RFI Official Responses.pdf

PDF 121 KB Posted

Attached to
127EAW23R0060 - Sandy Bar River Access Road Repair
Solicitation number
127EAW23R0060
Issued by

About this file

This document contains responses to requests for information (RFIs) related to solicitation number 127EAW23R0060 for repair of the Sandy Bar River Access Road. The United States Forest Service solicitation is for a project to recondition approximately 2,000 feet of road, including grading and pulling ditches. Per the RFI responses, the contractor may use water from the river for construction if a screened intake is used, no riprap will be provided by the Forest Service, disposal will be at a designated site, and the contractor can camp on site.

View the file

Other files

File Type Posted
A00001 - RFI Responses.pdf PDF
2. Schedule.docx DOCX document
3. Location Map, Drawings, General Notes.pdf PDF
7. Wet Weather Operations.pdf PDF
8. Davis-Bacon Act WD # CA20230007.pdf PDF
4. Project Specification List.pdf PDF
6. Fire Plan.pdf PDF
5. Supplemental Specifications.pdf PDF
127EAW23R0060 - Sandy Bar River Access Road Repair.pdf PDF
9. RFI Form.docx DOCX document
1. Statement of Work.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

REQUEST FOR INFORMATION (RFI) OFFICIAL RESPONSES

127EAW23R0060 - Sandy Bar River Access Road Repair

RFI responses will be responded to as necessary in amendment format which will be posted to the solicitation via beta.SAM.gov

Telephone requests for information will not be accepted or returned.

RFI #1 – May Contractor use water from river for construction?

USFS Response – Yes, site will be designated by COR. Water drafting from stream requires a screen mesh. The screen mesh must be in good repair and present a sealed, positive barrier-effectively preventing entry of immature fish or other aquatic wildlife into the intake.

RFI #2 – Is there a FS Rip Rap site Available?

USFS Response – No, Rip Rap shall be furnished by contractor.

RFI #3 – Does the forest Service have a disposal site?

USFS Response – Yes, disposal site will be designated by COR.

RFI #4 – What is the total length of the job? Road Recondition, grading, pull ditch. Start and stopping point?

USFS Response – The length of the road to be treated is a distance of around 2,000 feet.

RFI #5 – What is the treatment for the large hole in the bottom.

USFS Response – No large holes to be treated.

RFI #6 – May contractor camp on site?

USFS Response – Contractor may camp on site.