Amendment 0001.pdf
PDF 90 KB Posted
- Attached to
- Sabino Canyon Toilet Replacement
- Solicitation number
- 127EAX23Q0032
About this file
This document is an amendment to a federal solicitation providing additional questions and answers, notification of a site visit, and extension of the quote submission deadline. The Sabino Canyon Toilet Replacement solicitation from the U.S. Department of Agriculture Forest Service R3-Southwestern Region seeks quotes to replace toilets at Sabino Canyon. A mandatory site visit is scheduled for September 27, 2023 at 9:00 A.M. at the back gate of 5700 N. Sabino Canyon Rd in Tucson, Arizona. The quote submission deadline is extended to September 29, 2023 at 8:00 A.M. Arizona time. The amendment includes answers to three questions confirming archaeological monitoring requirements, the ability of trails and roads to support heavy equipment weighing around 100,000 pounds without damage, and vegetation clearing required for crane access.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 127EAX23Q0032 Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
127EAX23Q0032
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
7EAX
ALBUQUERQUE NM 87102-3498
333 BROADWAY BLVD SE
USDA-FS CSA SOUTHWEST 7
09/18/20230001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
09/18/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to provide questions and answers, add site visit information and extend the due date for quotes
A site visit is scheduled for Sep 27, 2023 at 9:00 A.M.
Meet Forest Service Rep at back gate / entrance to Sabino Canyon. The address is 5700 N.
Sabino Canyon Rd. 85750. The coordinates are: 32.315328° -110.822636°
The back gate entrance is approximately 0.34 miles past the main entrance.
The due date for submitting quotes is extended to Sep 29, 2023 at 08:00 A.M. Arizona Time
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
MICHAEL E. CARICO
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
127EAX23Q0032/0001
Here are three questions with answers:
1. Are there any cultural resources or special species that will need consideration for this job?
ANSWER: Per the NEPA document all new ground disturbance may be monitored by a Forest archaeologist. This includes the Rattlesnake
Restroom. The monitoring shall not impact construction schedule. No federal threatened and endangered species, designated critical habitat, or Forest Service Sensitive species will be impacted. No mitigations shall be required.
2. Can the trails hold heavy equipment without causing damage to the trails? Semi with toilets will be around 100,000 lb¿s? Who is responsible for damages if they occur?
ANSWER: Travel on trails is not required to access the work sites. The National Forest System
Roads leading to the work sites are paved. We do not anticipate any damage to roadways as a tractor trailer has recently transported a 2-hole
CXT building on the same road system.
3. Can plants/ trees be removed and ground graded for access by crane/semi?
ANSWER: For a crane to access the work sites, no tree trimming or vegetation removal of any kind shall be required. However, clearing and grubbing will be required prior to installation of the CXT building at the Rattlesnake site.