HENSHAW FIRE STATION RESIDENCE REROOF
STATEMENT OF WORK - REVISION 001
STATEMENT OF WORK - REVISION 001
1 SCOPE OF WORK
This project work includes, but is not limited to the following:
a. Henshaw Fire Station Residence building existing roof type is asphalt composition shingle and is approximately 1650 square feet. Reroof structure by removing all roofing shingles and underlayment down to the substrate material.
b. Remove gutters as necessary and reset after roof work is completed.
c. Remove existing and install all new fascia boards and soffit, approximately 250 linear feet.
d. Replacement of roof underlayment, shingles, flashing, drip edge, vent, sleeves, and collars, and add an approved moisture protection material and all incidentals.
e. The existing residence building was constructed in 1936. Recent lead-based paint sampling and testing was completed, and the eaves were shown to have lead-based paint. Asbestos sampling and testing were recently completed, and roof components were shown to have asbestos. See the Specification Section 02 41 00 Demolition, for the guidelines for removal and disposal of hazardous materials.
f. Existing conditions shall be verified by the Contractor. The roof area is approximately 1650 square feet and shall be verified by Contractor. Contractor shall inspect existing roof prior to beginning construction and bring to the attention of the Contracting Officer any discrepancies not covered by contract work listed herein. A site visit is highly recommended prior to bidding.
g. All work shall be performed in a manner to minimize ground disturbance.
h. HAZARDOUS MATERIALS: Hazardous building materials include, but are not limited to, asbestos and lead containing materials.
a. The contractor must be a licensed and/or accredited contractor to inspect, handle, and remove asbestos and lead in California. The contractor must follow all OSHA, local, California state, and federal regulations for handling, removal, and transportation of the hazardous material.
b. Asbestos that is friable, or may become friable, must be removed from the structures prior to demolition.
c. The Limited Asbestos and Lead Sampling Report is attached to the solicitation.
i. OPTION ITEM 1: Remove and replace roof substrate decking material with like material where required to complete necessary work. Approximately 50 square feet of decking repair work is estimated; however, this quantity may change when substrate material is exposed. All repair work is to be discussed with the Contracting Officer prior to substrate replacement. Contractors shall submit a Request for Information
(RFI) after a site visit if the contractor anticipates a larger area of substrate material needing replacement than what has been indicated in the solicitation.
Total work time is 25 calendar days from the issuance of the Notice to Proceed.
STATEMENT OF WORK
2 PROJECT LOCATION
Henshaw Fire Station, San Diego County, Palomar Ranger District
From San Diego travel north on Interstate 15 to Pala, CA and take Highway 76. Turn right on Highway
76 and travel east ~ 40 miles. The Henshaw Fire Station is on the right. The site address is 26147 Hwy
76, Santa Ysabel, CA 92070.
3 FOREST CONTACT
For information regarding site conditions, contact Tammie Mather at (858) 674-2972 between the hours of 8:00 am and 4:00 pm, Monday through Friday, except legal holidays.
4 PROJECT MANAGEMENT
The contractor shall appoint a Project Manager to coordinate all Contractor’s activities during construction and to liaise with the Contracting Officer Representative (COR) and/or Contracting Officer
(CO), and Project Engineer for the USDA Forest Service. Contractor shall designate in writing an on-site superintendent to be on-site at all times that any construction activities take place and to coordinate all site work and activities.
5 GENERAL INFORMATION
5 - 1 Parking and Storage
The Contractor shall coordinate parking of their vehicles and temporary storage of equipment and materials with the Contracting Officer. Contractor shall have all heavy equipment washed prior to entering the project area to remove soil, seeds and plant material from noxious weeds to prevent the introduction and spread of weeds not already present on Descanso Ranger District or the Cleveland
National Forest. Inspections shall be coordinated and scheduled with the Contracting Officer’s
Representative at least 2 days prior to equipment arriving on site.
6 SPECIFICATIONS
The Construction Specification Institute (CSI) specifications applicable to this contract are listed below:
00 01 10 TABLE OF CONTENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 31 00 PROJECT MANAGEMENT AND COORDINATION
01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SUBMITTALS
01 40 00 QUALITY REQUIREMENTS
01 41 00 REGULATORY REQUIREMENTS
01 57 24 STORMWATER POLLUTION CONTROL
01 71 13 MOBILIZATION
01 74 00 CLEANING AND WASTE MANAGEMENT
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
02 41 00 DEMOLITION
06 10 00 ROUGH CARPENTRY
07 00 00 THERMAL AND MOISTURE PROTECTION
07 31 13 ASPHALT SHINGLES
07 62 00 FLASHING AND SHEET METAL
07 92 00 JOINT SEALANTS
09 90 00 PAINTING
7 DELIVERABLES
7-1 Fire Plan
See the Fire Plan for fire restrictions and requirements, emergency contact information, and fire project activity levels.
7-2 Work Plan
The Contractor(s) shall provide the Government with two (2) copies of the Work Plan for the project prior to mobilization. This Work Plan shall include, but is not limited to, the following:
• A description of how the work will be performed.
• Specific exclusions/ assumptions regarding the specific work to be performed.
• A listing of personnel, including subcontractor(s), working on the project.
• A list of equipment proposed for use on the project.
• A Project Work Schedule.
• Detailed cost estimate/cost breakdown of work to be performed per Specification Section that can be used for partial payments as work is completed and accepted.
7-3 Storm Water Management Plan
Contractor shall develop an Erosion Control/Storm Water Control Plan. Contractor shall identify and address all types and specific locations of erosion control measures.
7-4 Construction Waste Management Plan
Contractor shall develop a proposal on how to collect, segregate, and dispose of all construction wastes and debris produced by the work of this contract, including hazardous materials, according to all applicable regulations.
7-5 Spill Prevention Control and Countermeasures (SPCC), spill response plan and an emergency response plan for refueling and servicing vehicles.
Identify and use suitable measures around vehicle service, storage and refueling areas, and waste dumps to fully contain spills and avoid or minimize soil contamination and seepage to groundwater. Use suitable measures to avoid spilling fuels, lubricants, cleaners, and other chemicals during handling and transporting. Report spills to the Contracting Officer’s
Representative and initiate suitable cleanup action in accordance with applicable State and
Federal laws, rules, and regulations.
7-6 Hazardous Materials Abatement Work Plan
Contractor shall develop an Abatement Work Plan for lead-based paint and asbestos abatement.
END OF STATEMENT OF WORK