1. Statement of Work.pdf

PDF 191 KB Posted

Attached to
127EAW24R0009 - Modoc Forest Barrack Maintenance
Solicitation number
127EAW24R0009
Issued by

About this file

This document is a Statement of Work (SOW) for a forestwide barracks maintenance project on the Modoc National Forest. The purpose is to renovate all barracks on the forest due to being outdated, including work on roofing, siding, windows, flooring, interiors, HVAC, wood stoves, and lighting. The work is estimated to cost between $1,000,000 and $2,000,000 and will be procured through a Request for Proposal (RFP) with Solicitation Number 127EAW24R0009. The procurement is set aside for Small Businesses certified in the System for Award Management (SAM). The solicitation will be posted on or about March 21, 2024 and all work must be completed by May 1, 2025. An optional site visit is scheduled for April 2, 2024. Contractors must submit a proposed schedule with their bid to allow the Forest Service to manage tenant occupancy.

View the file

Other files

File Type Posted
8. Davis-Bacon Act WD # CA20240007.pdf PDF
7.2 Barracks Photos.zip ZIP file
7.1 Barracks Photos.zip ZIP file
5. Modoc Barracks Map.pdf PDF
7.3 Barracks Photos.zip ZIP file
7. Barracks Photos.zip ZIP file
127EAW24R0009 - Modoc Forest Barrack Maintenance.pdf PDF
2. Schedule .docx DOCX document
9. RFI Form.docx DOCX document
4. Modoc Barracks Locations.pdf PDF
6. Asbestos Reports.zip ZIP file
3. Supplemental Specifications.pdf PDF
Pre-Solicitation Notice.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FORESTWIDE BARRACKS MAINTENANCE

Modoc National Forest

Modoc, Lassen & Siskiyou Counties

STATEMENT OF WORK

The purpose of this project is to renovate all barracks located on the Modoc National Forest due to being outdated. This includes but is not limited to roofing, exterior siding, windows, flooring, interior painting, bathroom renovation, propane refrigerators, cabinets, countertops, HVAC, wood stoves, LED lighting, HAZMAT mitigation.

Furnish all labor, materials, equipment, and other incidentals necessary to complete the following work items as listed in the Schedule of Items:

• Roofing (074113) - Remove and replace all roofing on specified buildings with screwless or hidden fastener high-rib style metal roofing. Complete any structural repairs necessary before installation of new roofing. Installation of roofing shall provide a complete and usable roofing system including but not limited to all surfacing materials, associated venting, penetration sealing, and replacement of any existing gutters. Installation will comply with contract specifications and manufacturer’s installation instructions. All installations must comply with

Modoc County Building Codes. Contractor will dispose of all waste, including removed roofing and decking materials. Up to 15% of the roof structural assembly, including sheathing, rafters, fascia, soffit, vent assemblies, and other roof components, if damaged, will be replaced or repaired per the CO with no modification to this contract. Additional needs will be addressed via negotiation and contract modification.

• Siding (074646) - Remove and replace all siding and trim on specified buildings. Complete any needed repairs or replacement of insulation. Paint siding and trim to match other buildings on complex or other colors as approved.

• Windows – Remove and replace all windows in specified buildings. Each window shall be replaced with a similar style window (i.e. fixed, single-hung, double-hung, sliding, etc.)

Replacement windows shall be high-quality vinyl, double-pane, Energy Star rated windows, PlyGem West Pro Vinyl Series 200 or equivalent.

• Flooring (096516) - Remove and replace all flooring in specified buildings with commercial grade vinyl plank flooring. Complete any structural repairs necessary before installation of new flooring.

• Interior Painting – Paint all interior walls in specified buildings with satin finish, Swiss coffee colored paint, Sherwin Williams SuperPaint Interior Latex Satin or equivalent.

• Bathroom Renovation – Gut (remove tub, shower, toilet, vanity, mirror, cabinets, flooring, towel bars, fixtures, etc.) bathroom and renovate in specified buildings, replacing all items and fixtures in kind (unless otherwise noted) with modern, high-quality, products.

o All tubs/showers shall be replaced with standing showers with high-quality mounted curtain bars, Aquatic 13632P or equivalent. Tub/shower fixtures shall be Delta Classic

Bath Collection (T13020, T13120, T13220) or equivalent. All fixtures shall be low flow.

o Vanities shall be free standing Master Brand Mantra or equivalent.

o Faucets shall be single-handle commercial grade faucets. Peerless P188620LF-BN or equivalent.

o Toilets shall be Grover Western Pottery B872WH/T8HPWH or equivalent.

• Propane Refrigerators – Remove and replace propane refrigerators with new, high-quality, similarly sized (~20 cubic feet), over and under propane fridges, Unique Appliances Off-Grid

34.6 in. 19 Cu. Ft. Propane Top Freezer Refrigerator (Model # UGP-19C SM W) or equivalent.

• Cabinets & Countertops – Remove and replace all cabinets and countertops with modern, high quality cabinets/countertops matching current layout and design. Counters shall be Corian

Solid Surface or equivalent. Cabinets shall be Master Brand Mantra or equivalent.

• HVAC Installation – Remove old heaters/stoves as specified in the Schedule of Items and replace with a HVAC mini-split with multizone air handler in each room. Mini-splits shall be wall-mounted with programable thermostats mounted on the wall. A 4-ton multizone inverter heat pump system mini-split that is a Mitsubishi MXZ-SM48NAMHZ or equivalent shall be installed in four to five bedroom facilities. A 2.5-ton multizone inverter heat pump system mini-split that is a Mitsubishi MXZ-3C30NAHZ4 or equivalent shall be installed in two to three bedroom facilities.

• Wood Stoves – Remove old heating apparatuses and wood stoves as noted in Schedule of

Items and replace wood stove (including chimney and all components unless otherwise noted in Schedule of Items) with new, high-quality wood stove (free standing or insert as noted in

Schedule of Items). Free standing stoves shall be replaced with Blaze King Sirocco 20.2 or equivalent. Inserts shall be replaced with Blaze King Princess 29 insert or equivalent. All piping shall be replaced with minimum double-wall, Simpson or Dura-Vent or equivalent.

Repair any damage to floors/walls/paint/etc. left from the removal of old heating sources.

• LED Lighting – Replace all light fixtures in specified buildings (including exterior lighting on building) with high-quality LED light fixtures, SATCO Nuvo S39906 or equivalent.

• HAZMAT Mitigation – Properly remove and dispose of any asbestos containing materials

(noted in Schedule of Items).

Note that removal of any items listed for removal includes appropriate disposal off-forest.

SUBMITTALS

Full submittals including product specifications and details shall be required by the successful bidder for the following. Brands, materials, colors, designs, sizes, and other details as applicable must be approved by a Forest Service representative prior to purchase and installation:

• Roofing systems

• Siding

• Flooring

• HVAC systems

• Windows

• Toilets

• Showers and shower fixtures

• Curtain/towel bars

• Sinks/faucets/vanities/mirrors

• Cabinets/countertops

• Paint

• Lighting fixtures

• Wood stoves

• Propane Refrigerators

PROPOSALS

Contractor’s quotes shall provide for the purchase and installation of the items and types specified in the Schedule of Items and Specifications. Contractors may also provide quotes and technical plans for optional alternative systems or items but must demonstrate cost savings or superior performance of the alternative options. The contractor’s technical proposal should clearly identify the use of either a metal roofing system structurally rated for the existing purlin span, or the addition of sheathing to support the type of metal roofing specified in this contract, which requires a continuous, rigid substrate. If proposing an alternative structural metal system, provide manufacturer’s specifications.

SITE VISITS

An organized site visit has been scheduled for-

Date / Time: Tuesday, April 2nd, 2024 @ 0830

Participants will meet at-

Address / bldg. #: Canby Work Center, 22529 Hwy 299. Canby, CA 96015 (next to the Canby Post Office). We will visit a representative facility in Canby and then another in Adin, CA.

FS personnel leading Site Visit Contact Info

Title: Forest Engineer/COR

Name: Chris Bielecki

Phone #: 530-801-1637

All bidders are strongly urged to conduct site visits prior to entering bids in order to best assess the nature and condition of the existing buildings. The building exteriors are accessible without prior approval. A tour of several representative facilities will be held on April 2nd, 2024 at 0830 AM PST at which time the interior of the buildings in concern will be open for viewing. Please contact Forest

Engineer, Christopher Bielecki at (530) 233-8850 christopher.s.bielecki@usda.gov for further questions or to schedule site visits you would like to conduct to barracks not shown on the tour.

SCHEDULE

354 Calander days: June 3rd, 2024 through May 25th, 2025

All work shall be completed by May 1, 2025. Barracks are generally occupied between May and

October. Unless circumstances allow, only one barracks will be made available for work at a time and all work must be completed within an agreed upon time frame to allow for occupants to return. All buildings shall be entirely functional while occupied. Bidders shall submit a proposed schedule along with their bid so that the US Forest Service can manage tenants accordingly.

PERSONNEL QUALIFICATIONS

All work shall be performed by a contractor licensed to install scheduled items in the State of

California.

mailto:christopher.s.bielecki@usda.gov

PROJECT LOCATION

A map of complex locations has been provided in the contracting documents and sites are generally locatable through online mapping applications. Approximate GPS coordinates of each complex along with aerial images inticating building locations within each compound have also been provided in the Building Locations document. Some sites require travel on National Forest roads which can be infeasible in the winter depending on conditions. Some NF routes may also be in use for log haul and as such, logging truck traffic should be anticipated. For further information, or directions, contact

Forest Engineer, Christopher Bielecki at (530) 233-8850 christopher.s.bielecki@usda.gov.