GAOA McKinley Grove Trail Maintenance
Solicitation number
127EAW22Q0020
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15A.NAME AND TITLE OF SIGNER (Type or print) 16A.NAME AND TITLE OF CONTRACTING OFFICER

Contracting Officer

16B.UNITED STATES OF AMERICA

By

(Signature of Contracting Officer)

15C.DATE SIGNED

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT CONTRACT ID CODE PAGE 1 OF 4 PAGES

2 AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

5/31/2022

4. REQUISITION/PUCHASE REQ. NO. 5. PROJECT NO.(IF APPLICABLE)

6. ISSUE BY CODE 7.ADMINISTERED BY (if other than item 6) CODE

USDA FOREST SERVICE

OAK KNOLL RD KLAMATH NF

PO BOX 10

KLAMATH RIVER CA 96050

8.NAME AND ADDRESS OF CONTRACTOR(No., street, county, State and ZIP Code) 9A.Amend Solicitation. 127EAW22Q0020

9B.Dated 5/16/2022 10A.Mod Contract/Order # 10B.Dated (see Item 13) code facility code

11. THIS ITEM APPLIES ONLY TO AMENDMENT OF SOLICITATION

[x] The above numbered solicitation is amended as set forth in the item 14. The hour and date specified for receipt of Offers [ ] is extended [X] is not extended. Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15 and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted, or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegam or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting and Appropriation Data (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. This change order is issued pursuant to; (specifiy authority) The changes set forth in item 14 are made in the Contract/Order # in item 10A.

B. The above numbered Contract/Order is modified to reflect the administrative changes (such as changes in paying office, appropriation date, etc.) set forth in item 14, pursuant to the authority of FAR 43.103(b)..

C. This supplemental agreement is entered into pursuant to authority of:

D Other: (Specify type of modification and authority):

E. IMPORTANT: Contractor [ ] is not [ ] is required to sign this document and return _ Original to the issuing office.:

14. DESCRIPTION OF AMENDMENT/MODIFICATION

GAOA MCKINLEY GROVE RECREATION TRAIL

THIS AMENDMENT IS TO INCORPORATE AN UPDATED SCHEDULE OF ITEMS AND REQUESTS FOR INFORMATION.

15B.CONTRACTOR/OFFEROR

By (Signature of person authorized to sign)

16C.DATE SIGNED

Standard Form 30 Prescribed by GSA FAR (48CFR) 53.243

Item No. Description Unit Quantity Unit Price Total Cost

1050 CONSTRUCTION STAKING LS 1

1442 QUALITY CONTROL AND QUANTITY

MEASUREMENT

LS 1

1505 MOBILIZATION LS 1

1550 INSTALL BEST MANAGEMENT PRACTICES

(BMPS) (includes fiber rolls, wattles, erosion control products, etc.)

LS 1

2100 DEMOLITION - REMOVAL AND DISPOSAL OF

EXISTING FACILITIES (includes signs, asphalt surface trail, board edge along the asphalt surface trail, etc.)

LS 1

2100 SLASH CLEANUP LS 1

2340 CONSTRUCT AGGREGATE BASE - 3" DEPTH, 5'

WIDTH, AND 2166' LENGTH (includes 2077LF for asphalt surface trail, 25LF for asphalt aprons, and 64LF for asphalt access aisles)

CY 100

2513 CONSTRUCT ASPHALT SURFACE (PG 64-10) -

3" DEPTH, 5' WIDTH, AND 2166' LENGTH

(includes 2077LF for asphalt surface trail, 25LF for asphalt aprons, and 64LF for asphalt access aisles)

TON 200

2580 INSTALL STRIPING LS 1

2725 INSTALL ROCKLINED DITCH LF 110

2818 CONSTRUCT PICNIC SITES (includes hardened aggregate surface)

SQ FT 810

2830 CONSTRUCT OUTDOOR RECREATION

ACCESS ROUTES (ORARS) (includes hardened aggregate surface at interpretive signs)

SQ FT 728

2873 INSTALL PICNIC TABLES EA 3

2883 INSTALL ENTRANCE SIGN EA 2

2883 INSTALL BULLETIN BOARDS (includes hardened aggregate surface)

EA 2

2883 INSTALL SIGNS EA 13

TOTAL

31-May-22

SCHEDULE OF ITEMS

MCKINLEY GROVE RECREATION TRAIL MAINTENANCE AND

HIGH SIERRA RANGER DISTRICT

SIERRA NATIONAL FOREST

FRESNO COUNTY

INTERPRETIVE CENTER REHABILITATION PROJECT

McKinley Grove Requests for Information 31 May 2022

1. 1050.4.3 survey precision asphalt paving elevation +/- 0.02 feet. The nature of asphalt trails is such that the intent is to flow in both grade and alignment.

Being held to a set elevation within ¼” is next to impossible. FSORAG has exceptions on this. Can this requirement be removed as long as the trail is built to the required slope and thickness?

Answer: A new section on Accessibility Requirements has been added to sections 1050, 2340, and 2513. The accessibility requirements take precedents over the +/-0.02 feet elevation. See attached revised specifications.

2. The paver requirement states that auto grade control be used. For trail paving it is not common to have grade control on trail pavers Can this requirement be removed from the specs?

Answer: No – the requirement will not be removed. Is contractor proposing to use manual control in lieu of auto control? If so, have the contractor reference section

2513.3.3 and address in their proposal.

When the Forest Service deems that the automatic screed control operation is not practical under a particular set of conditions, he may order the use of manual control in lieu thereof. However, the machine shall be equipped with the automatic device.

3. The compaction requirements call for a 6 ton minimum vibratory roller. For trail paving this size of machine is too large. Can this requirement be removed?

Answer: No – the requirement will not be removed. What is the contractor proposing to be used in lieu of the 6 ton minimum vibratory roller for compaction? Please have the contractor address in their proposal.

4. The compaction requirement for asphalt density is minimum of 92% and average of 95%.

For trail work compaction sometimes is hard to achieve due to the maximum size of roller allowed and hauling and placing of asphalt in a timely manner. The forest service has STANDARD SPECIFICATIONS FOR CONSTRUCTION OF TRAILS AND TRAIL BRIDGES ON FOREST SERVICE PROJECTS, section 913.20 - Hot Asphalt Plant Mix Trail Surfacing has compaction guidelines for trail paving compaction. Can the designated compaction requirements be removed and use of the “STANDARD

SPECIFICATIONS FOR CONSTRUCTION OF TRAILS AND TRAIL BRIDGES ON

FOREST SERVICE PROJECTS” be used on this project?

Answer: Forest Service needs more information. What is the minimum compaction requirement that can be achieved for asphalt density for trail work?

5. The bid quantity on line 006 shows only 810 sq. ft. Can this be adjusted to include all the asphalt paving sq. ft.?

Answer: Reference new amendment from contracting officer.

6. Line 11 of the solicitation states completion is within 10 days of notice to proceed. Is this the expectation for completion?

Answer: In block 11 of the solicitation, SF1442, it states “The Contractor shall begin performance 10 calendar days and complete it within 90 calendar days after receiving the notice to proceed”.

Schedule of Items Amendment 2.pdf.pdf
ScheduleOfItems