C04 - Attachment 2 - Statement of Work.pdf
PDF 308 KB Posted
- Attached to
- ANF Suppression Damage Chantry
- Solicitation number
- 127EAW27Q0003
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) issued by the US Department of Agriculture Forest Service for road repairs and damage restoration at Chantry Flats Picnic Area and San Olene Road on the Angeles National Forest in California.
The contract scope requires the contractor to pulverize, compact, and repave San Olene Road with 2 inches of Caltrans HMA over new road base while maintaining current drainage features. The Chantry Flats Picnic Area (approximately 82 parking stalls) must be slurry sealed using CalTrans Spec 37-3 Type 1 Slurry Seal and restriped to match the existing layout. Additionally, two concrete slabs (4 inches, 4000 psi per FP-24 Table 501-1) must replace damaged sections of a 36-inch-wide walkway adjacent to San Olene Road. All work must comply with FP-24 Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects unless superseded by Caltrans specifications. The contractor is responsible for all quality control testing (aggregate base compaction, HMA compaction/temperature verification, and concrete slump), with results submitted to the Contracting Officer's Representative within 48 hours of testing. Work shall be performed Monday through Friday between 7:00 AM and 5:00 PM for 90 calendar days from the Notice to Proceed, with an expected start in January 2027. The contractor must obtain a valid California contractors license as a General Engineering Contractor, General Building Contractor, or relevant Specialty Contractor, provide an onsite superintendent and project manager within five business days of award, submit eight deliverables (including project schedule, operations plan, quality control plan, and material submittals) within specified timeframes, and bear all travel costs. The contractor is responsible for inspecting access routes prior to bidding, managing traffic control and equipment staging, protecting existing drainage features, and obtaining daily fire activity level (PAL) restrictions from Forest dispatch.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
ANF Suppression Damage Chantry
Angeles National Forest
STATEMENT OF WORK
The purpose of this contract is to provide road repairs to the Chantry Flats Picnic Area as well as San Olene Road from Chantry Flats to the Helispot. The existing San Olene road will be pulverized, compacted and repaved to maintain current drainage features and flows. San Olene road will be repaved and 2” of Caltrans HMA will be paved over the new road base. The Chantry Flats Picnic Area will be slurry sealed to repair damage from dozer and excavators tracking on the pavement during the 2025 Eaton Fire. To match, the entire picnic area will be slurry sealed and restriped to match the existing parking layout. The slurry seal will consist of CalTrans Spec 37-3 Type 1 Slurry Seal. Chantry picnic area consist of approximately 82 parking stalls, directional arrows, traffic control lines and various no parking areas. Two slabs of concrete will be replaced adjacent to San Olene Road, where dozers tracked over the existing walkway leading to the concrete failure.
The concrete replacement will consist of 4” concrete, 4000 psi per FP-24 Table 501-1. Existing walkway dimensions shall remain the same which is currently 36” wide with an approach off of San Olene Road.
This contract provides for the equipment, labor, and services necessary to perform work ordered by the Government for road pulverization and repaving of San Olene Road, slurry sealing and striping the Chantry Flats picnic area and replacing damaged concrete walking path sections, in compliance with the terms, specifications, drawings and provisions of this contract. Locations of work will be directed by the Forest Service.
The Contractor is responsible for inspecting the access route prior to bidding and utilizing appropriately sized haul trucks and equipment.
PROJECT LOCATION
The project location is on the Angeles National Forest within the Los Angeles Gateway Ranger Districts. The terrain can be relatively flat in a few areas and moderately hilly and steep in others. Soil conditions vary as well, from soft and sandy to compacted and extremely rocky. A general Vicinity Map is included with this solicitation. Angeles National Forest maps are also available to assist in locating the individual roads and can be purchased at the Supervisors Office. The office is open between the hours of 8:00 am and 4:30 pm, Monday through Friday. The office is located at 701 N Santa Anita Ave, Arcadia CA 91016
The Government will not provide a pre-bid site meeting. All roads are open for review and highly suggested to be driven for existing condition. For additional information regarding road access for the contract contact Zach Binversie at (626) 701-9655 or Zachary.Binversie@usda.gov
PERIOD OF PERFORMANCE:
Start is expected immediately after contract award (January 2027).
Time for completion: 90 calendar days from the issuance of the “Notice to Proceed”.
Work shall be performed Monday through Friday between the hours of 7:00 AM and 5:00 PM. Work is prohibited on weekends and Federal holidays, unless approved in writing by the Contracting Officer (CO).
SCHEDULING
The contractor shall submit a proposed work schedule to allow the COR and District Rangers to evaluate options for temporary road closures along the entirety of the project. Road closures will not be guaranteed in full, but will be considered for this project.
REQUIREMENTS
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities to perform the Statement of Work/Specifications referenced below. Equipment staging, material stockpiling, and portable sanitation facilities shall be confined strictly to areas designated by the Contracting Officer's Representative (COR) within the Area.
The Contractor shall provide equipment that is free and clear of soils, seeds, vegetative materials and other debris that could contain or hold seeds of noxious weeds. Once on-site, there will be no equipment washing requirement as this project is located within one area.
Water is available for the contractor to use on site. The Angeles National Forest operates its own water system and due to unforeseen conditions or needs this system is not guaranteed to be operational during the period of this contract. The contractor is responsible for providing an alternative off-site water source as needed.
The Contractor shall minimize mechanical activity during rainy periods and the CO may shut down the operation if excessive soil disturbance and/or erosion problems occur.
The Contractor shall repair all associated damage on established roads, adjacent vegetation or other improvements caused by their operations or equipment prior to partial or final payment.
The Contractor shall provide technical submittals for all materials that may be furnished on this project for Forest Service review and approval prior to installation.
The Contractor shall dispose of all project related trash and debris off of Forest lands prior to final payment.
The Contractor is responsible for contacting the Forest dispatch center to obtain the fire predicted Project Activity Level (PAL) each day and restrict their work accordingly.
The Contractor shall adhere to the pertinent requirements addressed in the Fire Plan. Fire Plan restrictions may require work to cease at 1:00 pm or not be initiated at all on a high fire activity (PAL) day.
The Contractor is responsible for traffic control and equipment staging requirements in work areas when working on National Forest System Lands. The Contractor shall install high-visibility barricades, caution tape, and advance warning signage around all active work zones, wet slurry seal areas, and open excavations. A dedicated spotter shall be used whenever heavy equipment is operating in reverse or maneuvering near public trailheads.
The Contractor shall protect all existing culverts, drop inlets, and drainage ditches from construction debris, pulverized base, and slurry runoff. Any drainage features fouled by Contractor operations shall be cleaned out and restored to full flow capacity at no additional cost to the Government.
The Contractor must obtain a valid contractors license in the State of California upon award under FAR 52.236- 7 Permits and Responsibilities. Contractor must be licensed as a (A) General Engineering Contractor, (B) General Building Contractor, or (C) Specialty Contractor with relevant specialization.
SPECIFICATIONS
All Specifications are from the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24). Digital copies of FP-24 can be found here https://highways.dot.gov/sites/fhwa.dot.gov/files/fp-24_0.pdf FP-24 applies unless specifically superseded by Caltrans specifications noted.
https://highways.dot.gov/sites/fhwa.dot.gov/files/fp-24_0.pdf
QUALITY CONTROL (QC) TESTING
The Contractor is responsible for all Quality Control testing in accordance with FP-24 and applicable Caltrans specifications, including aggregate base compaction testing, HMA compaction/temperature verification, and concrete slump. All test results shall be submitted to the COR within 48 hours of testing.
SUBMITTALS
Item No. Deliverable Objective Due 1 Project Schedule Define the timeline, milestones of contract items, and identify critical path. Update of the preliminary schedule submitted with the quote.
Within 10 calendar days after Notice of Award
2 Plan of Operations and Traffic Control Plan
FP-24 156 Within 10 calendar days after Notice of Award
3 Contractor Quality Control Plan
FP-24 153 Within 10 calendar days after Notice of Award
4 HMA Mix Data (Caltrans Type A PG 64-10)
Material and workmanship compliance
Due 14-days prior to mobilization
5 Slurry Seal Mix Data (CalTrans Spec 37-3 Type 1)
Material and workmanship compliance
Due 14-days prior to mobilization
6 Concrete Mix Data (4000 psi)
Material and workmanship compliance
Due 14-days prior to mobilization
7 Steel Welded Wire
(AASHTO M336)
Material and workmanship compliance
Due 14-days prior to mobilization
8 Permanent Pavement Markings Type-H
Material and workmanship compliance
Due 14-days prior to mobilization
TRAVEL
The Contractor must cover all travel costs needed to complete this project scope.
CONTRACTOR'S KEY PERSONNEL
The Contractor shall provide an onsite contract representative (superintendent) who will oversee the performance of the work specified in this contract in the field no later than five (5) business days after contract award. Designate in writing to CO, the name of the contract representative and an alternate who shall have the authority to act for the Contractor on all contract matters relating to onsite daily operation of this contract. The CO/COR shall be notified at least 10 working days in advance of any subsequent personnel changes.
Replacement personnel shall have the same level or better experience as the person being replaced.
The contractor shall provide a Project Manager representative who will oversee all administrative actions for the performance of work no later than five (5) business days after contract award. Designate in writing to CO, the name of the contract representative and an alternate who shall have the authority to act for the Contractor on all contract matters relating to administrative operations of this contract. The CO/COR shall be notified at least 10 working days in advance of any subsequent personnel changes. Replacement personnel shall have the same level or better experience as the person being replaced.