This document is a contract amendment for the GAOA Bayview Parking Lot Upgrades - Phase 2 solicitation, Solicitation Number 127EAW24R0024. The purpose of this amendment is to provide answers to Requests for Information (RFIs) submitted by interested vendors.

The key details are:

  • One person may be assigned multiple roles as Superintendent, Site Safety and Health Officer (SSHO), and Quality Control (QC) Manager.
  • The period of performance will not be extended beyond the required 60 calendar days after the Notice to Proceed is issued.
  • A soil boring report is not available, but excavation is expected to be clear of bedrock based on prior construction in the area.
  • Failure to use the revised documents and requirements will result in a non-responsive proposal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

2. AMENDMENT/MODIFICATION NUMBER

A00001

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

JEREMY BEDNER

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment A00001 GAOA Bayview Parking Lot Upgrades - Phase 2

Lake Tahoe Basin Management Unit, CA.

The purpose of this solicitation is to post answers to the Requests For Information

See page 2 for additional information.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

USDA FOREST SERVICE

PPS FPO SW ZONE CSA-6

TANYA TORRES

CONTRACT SPECIALIST

ALL INTERESTED VENDORS

9A. AMENDMENT OF SOLICITATION NUMBER

127EAW24R0024

1 2

06/05/2024

9B. DATED (SEE ITEM 11)

05/06/2024

1125915

7EAW

X 1

X

AMENDMENT OF SOLICITAITON/MODIFICATION OF CONTRACT PAGE NO. 2 OF 2

CONTINUATION PAGE

CONTRACT NO:

127EAW24R0024

ORDER NO: MODIFICATION NO:

A00001

14. DESCRIPTION OF AMENDMENT/MODIFICATION (CONTINUED)

STANDARD FORM 30 (CONTINUATION)

A. The following Request For Information are answered.

• Question 1: Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

Answer: No they do not. One person may be assigned multiple roles.

• Question 2: Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

Answer: The period of performance will not be extended. Grading activities may only occur from May 1 to October 15. The contractor shall begin performance within 10 calendar days and complete it within 60 calendar days after receiving Notice To Proceed (NTP). The NTP will be issued once all submittals have been received and approved. A stop-work order may be issued due to winter weather conditions.

• Question 3: Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions.

Answer: A soil boring report is not available. However based on prior construction activities at the site it is assumed that excavation within the project footprint will be clear of bedrock. Below grade boulders are possible based on prior excavation at the site.

B. Failure to use the revised documents and requirements revised within will result in your proposal being non-responsive.

All other terms and conditions remain unchanged.

///////////////////////////////////////////////LAST ITEM//////////////////////////////////////////////////

Amendment - A00001 - 127EAW23R0011 - Sky Ranch Road
Amendment 1 - Continuation - 127EAW23R0011 - Sky Ranch Road
PAGE 2.pdf
A00001 - 127EAW24R0017 - Crestline Group CG Renovation
Amendment - A00001 - 127EAW23R0011 - Sky Ranch Road

SF 30 Continuation Page

File details come from the government source that posted it. Updated .