This document is a Schedule of Items (SOI) for the Chip and Crack Seal Treatment of NFSR 333 - Cibola NF contract opportunity. The contract is for the application of crack seal treatment and chip seal on the NFSR 333, 333A asphalt roadways and the La Luz Trailhead asphalt parking lot, spanning approximately 2.38 miles on the Sandia Ranger District of the Cibola National Forest.
The SOI includes line items for mobilization, shoulder reconstruction, asphalt surface treatment, asphalt pavement crack sealing and filling, asphalt pavement patching, wheel stops, roadway and parking lot pavement markings, and temporary traffic control. Pricing is provided for a base bid and two option items (fog seal and untreated aggregate base). The contract duration is 90 days. This opportunity is being solicited by the USDA Forest Service R3-Southwestern Region under Solicitation Number 127EAX24R0011.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AWARD NOTICE.pdf | ||
| 127EAX24R0011 Solicitation.pdf | ||
| Presolicitation Notice.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Schedule of Items |
| Sandia Ranger District |
| NFSR 333, 333A, and La Luz Trailhead Pavement Preservation |
| Contract Time: 90 days |
| BASE | ||||||||
| Item Number | Task Description | Method of Meas | Unit | Price | ||||
| ($) | Quantity | Total | ||||||
| 151 | Mobilization | CQ | LS | 1 | ||||
| 404 | Shoulder reconstruction | AQ | LF | 265 | ||||
| 407 (1) | Asphalt Surface Treatment - CR2P Latex Modified Asphalt at 0.4 Gal/SY | AQ | TON | 52.9 | ||||
| 407 (2) | Asphalt Surface Treatment - Aggregate Chips 3/8" Type 1C (Purchase, Haul, Place) | CQ | SY | 31500 | ||||
| 414 | Asphalt Pavement Crack Sealing and Filling | CQ | LS | 1 | ||||
| 418.03 (1) | Asphalt Pavement, Base, and Subgrade Full Depth Patch Type I | AQ | SF | 325 | ||||
| 418.03 (2) | Asphalt Pavement, Base, and Subgrade Full Depth Patch Type I | |||||||
| Extensive - Repaving Needed | AQ | SF | 840 | |||||
| 609.08 (1) | Wheel stops - Concrete | AQ | EA | 40 | ||||
| 609.08 (2) | Wheelstops - Rubber | AQ | EA | 2 | ||||
| 634 (1) | Roadway Permanent Pavement Markings - (2 coat) Double Yellow 4" Type B with glass beads. - Center Lines | CQ | LS | 1 | ||||
| 634 (2) | Roadway Permanent Pavement Markings - (2 coat) White 4" Type B with glass beads - Shoulder Stripes | CQ | LS | 1 | ||||
| 634 (3) | Parking Lot Permanent Pavement Markings - (2 coat) 4" Yellow or White Type B with glass beads - Hatching and Park Stall Lines | CQ | LS | 1 | ||||
| 634 (4) | Permanent Pavement Markings - (2 coat) White Type B with glass beads - Through Lane-Use Arrows (6), ADA accessible Parking spaces (2) | CQ | LS | 1 | ||||
| 635 | Temporary Traffic Control - Traffic control including all necessary planning, materials, equipment, and certified personnel. | AQ | LS | 1 | ||||
| Total: |
| OPTION A | ||||
| 151 | Mobilization | CQ | LS | 1 |
| 406 | Fog Seal CSS-1H at 0.12 Gal/SY | AQ | Gal | 3780 |
| Total: | ||||
| OPTION B | ||||
| 151 | Mobilization | CQ | LS | 1 |
| 301 | Untreated Aggregate Base - Gradation A (Purchase, Haul, Place) | CQ | Ton | 480 |