This document is a set of questions and answers from a site visit related to Solicitation Number 127EAT24Q0029 for Landscape Services for the USDA Forest Service Region 5 Regional Office Building. The key details are:

The solicitation is for landscape services including tree/shrub removal and replacement, planting, irrigation system work, and other landscaping tasks at the Region 5 Regional Office in Vallejo, CA. The contract period is from April 1, 2024 to June 28, 2024. The solicitation requires a certified irrigation designer, drought-resistant plantings, and use of recycled/recyclable materials. Specific requirements include removing existing irrigation, evaluating the water supply equipment, and designing a new 100% coverage drip irrigation system. For planting, the contractor must remove dead/diseased vegetation, grind stumps, and plant new drought-resistant shrubs, ground cover, and trees in specified areas around the facility. The contractor must also apply slow-release organic fertilizer and install 3-inch deep natural wood mulch. A site visit was held and the questions and answers cover topics like tree/stump removal, irrigation design software, and the solicitation timeline. The due date for proposals was extended from April 8th to April 9th.

View the file

Other files

File Type Posted
Landscape Renewal pre-bid meeting sign in sheet.pdf PDF
127EAT24Q0029.pdf PDF
Wage Determination.pdf PDF
127EAT24Q0029.pdf PDF
R5RO-SOW-Landscape Renewal with Appendix.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

127EAT24Q0029 – Landscape Services for USDA FS Region 5 RO Building Site Visit RFI’s and Answers

1. Will there be any work required on tree by the solar panel?

A: No, tree has already been removed. There is nothing in SOW regarding removal of tree by any solar panel.

2. What to do with the stumps?

A: Stumps need to be ground

3. What do you require of the conifer trees? They should not be touched during summer time?

A: If any work needs to be done on these types of trees it can be done after the summer period.

4. What is the preferred software for the design?

A: Autocad is preferred. Hand drawn is also acceptable as long as turned in to a PDF.

5. Can we design design first and then bid on winning design?

A: No, contract will encompass everything for this project. Design and work all at once. We do not consider it a complex project.

6. Will you require a certified Irrigation designer?

A: Yes, it is stated in SOW that a Certified Irrigation Designer is required for this project. Please read point number 7 of SOW for requirements of the Irrigation work.

7. Are weeds part of the contract?

A: NO weeds are not part of this requirement.

8. Will there be an extension to quote due date?

A: Yes, due date will be extended 1 day. Due date will be April 9th at 3:00 PM Pacific.