This document is a Request for Proposals (RFP) for a Firm Fixed-Price construction contract to improve restroom sites at nine locations in the Coronado National Forest in Arizona. The planned work includes reinforced concrete low water crossing, concrete block retaining wall, reinforced concrete sidewalks, decomposed granite pad and walking path, pedestal grills, picnic tables, and water hydrants with accompanying concrete pad and drain pit.

This is a 100% Small Business Set Aside under NAICS code 237310 for Highway, Street, and Bridge Construction with a project magnitude between $250,000 and $500,000. The period of performance is from 09/06/2024 to 09/05/2025 or 120 days after notice to proceed. Proposals are due by 1300 Central Daylight Time on 08/30/2024 and should be emailed to the Contract Specialist. A site visit is scheduled for 08/06/2024. Davis Bacon wage rates apply and the Government anticipates awarding a Firm Fixed-Price contract using a LPTA evaluation.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Introduction: The USDA Forest Service, Coronado National Forest, has a requirement to improve restroom sites at nine (9) locations around the Forest. The site improvements include reinforced concrete low water crossing, concrete block retaining wall, reinforced concrete sidewalks, decomposed granite pad and walking path, pedestal grills, picnic tables, and water hydrants with accompanying concrete pad and drain pit.

Location:

Work will take place at nine (9) sites throughout the Coronado National Forest in Arizona.

1. Sabino Canyon Turnaround: Physical address 5700 N Sabino Canyon Rd., Tucson, AZ 85750. Restroom is located within the Sabino Canyon Recreation Area behind locked gate and is only accessible with a FS escort. Pima County. Township 13 South, Range 15 East & Section 9.

Latitude: 32.313399°; Longitude: -110.812124°.

2. Proctor: From Tucson, Arizona, travel south on I-19 for approximately thirty-five (35) miles to the Continental Road exit (Exit 63) in Green Valley, Arizona. Turn left (east) on Continental Road and go approximately one (1) mile to the junction with the Madera Canyon/White House Canyon Road. Turn right (southwest) and travel approximately eleven (11) miles to the entrance of the Proctor Picnic Area. Santa Cruz County. Township 19 South, Range 14 East & Section 35.

Latitude: 31.7411409°; Longitude: -110.886831°.

3. Whitehouse: From Tucson, Arizona, travel south on I-19 for approximately thirty-five (35) miles to the Continental Road exit (Exit 63) in Green Valley, Arizona. Turn left (east) on Continental Road and go approximately one (1) mile to the junction with the Madera Canyon/White House Canyon Road. Turn right (southwest) and travel approximately twelve (12) miles to the Whitehouse Picnic Area. Santa Cruz County. Township 19 South, Range 14 East & Section 35. Latitude: 31.73347°; Longitude: -110.882538°.

4. Madera Trailhead: From Tucson, Arizona, travel south on I-19 for approximately thirty-five

(35) miles to the Continental Road exit (Exit 63) in Green Valley, Arizona. Turn left (east) on Continental Road and go approximately one (1) mile to the junction with the Madera Canyon/White House Canyon Road. Turn right (southwest) and travel approximately thirteen

(13) miles to the Madera Picnic Area on left hand side. Santa Cruz County. Township 19 South, Range 14 East & Section 35. Latitude: 31.726888°; Longitude: -110.88040°.

5. Parker Canyon Lake: From Tucson, travel east on Interstate 10 to State Route 83 (exit 281) and turn south fifty (50) miles through Sonoita to Parker Canyon Lake. Restroom is the one closest to the store. Cochise County. Township 23 South, Range 19 East & Section 18. Latitude:

31.424424°; Longitude: -110.448622°.

6. Cochise Stronghold: From Tucson, take 1-10 east for approximately seventy-two (72) miles to US 191. Turn right (south) on US 191 and drive eighteen (18) miles to Ironwood Road. Turn right (west) on Ironwood Road and drive about nine (9) miles to the Cochise Stronghold Campground and the Cochise Trailhead. Restroom is at end of campground. Cochise County.

Township 17 South, Range 23 East & Section 26. Latitude: 31.9220098°; Longitude: - 109.9675653°.

7. Rustler Park: From Tucson, take I-10 east eighty-one (81) miles. Turn right (south) on AZ 186 and continue for thirty-three (33) miles. Turn left (east) on AZ 181 toward Chiricahua National Monument and drive three (3) miles, then turn right (south) on Forest Road 42.

Continue up FR 42 (Pinery Canyon) twelve (12) miles to Forest Road 42D. Turn right at Onion Saddle and drive approximately 2.5 miles to Rustler Park Campground. Restroom is located at the end of campground loop. Cochise County. Township 17 South, Range 30 East & Section 33.

Latitude: 31.9051°; Longitude: -109.27985°.

8. Upper Arcadia: From Tucson, Arizona: Take I-10 east for ninety (90) miles. Take exit 352 for US 191 and turn left toward Safford. Drive 26.3 miles north and turn left on AZ 366/Swift Trail. Turn left (southwest) onto AZ 366 and drive 11.6 miles. Turn right on the road 0.1 mile past the entrance to Arcadia Campground. Graham County. Township 9 South, Range 25 East & Section 18. Latitude: 32.6483762°; Longitude: -109.820315°.

9. Noon Creek: From Tucson, Arizona: Take I-10 east for ninety (90) miles. Take exit 352 for US 191 and turn left toward Safford. Drive 26.3 miles north and turn left on AZ 366/Swift Trail.

Turn left (southwest) onto AZ 366 and drive approximately seven (7) miles. The picnic area is on the right-hand side of the road. Graham County. Township 9 South, Range 25 East & Section

9. Latitude: 32.6682°; Longitude: - 109.79669°.

Type of Award. As a result of this solicitation, the Government anticipates awarding a Firm Fixed-Price construction contract.

This is 100% Small Business Set Aside under NAICS code 237310 Highway, Street, and Bridge Construction, Small Business Size Standard $45M, PSC code of Z2QA.

Project Magnitude: Between $250,000.00 and $500,000.

Period of Performance: 09/06/2024 – 09/05/2025 or 120 days after notice to proceed (NTP).

Wage Rates:

General Wage Rate Decision Number: AZ20240038 State and County: Cochise, Graham, Santa Catalina, Santa Cruz, Arizona Construction Type: Building

Bonds:

Payment, Performance and Bid Bonds are required.

Instruction to Offerors:

Before submitting a proposal or any questions regarding the solicitation, please read the entire solicitation package carefully. Submit your proposal and questions via email to the contract specialist. Mailed/hard copy proposals will not be accepted. Return the following items with your response:

Official Proposal Technical Proposal

Schedule of Items (Pricing Proposal) Acknowledgment of any/all Amendments to Solicitation

Interested contractors must be registered in SAM (System for Award Management, www.sam.gov) and complete online representations and certifications before the solicitation response due date.

Format for Proposals:

1. Proposals shall be 8 ½” x 11”

2. A page is defined as one face of a sheet of paper containing information

3. Typing shall not be less than 12 pitches (Times New Roman/Ariel/Etc.), 1-inch border, no artistic script fonts for readability

4. Elaborate formats, bindings or color presentations are not desired or required

List of Attachments:

1. Statement of Work

2. Specifications

3. BioPreferred

4. Fire Precaution Plan

5. Restroom Site Improvements East Drawings

6. Restroom Site Improvements Medera Drawings

7. Restroom Site Improvements Sabino Turnaround Drawings

8. Wage Determination #AZ20240038

9. Wage Determination #AZ20240040

10. Wage Determination #20240025

11. Wage Determination #20240028

For Further Information:

Solicitation Contact Information: Troy McCullough will be the main point of contact for this solicitation and can be reached at troy.mccullough@usda.gov.

The Deadline for receipt of responses to the RFQ shall be August 30, 2024, 1300 Central Daylight Time. Response to the RFQ shall be sent to the Contract Specialist. Response packages should be sent by email and should contain the Solicitation Number 127EAX24R0024 in the subject line of the email. Contract Specialist Email: troy.mccullough@usda.gov

Site Visit Information:

Site Visit Date: August 6th, 2024 at 1300 Local Time. Location TBD.

Questions Due Date: August 13th, 2024 by 1300 Central Daylight Time

Any and all questions shall be submitted via email only; no verbal questions will be accepted. Please be sure to include the solicitation number in your proposal and in the subject line of any email submitted.

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1128112

SOUTHWESTERN REGION

333 BROADWAY SE

ALBUQUERQUE NM 87102

Troy McCullough

Contract Specialist US Forest Service

TROY MCCULLOUGH

1x 07/30/2024

127EAX24R0024

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Work associated with this project shall consist of improving restroom sites at nine

(9) locations around the Forest. The site improvements include reinforced concrete low water crossing, concrete block retaining wall, reinforced concrete sidewalks, decomposed granite pad and walking path, pedestal grills, picnic tables, and water hydrants with accompanying concrete pad and drain pit.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 120 calendar days and complete it within ________________ ________________ calendar days after receiving

08/30/2024

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

SOUTHWESTERN REGION

333 BROADWAY SE

ALBUQUERQUE NM 87102

MICHELLE L. BAHR

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 41

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

127EAX24R0024

Davis Bacon wages apply.

The government anticipates awarding a firm-fixed price contract using RFQ LPTA.

The magnitude of this project is between $250,000 and $500,000.

Offers or responses to the solicitation (include the solicitation number in the name of the document) should be sent to the contracting specialist by email; troy.mccullough@usda.gov before the deadline.

Delivery Location Code: AMS-FV-PACAAZ-9JF8

FV PACA TUCSON AZ

300 WEST CONGRESS STREET

BOX 30 FEDERAL BLDG ROOM 7T

TUCSON AZ 85701-1319 US

FOB: Destination

Period of Performance: 09/06/2024 to 09/05/2025

0001 All improvments at nine sites

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice

Processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in the previous communications from USDA and Treasury.

All invoices are to be submitted via the electronic Invoice Processing Platform. This is a mandatory requirement initiated by the U.S.

Department of Treasury and you can find more information at this website https://www.ipp.gov/index.html.

Please make sure that your company has registered at https://www.ipp.gov/vendors/enrollment-vendors.htm l to establish your account.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation No: 127EAX24R0024 Project Name: Coronado Nation Forest Restroom Repairs

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATION

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III—LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J—LIST OF ATTACHMENTS

J.1 ATTACHMENTS

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND

OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

K.1 PROVISIONS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS

L.1 PROVISIONS

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 PROPOSAL EVALUATION

M.2 TECHNICAL EVALUATION FACTORS

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

Item Supplies/Services Qty Unit of Issue

Unit Price Total Price

0001 Mobilization/Demobilization for all Work 1 LS Sabino Canyon Turnaround 0002 Reinforced Concrete Low Water

Crossing, Per Attached Drawing

1 LS

0003 Retaining Wall, Split-Face CMU Construction, Per Attached Drawing

400 SF

0004 Reinforced Concrete Sidewalks, 4” Thick 60 SY 0005 Supply and Install Hydrant with

Accompanying Concrete Pad and Drain Pit

1 LS

0006 Waterlines Including Trench Excavation, Pipe Bedding, Valve Boxes, Valves, and Backfill

40 LF

Proctor 0007 Reinforced Concrete Sidewalks, 4” Thick 21 SY 0008 Supply and Install Hydrant with

Accompanying Concrete Pad and Drain Pit

1 LS

0009 Waterlines Including Trench Excavation, Pipe Bedding, Valve Box, Valves, and Backfill

10 FL

Whitehouse 0010 Reinforced Concrete Sidewalks, 4” Thick 24 SY 0011 Decomposed Granite Pad 6 TON 0012 Supply and Install Picnic Table 1 EA 0013 Supply and Install Pedestal Grill 1 EA

Madera Trailhead 0014 Reinforced Concrete Sidewalks, 4” Thick 24 SY 0015 Decomposed Granite Pad 6 TON 0016 Supply and Install Picnic Table 1 EA 0017 Supply and Install Pedestal Grill 1 EA

Parker Canyon Lake 0018 Reinforced Concrete Sidewalks, 4” Thick 64 SY

Cochise Stronghold 0019 Reinforced Concrete Sidewalks, 4” Thick 33 SY

Rustler Park 0020 Decomposed Granite Path 6 TON

Upper Arcadia 0021 Reinforced Concrete Sidewalks, 4” Thick 24 SY 0022 Supply and Install Hydrant with

Accompanying Concrete Pad and Drain Pit

1 EA

0023 Waterlines Including Trench Excavation, Pipe Bedding, Valve Box, Valves, and Backfill

190 LF

Noon Creek 0024 Reinforced Concrete Sidewalks, 4” Thick 49 SY 0025 Decomposed Granite Pad 3 TON 0026 Supply and Install Picnic Table 1 EA 0027 Supply and Install Pedestal Grill 1 EA

Total Price

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

Planned Work: Work associated with this project shall consist of improving restroom sites at nine (9) locations around the Forest. The site improvements include reinforced concrete low water crossing, concrete block retaining wall, reinforced concrete sidewalks, decomposed granite pad and walking path, pedestal grills, picnic tables, and water hydrants with accompanying concrete pad and drain pit.

C.2 PROJECT LOCATION

Work will take place at nine (9) sites throughout the Coronado National Forest in Arizona.

1. Sabino Canyon Turnaround: Physical address 5700 N Sabino Canyon Rd., Tucson, AZ 85750. Restroom is located within the Sabino Canyon Recreation Area behind locked gate and is only accessible with a FS escort. Pima County. Township 13 South, Range 15 East & Section 9.

Latitude: 32.313399°; Longitude: -110.812124°.

2. Proctor: From Tucson, Arizona, travel south on I-19 for approximately thirty-five (35) miles to the Continental Road exit (Exit 63) in Green Valley, Arizona. Turn left (east) on Continental Road and go approximately one (1) mile to the junction with the Madera Canyon/White House Canyon Road. Turn right (southwest) and travel approximately eleven (11) miles to the entrance of the Proctor Picnic Area. Santa Cruz County. Township 19 South, Range 14 East & Section 35.

Latitude: 31.7411409°; Longitude: -110.886831°.

3. Whitehouse: From Tucson, Arizona, travel south on I-19 for approximately thirty-five (35) miles to the Continental Road exit (Exit 63) in Green Valley, Arizona. Turn left (east) on Continental Road and go approximately one (1) mile to the junction with the Madera Canyon/White House Canyon Road. Turn right (southwest) and travel approximately twelve (12) miles to the Whitehouse Picnic Area. Santa Cruz County. Township 19 South, Range 14 East & Section 35. Latitude: 31.73347°; Longitude: -110.882538°.

4. Madera Trailhead: From Tucson, Arizona, travel south on I-19 for approximately thirty-five

(35) miles to the Continental Road exit (Exit 63) in Green Valley, Arizona. Turn left (east) on Continental Road and go approximately one (1) mile to the junction with the Madera Canyon/White House Canyon Road. Turn right (southwest) and travel approximately thirteen

(13) miles to the Madera Picnic Area on left hand side. Santa Cruz County. Township 19 South, Range 14 East & Section 35. Latitude: 31.726888°; Longitude: -110.88040°.

5. Parker Canyon Lake: From Tucson, travel east on Interstate 10 to State Route 83 (exit 281) and turn south fifty (50) miles through Sonoita to Parker Canyon Lake. Restroom is the one closest to the store. Cochise County. Township 23 South, Range 19 East & Section 18. Latitude:

31.424424°; Longitude: -110.448622°.

6. Cochise Stronghold: From Tucson, take 1-10 east for approximately seventy-two (72) miles to US 191. Turn right (south) on US 191 and drive eighteen (18) miles to Ironwood Road. Turn right (west) on Ironwood Road and drive about nine (9) miles to the Cochise Stronghold Campground and the Cochise Trailhead. Restroom is at end of campground. Cochise County.

Township 17 South, Range 23 East & Section 26. Latitude: 31.9220098°; Longitude: - 109.9675653°.

7. Rustler Park: From Tucson, take I-10 east eighty-one (81) miles. Turn right (south) on AZ 186 and continue for thirty-three (33) miles. Turn left (east) on AZ 181 toward Chiricahua National Monument and drive three (3) miles, then turn right (south) on Forest Road 42.

Continue up FR 42 (Pinery Canyon) twelve (12) miles to Forest Road 42D. Turn right at Onion Saddle and drive approximately 2.5 miles to Rustler Park Campground. Restroom is located at the end of campground loop. Cochise County. Township 17 South, Range 30 East & Section 33.

Latitude: 31.9051°; Longitude: -109.27985°.

8. Upper Arcadia: From Tucson, Arizona: Take I-10 east for ninety (90) miles. Take exit 352 for US 191 and turn left toward Safford. Drive 26.3 miles north and turn left on AZ 366/Swift Trail. Turn left (southwest) onto AZ 366 and drive 11.6 miles. Turn right on the road 0.1 mile past the entrance to Arcadia Campground. Graham County. Township 9 South, Range 25 East & Section 18. Latitude: 32.6483762°; Longitude: -109.820315°.

9. Noon Creek: From Tucson, Arizona: Take I-10 east for ninety (90) miles. Take exit 352 for US 191 and turn left toward Safford. Drive 26.3 miles north and turn left on AZ 366/Swift Trail.

Turn left (southwest) onto AZ 366 and drive approximately seven (7) miles. The picnic area is on the right-hand side of the road. Graham County. Township 9 South, Range 25 East & Section

9. Latitude: 32.6682°; Longitude: - 109.79669°.

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

Between $250,000 and $500,000

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

52.246-12 Inspection of Construction (AUG 1996) 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

52.211-13 Time Extensions (SEP 2000) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days. The time stated for completion shall include final cleanup of the premises.

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held within 10 working days after the date of contract award. The conference will be held virtually on

TEAMS.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

Site Superintendent

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses:

https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:

https://www.acquisition.gov/agar (AGAR clauses begin with 452) FAR and AGAR Deviations to clauses may be viewed at: Policies & Regulations | USDA

52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity

(MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights (NOV 2023) (Whistleblower

Guidance to contractor employees) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY

2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN

2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab Covered Entities (DEC 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment (NOV 2021) 52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (NOV 2021) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.usda.gov/da/ocp/ppd/policies-regulations https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK

52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (FEB 2024) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY

2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC

2010) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-54 Employment Eligibility Verification (MAY 2022) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN

2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction

Contracts (SEP 2013) 52.223-3 Hazardous Material Identification and Material Safety Data Alt 1 (FEB 2021) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction

Contracts (AUG 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN

2020) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007)

52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT

2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)

Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Products and Commercial Services (FEB 2024) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)

Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV

1996) 452.236-71 Prohibition Against the Use of Lead-Based Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996)

452.236-73 Archaeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

52.225-9 Buy American Act-Construction Materials (OCT 2022)

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if– https://www.acquisition.gov/far/part-2#FAR_2_101 https://www.acquisition.gov/far/part-25#FAR_25_105

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505

None

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1) (i)Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (Dollars)* Item1 Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2 Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]

(End of clause)

52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION MAY 2023)

(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond -

(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and

(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].

(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.

(c) A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release. The security interest on the individual surety's assets in support of a payment bond shall be maintained—

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C. 3131). For 1 year following final payment, or until resolution of all pending claims filed against the payment bond during the 1-year period following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For 90 days following final payment.

(d)The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph (a) of this clause within the timeframe established by the Contracting Officer.

https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy-original-documents-signatures-notarization-seals-bonds-other-seals.pdf https://www.acquisition.gov/far/part-28#FAR_28_203_1

52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) (DEVIATION

MAY 2023)

(a)Definitions. As used in this clause -- “Original contract price” means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:

(1) Performance Bonds (Standard Form 25, EXCEPT THAT A SEAL IS NOT REQUIRED). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bonds (Standard Form 25-A, EXCEPT THAT A SEAL IS NOT REQUIRED). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(3) Additional bond protection.

(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.

(ii) The Government may secure the additional protection by directing…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .