This document is a Fire Plan for Construction and Service Contracts related to a federal contract opportunity. The project involves replacing and upgrading plumbing at the Santa Maria Air Tanker Base, including replacing the backflow valve assembly, sections of pipe, and fixtures. The contractor must be licensed, bonded, and certified, and will be responsible for obtaining all permits, scheduling inspections, and adhering to strict security and safety requirements. No government-furnished equipment or supplies will be provided. Key deliverables include submitting manufacturer information, installation instructions, and a project-specific safety plan. The project is located at the Santa Maria Airport in California, with a contract period of performance between 7am and 5pm Monday through Friday, excluding federal holidays. The related federal contract opportunity, Solicitation Number 127EAW24R0041, is a small business set-aside for a construction project valued between $25,000 and $100,000 for the Santa Maria Air Tanker Base Water Manifold Replacement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FIRE PLAN FOR CONSTRUCTION AND SERVICE
CONTRACTS 05/20/2024
1. SCOPE:
This project involves the replacement and upgrade from the current diameter PVC to 6” galvanized steel and/or appropriate metal plumbing of the current backflow valve assembly including but not limited to all fittings, water meter, backflow assembly, valves, flanges, and other items associated with the present unit. In accordance with current statutes, there shall be a concrete pad around the assembly and concrete thrust blocks at the ninety-degree fittings below grade. There shall be a replacement of the ‘fill side’ of the pipe where the ridged section meets a flexible section. This will be at an elevation to allow the flexible pipe to be moved across an existing section of curb.
There is a section of pipe near the primary supply valve, approximately 150 yards to the South-East, that has a reduced diameter. This pipe, now 4”, is a formerly replaced section of the original 6” pipe. This section, approximately ten feet long and approximately three feet below grade is to be replaced with pipe equal to the rest of the plumbing. This is to insure proper volume and pressure to the retardant manufacturing and dispensing process. The project also includes replacing a section of the 2” section of pipe which is connected by a ‘Tee’ which is reduced from six to two inch and leads to additional plumbing fixtures. This 2” section shall remain at this size. All fixtures must adhere to current county, state and applicable statutes including but not limited to any FAA directives.
2. RESPONSIBILITIES:
The contractor shall be licensed and bonded will all appropriate construction and plumbing certifications, including but not limited to those allowing the replacement of a municipality-supplied backflow prevention unit.
Upon submitting a bid, evidence of current license, bond, insurance, any and all certifications appropriate for county, state, federal and if necessary, FAA-requirements for backflow prevention repair and replacement shall be provided with any bid. All appropriate permits and fees shall be the responsibility of the Contractor. No work shall be performed until all permits and fees are acquired and paid in full. All county, state, and other inspections shall be scheduled by the Contractor and the Contractor or approved and qualified representative shall be present for all inspections. ‘Qualified’ representatives must include someone who can answer any questions that inspectors may have or be able to provide an answer in an appropriate amount of time.
All the work is completed behind security fences, in and around sensitive structures, buildings, aircraft and infrastructure. All vehicles and personnel entering and leaving shall be escorted by Air Attack Base or Forest Service personnels. All gates must have someone present to insure only those involved with the project are allowed to enter. Any violation is subject to FAA rules and statutes.
No personnel including the Contractor, subcontractors, employees or anyone associated with the project, excluding federal, state and local government officials, shall venture outside the work area. There shall be no trespassing into or on or near buildings, aircraft, equipment, structures, runways or areas where aircraft or vehicles, other than work vehicles associated with the project, are located or in transit. When aircraft are near the project, the Contractor, subcontractor any and all employees and personnel associated with the project shall adhere to directives from Air Attack Base personnel and/or anyone associated with the airport, or security as where to go, where to stay and what to do when in proximity of any moving or stationary aircraft. Any violation of directives, rules, statutes or orders can result in immediate removal from inside of the fenced area or possible citations or legal actions deemed appropriate by authorities.
• The sections of the plumbing to be replaced and upgraded will require appropriate licensing and expertise. The Contractor and any subcontractors shall be knowledgeable in all aspects of the required work.
o The work shall involve removing of all plumbing and fixtures from the below-grade level where the pipe connects to a ninety-degree fitting. This includes the ninety-degree fitting and the installation of thrust blocks at the required fittings/junctions. The removal shall include the two-inch section to the below-grade horizontal section where the line leads to the devices further down the line. Also removed shall be the reduced diameter section of supply line pipe near the primary valve.
o All demolished materials shall be disposed of appropriately in a landfill, recycled or other disposal method in accordance with applicable statutes and regulations.
o The replacement unit and parts shall include all fittings, supports and concrete pad to support the aforementioned backflow prevention structure. This shall include the municipal water meter and any valve and connections. The two-inch plumbing shall be replaced, including valves and meter to the below-grade section where it leads to the horizontal section. There shall be at least two feet of new galvanized pipe on the horizontal section prior to connecting to the original pipe.
o All below-grade work shall be in compliance with OSHA standards for depth.
o All below-grade work shall expose horizontal pipe for no less than six feet in all directions beyond any replaced sections, excepting where the line may expose the primary valve. In this case, the exposed area need only terminate at the valve box.
o All metal fittings shall have an appropriate sealant including but not limited to non-reactive tape (e.g. Teflon), or thread sealant to both. All sealants must be code-approved for use in potable water plumbing and fixtures.
o All fittings and flanges must be tightened to prevent any and all leakage. Any ‘break-away’ bolts or assemblies must adhere to appropriate torque as designated by the manufacturer.
o All components must adhere to federal standards including being manufactured in the United States of America. Any component manufactured out of the country shall be rejected and replaced at the cost of the Contractor.
o The hours of operation are to be between 7AM (0700) to 5PM (1700) Monday through Friday, excluding federal holidays. Any work on the project must have a Contracting Officer (CO), Contracting Officer Representative (COR) or Inspector present.
3. Government Furnished
There will be no government furnished equipment or supplies.
4. Deliverables / Schedule
• All deliverables and documents shall be presented to the Contracting Officer.
• All written deliverables shall be phrased in layperson language and delivered within 10 calendar days from the date of acceptance from the Contracting Officer and prior to final payment. There shall be a minimum of an original and two copies of all deliverables. All “hard copy” deliverables, instructions shall be submitted on recycled content paper and printed double-sided, excepting project plans. All catalog cuts and data associated with the treatment system within 7 calendar days from the Notice to Proceed.
• A copy of manufacturer’s written instructions and recommendations for inspection purposes, no later than 7 calendar days prior to installation.
5. Travel The project is located at the Air Attack Base on the south side of the Santa Maria Airport in Santa Maria, California. The global location is 34 degrees, 53’ 29.85 N by 120 degrees, 27’ 17.84 W. To reach the security gate, from California Highway 101, head West on Union until it ‘T’s’ on Blosser Road. Turn Right/Northwest until the road dead-ends. The security gate will be on the right.
6. Contractor’s Key Personnel The Contractor shall provide a list of Key Personnel in the employ of the contractor’s company including contact information. This contact information shall include mailing, email, cell and any additional electronic or physical venues for communication.
7. Security Requirements
The project is behind a security gate. This does not constitute total security by the government. All materials, supplies, vehicles, and equipment associated with the project is the responsibility of the contractor until completion and final acceptance by the Contracting Officer. All jobsites shall be cleaned daily and in total upon completion in accordance with specifications and include sweeping and rolling a bar magnet to pick up all metal, screws, nails, etc. This includes where work or supply vehicles are stored, parked and/or staged excepting where fences or other barriers prevent access.
Prior to starting any work on this project, the Contractor shall develop and submit to the Contracting Office, a Safety Plan specific for each location. The Safety Plan shall adhere to all State or Federal OSHA regulations, whichever is more stringent. The Safety Plan shall also include a description for all flagging, signage and other means to ensure the safety of employees, vehicular and personnel traffic in and around the Project Sites.
8. DEFINITIONS:
The following definitions shall apply:
Ramp: The location where Aircraft taxi, and park. Additionally, the location The contractor will be driving, parking or operating equipment necessary to complete the Contract.
Retardant Plant: The location of the water manifold and mixing operation for loading aircraft with fire retardant.
F.B.O (Fixed Base Operator): Operation that provides aviation services such as fuel, parking and hangar space.
9. GENERAL
A. State Law: In addition to the requirements in this Fire Plan, the Contractor shall comply with all applicable laws of the State of California. In particular, see California Public Resource Codes.
B. Smoking: No Smoking on work site. Only in approved designated smoking areas.
C. Agency contact information:
Name Office Address Office telephone
Dispatch Center 805 938 9142
Nearest FS Station Santa Maria Air Tanker Base 1211 Citation Ct Santa Maria CA 93455 805-623-0451
Inspector Rick Nielsen 805-698-6682
COR Alyssa Thornburg 805-450-2746
Base Manager Miguel Quiz 661-902-9629
Fire Management Officer Concurrence Date
Line Officer Approval Date
I have considered the above request and determined the specified mitigation measures or actions must be implemented to continue operations in Project
Activity Level Ev. Unless extended, the approval remains in effect for ten
(10) calendar days unless cancelled sooner or extended by the Forest Service for an additional ten (10) days. At the sole discretion of the Forest
Service, this variance can be modified and/or cancelled at no cost to the government.
Contracting Officer Date
Contractor Representative Date
Proposed Actions:
Description of Mitigation Measures:
Remarks:
| NameDispatch Center: |
| Office AddressDispatch Center: |
| 805 938 9142: |
| 8056230451: |
| Inspector: |
| 1211 Citation Ct Santa Maria CA 93455Rick Nielsen: |
| 8056986682: |
| COR: |
| 1211 Citation Ct Santa Maria CA 93455Alyssa Thornburg: |
| 8054502746: |
| 1211 Citation Ct Santa Maria CA 93455Miguel Quiz: |
| 6619029629: |
| Proposed Actions Description of Mitigation Measures Remarks: |
| Fire Management Officer Concurrence: |
| Date: |
| Line Officer Approval: |
| Date_2: |
| Contracting Officer: |
| Contractor Representative: |
| Date_3: |
| Date_4: |
File details come from the government source that posted it. Updated .