urethane Products: Unless otherwise directed by the Contracting Officer (CO), provide products by one of the following:
a. Vulkem 922; Mameco International.
b. Dynatrol II; Pecora Corporation.
c. Flexiprene 2000; Polymeric Systems, Inc.
d. Sikaflex - 2c NS; Sika Corporation.
e. NP 2; Sonneborn Building Products Div., ChemRex Inc.
f. Dymeric 511; Tremco.
2. Type and Grade: M (multicomponent) and NS (nonsag).
3. Class: 25.
4. Additional Movement Capability: 50 percent movement in extension and
50 percent in compression for a total of 100 percent movement.
5. Use Related to Exposure: NT (nontraffic).
6. Uses Related to Joint Substrates: M, G, A, and, as applicable to joint substrates indicated, O.
DORMITORY STOREFRONT REPLACEMENT 079210-3
a. Use O Joint Substrates: Color anodic aluminum, galvanized steel, and ceramic tile.
B. Additional Movement Capability: Where additional movement capability is specified in the Elastomeric Joint-Sealant Schedule, provide products with the capability, when tested for adhesion and cohesion under maximum cyclic movement per ASTM C 719, to withstand the specified percentage change in the joint width existing at the time of installation and remain in compliance with other requirements of ASTM C 920 for uses indicated.
C. Stain-Test-Response Characteristics: Where elastomeric sealants are specified in the Elastomeric Joint-Sealant Schedule to be nonstaining to porous substrates, provide products that have undergone testing according to ASTM C 1248 and have not stained porous joint substrates indicated for Project.
2.3 LATEX JOINT SEALANTS
a. Latex Sealant Standard: Comply with ASTM C 834.
1. Products: Unless otherwise directed by the CO, provide products by one of the following:
a. Chem-Calk 600; Bostik Inc.
b. NuFlex 330; NUCO Industries, Inc.
c. LC 160 All Purpose Acrylic Caulk; Ohio Sealants, Inc.
d. AC-20; Pecora Corporation.
e. PSI-701; Polymeric Systems, Inc.
f. Sonolac; Sonneborn Building Products Div., ChemRex, Inc.
g. Tremflex 834; Tremco.
2.4 JOINT-SEALANT BACKING
A. General: Provide sealant backings of material and type that are nonstaining; are compatible with joint substrates, sealants, primers, and other joint filers; and are approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.
B. Cylindrical Sealant Backings: ASTM C 1330, of type indicated below and of size and density to control sealant depth and otherwise contribute to producing optimum sealant performance:
1. Type C: Closed-cell material with a surface skin.
C. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer for preventing sealant from adhering to rigid, inflexible joint-filler materials or joint surfaces at back of joint where such adhesion would result in sealant failure. Provide self-adhesive tape where applicable.
2.5 MISCELLANEOUS MATERIALS
DORMITORY STOREFRONT REPLACEMENT 079210-4
A. Primer: Material recommended by joint sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.
B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials, free of oily residues or other substances capable of staining or harming joint substrates and adjacent nonporous surfaces in any way, and formulated to promote optimum adhesion of sealants with joint substrates.
C. Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints. Leave no residue.
PART 3 – EXECUTION
3.1 EXAMINATION
A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with requirements for joint configuration, installation tolerances, and other conditions affecting joint-sealant performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint sealant manufacturer's written instructions and the following requirements:
1. Remove all foreign material from joint substrates that could interfere with adhesion of joint sealant, including dust, paints (except for permanent, protective coatings tested and approved for sealant adhesion and compatibility by sealant manufacturer), old joint sealants, oil, grease, waterproofing, water repellents, water, surface dirt, and frost.
2. Clean porous joint substrate surfaces by brushing, grinding, blast cleaning, mechanical abrading, or a combination of these methods to produce a clean, sound substrate capable of developing optimum bond with joint sealants. Remove loose particles remaining from above cleaning operations by vacuuming or blowing out joints with oil-free compressed air. Porous joint surfaces include the following:
3. Remove laitance and form-release agents from concrete.
a. Concrete.
b. Masonry.
4. Clean nonporous surfaces with chemical cleaners or other means that do not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants.
a. Metal.
DORMITORY STOREFRONT REPLACEMENT 079210-5
b. Glass.
B. Joint Priming: Prime joint substrates where recommended in writing by joint sealant manufacturer, based on preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.
C. Masking Tape: Use masking tape where required to prevent contact of sealant with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears.
Remove tape immediately after tooling without disturbing joint seal.
3.3 INSTALLATION OF JOINT SEALANTS
A. General: Comply with joint sealant manufacturer's written installation instructions for products and applications indicated, unless more stringent requirements apply.
B. Sealant Installation Standard: Comply with recommendations of ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.
C. Install sealant backings of type indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.
1. Do not leave gaps between ends of sealant backings.
2. Do not stretch, twist, puncture, or tear sealant backings.
3. Remove absorbent sealant backings that have become wet before sealant application and replace them with dry materials.
D. Install bond-breaker tape behind sealants where sealant backings are not used between sealants and back of joints.
E. Install sealants by proven techniques to comply with the following and at the same time backings are installed:
1. Place sealants so they directly contact and fully wet joint substrates.
2. Completely fill recesses provided for each joint configuration.
3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow optimum sealant movement capability.
F. Tooling of Nonsag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.
1. Remove excess sealants from surfaces adjacent to joint.
2. Use tooling agents that are approved in writing by sealant manufacturer and that do not discolor sealants or adjacent surfaces.
DORMITORY STOREFRONT REPLACEMENT 079210-6
3. Provide concave joint configuration per Figure 5A in ASTM C 1193, unless otherwise indicated.
G. Installation of Preformed Expanding Foam Sealants: Install each length of sealant immediately after removing protective wrapping, taking care not to pull or stretch material, producing seal continuity at ends, turns, and intersections of joints. For applications at low ambient temperatures where expansion of sealant requires acceleration to produce seal, apply heat to sealant in compliance with sealant manufacturer's written instructions.
3.4 CLEANING
A. Clean off excess sealants or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.
3.5 PROTECTION
A. Protect joint sealants during and after curing period from contact with contaminating substances and from damage resulting from construction operations or other causes so sealants are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated joint sealants immediately so installations with repaired areas are indistinguishable from the original work.
3.6 JOINT-SEALANT SCHEDULE
A. Multicomponent Nonsag Urethane Sealant
1. Applications: Exterior use.
B. Latex Sealant:
1. Applications: Interior use.
END OF SECTION 079210
DORMITORY STOREFRONT REPLACEMENT 084113 - 1
FRENCHBURG JOB CORPS CCC ALUMINUM-FRAMED STOREFRONT WINDOWS
SECTION 084113
ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Exterior aluminum-framed storefronts.
a. Glazing is retained mechanically with gaskets on four sides.
2. Exterior manual-swing aluminum doors.
1.2 RELATE WORK SPECIFICED ELSEWHERE
A. See Division 8 Section “Glazing” for glass to be installed in storefront systems.
1.3 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with requirements in U.S. Access Board’s “ADA/ABA Accessibility Guidelines” for plumbing fixtures for people with disabilities.
1.4 PERFORMANCE REQUIREMENTS
A. General: Provide aluminum-framed systems, including anchorage, capable of with-standing, without failure, the effects of the following:
1. Structural loads.
2. Thermal movements.
3. Movements of supporting structure indicated on Drawings including, but not limited to, deflection from uniformly distributed and concentrated live loads.
4. Dimensional tolerances of building frame and other adjacent construction.
5. Failure includes the following:
a. Deflection exceeding specified limits.
b. Thermal stresses transferred to building structure.
c. Framing members transferring stresses, including those caused by thermal and structural movements, to glazing.
d. Noise or vibration created by wind and thermal and structural movements.
e. Loosening or weakening of fasteners, attachments, and other components.
f. Sealant failure.
g. Failure of operating units to function properly.
B. Structural Loads:
DORMITORY STOREFRONT REPLACEMENT 084113 - 2
1. Wind Loads: 90 mph.
2. Importance Factor: II.
3. Exposure Category: C.
C. Deflection of Framing Members Normal to Wall Plane: Limited to 1/175 of clear span for spans up to 13 feet 6 inches (4.1 m) and to 1/240 of clear span plus 1/4 inch (6.35 mm) for spans greater than 13 feet 6 inches (4.1 m) or an amount that restricts edge deflection of individual glazing lites to 3/4 inch (19 mm), whichever is less.
D. Structural-Test Performance: Systems tested according to ASTM E 330 as follows:
1. When tested at positive and negative wind-load design pressures, systems do not evidence deflection exceeding specified limits.
2. When tested at 150 percent of positive and negative wind-load design pressures, systems, including anchorage, do not evidence material failures, structural dis-tress, and permanent deformation of main framing members exceeding 0.2 per-cent of span.
3. Test Durations: As required by design wind velocity but not less than 10 sec-onds.
E. Temperature Change (Range): Systems accommodate 120 deg F (67 deg C), ambient;
180 deg F (100 deg C), material surfaces.
F. Air Infiltration: Maximum air leakage through fixed glazing and framing areas of sys-tems of 0.06 cfm/sq. ft. (0.03 L/s per sq. m) of fixed wall area when tested according to ASTM E 283 at a minimum static-air-pressure difference of 6.24 lbf/sq. ft. (300 Pa).
G. Water Penetration Under Static Pressure: Systems do not evidence water penetration through fixed glazing and framing areas when tested according to ASTM E 331 at a minimum static-air-pressure difference of 20 percent of positive wind-load design pressure, but not less than 6.24 lbf/sq. ft. (300 Pa).
H. Condensation Resistance: Fixed glazing and framing areas of systems have condensa-tion-resistance factor (CRF) of not less than 53 when tested according to
AAMA 1503.
I. Average Thermal Conductance: Fixed glazing and framing areas of systems have av-erage U-factor of not more than 0.50 U-factor when tested according to AAMA 1503.
J. Solar Heat Gain Coefficient: 0.58 maximum.
1.5 SUBMITTALS
A. Within 10 days after the Notice To Proceed, furnish a shop drawing showing all exist-ing conditions, which shall include the existing storefront dimensions, thicknesses, glazing types and thickness, and description of existing entry/lock system. Furnish a separate drawing for each dormitory.
DORMITORY STOREFRONT REPLACEMENT 084113 - 3
B. Product Data: For each type of product indicated.
C. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work.
1. For entrances, include hardware schedule and indicate operating hardware types, functions, quantities, and locations.
D. Color and finish Samples: For each exposed finish.
E. Product test reports.
F. Sample Warranties.
1.6 CLOSEOUT SUBMITTALS
A. Final Warranties.
1.7 QUALITY ASSURANCE
A. Installer Qualifications: Acceptable to manufacturer and capable of preparation of da-ta for aluminum-framed systems including Shop Drawings based on testing and engi-neering analysis of manufacturer's standard units in assemblies similar to those indi-cated for this Project.
1.8 WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to re-pair or replace components of aluminum-framed systems that do not comply with re-quirements or that fail in materials or workmanship within specified warranty period.
1. Warranty Period: Two years from date of Substantial Completion.
B. Special Finish Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components on which finishes do not comply with requirements or that fail in materials or workmanship within specified warranty period. Warranty does not include normal weathering.
1. Warranty Period: Five years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Available Manufacturers: Subject to compliance with requirements, manufacturers of-fering products that may be incorporated into the Work include, but are not limited to, the following:
1. Kawneer.
DORMITORY STOREFRONT REPLACEMENT 084113 - 4
2. Tubelite Inc.
3. United States Aluminum.
4. OldCastle Building Envelope.
B. Basis of Design: EnCORE Window Framing Series by Kawneer.
2.2 MATERIALS
A. Aluminum Extrusions: Alloy and temper recommended by aluminum storefront man-ufacturer for strength, corrosion resistance, and application of required finish and not less than 0.070" (1.8 mm) wall thickness at any location for the main frame and com-plying with ASTM B 221: 6063-T6 alloy and temper.
B. Fasteners: Aluminum, nonmagnetic stainless steel or other materials to be non-corrosive and compatible with aluminum members, trim hardware, anchors, and other components.
C. Anchors, Clips, and Accessories: Aluminum, nonmagnetic stainless steel, or zinc-coated steel or iron complying with ASTM B 633 for SC 3 severe service conditions or other suitable zinc coating; provide sufficient strength to withstand design pressure indicated.
D. Reinforcing Members: Aluminum, nonmagnetic stainless steel, or nickel/chrome-plated steel complying with ASTM B 456 for Type SC 3 severe service conditions, or zinc-coated steel or iron complying with ASTM B 633 for SC 3 severe service condi-tions or other suitable zinc coating; provide sufficient strength to withstand design pressure indicated.
E. Sealant: For sealants required within fabricated storefront system, provide permanent-ly elastic, non-shrinking, and non-migrating type recommended by sealant manufac-turer for joint size and movement.
F. Thermal Barrier: A minimum 1/4" (6.4) separation between the interior and exterior aluminum created by intermittent polymer clips.
G. Tolerances: Reference to tolerances for wall thickness and other cross-sectional di-mensions of storefront members are nominal and in compliance with AA Aluminum Standards and Data.
H. Finish: Bronze, as selected from manufacturer’s full range.
2.3 FRAMING SYSTEMS
A. Brackets and Reinforcements: Manufacturer's standard high-strength aluminum with nonstaining, nonferrous shims for aligning system components.
DORMITORY STOREFRONT REPLACEMENT 084113 - 5
B. Fasteners and Accessories: Manufacturer's standard corrosion-resistant, nonstaining, nonbleeding fasteners and accessories compatible with adjacent materials. Where ex-poses shall be stainless steel.
C. Perimeter Anchors: When steel anchors are used, provide insulation between steel material and aluminum material to prevent galvanic action
D. Packing, Shipping, Handling and Unloading: Deliver materials in manufacturer's orig-inal, unopened, undamaged containers with identification labels intact.
E. Storage and Protection: Store materials protected from exposure to harmful weather conditions. Handle storefront material and components to avoid damage. Protect store-front material against damage from elements, construction activities, and other hazards before, during and after storefront installation.
2.4 GLAZING SYSTEMS
A. Glazing: As specified in Division 8 Section "Glazing."
B. Glazing Gaskets: Manufacturer's standard compression types, replaceable, molded or extruded EPDM rubber,that maintains uniform pressure and watertight seal.
C. Spacers and Setting Blocks: Manufacturer's standard elastomeric types.
D. Bond-Breaker Tape: Manufacturer's standard TFE-fluorocarbon or polyethylene ma-terial to which sealants will not develop adhesion.
E. Glazing Sealants: For structural-sealant-glazed systems, as recommended by manu-facturer for joint type, and as follows:
1. Structural Sealant: ASTM C 1184, single-component neutral-curing silicone formulation that is compatible with system components with which it comes in contact, specifically formulated and tested for use as structural sealant and ap-proved by a structural-sealant manufacturer for use in aluminum-framed systems indicated.
a. Color: Bronze.
2. Weatherseal Sealant: ASTM C 920 for Type S, Grade NS, Class 25, Uses NT, G, A, and O; single-component neutral-curing formulation that is compatible with structural sealant and other system components with which it comes in con-tact; recommended by structural-sealant, weatherseal-sealant, and aluminum-framed-system manufacturers for this use.
a. Color: Matching structural sealant.
2.5 DOORS
A. Doors: Manufacturer's standard glazed doors, for manual swing operation.
1. Door Construction: 1-3/4-inch (44.5-mm) overall thickness, with minimum 0.125-inch- (3.2-mm) extruded-aluminum tubular rail and stile members. Me-
DORMITORY STOREFRONT REPLACEMENT 084113 - 6
chanically fasten corners with reinforcing brackets that are deep penetration and fillet welded or that incorporate concealed tie rods.
2. Door Design: Narrow stile; 2-1/2-inch nominal width.
a. Accessible Doors: Smooth surfaced for width of door in area within 10…