Questions and Answers.docx

DOCX document 13 KB Posted

Attached to
Sierra National Forest, Buffin Meadow Site Prep Federal contract opportunity
Solicitation number
127EAS23Q0124
Issued by
Department of Agriculture Forest Service

About this file

This document contains questions and answers related to solicitation 127EAS23Q0124 from the Department of Agriculture Forest Service. The solicitation is for site preparation work at the Sierra National Forest Buffin Meadow area with an estimated completion date of December 31, 2023. The 33-day estimated period to complete the work is considered a more accurate timeframe than the placeholder completion date. Reasonable delays outside the contractor's control would result in a timeline extension without holding the contractor responsible.

View the file

Other files for this federal contract opportunity

Other files attached to Sierra National Forest, Buffin Meadow Site Prep, newest first.
File Type Posted
Fire Plan_BLRD.doc DOC document
127EAS23Q0124 A00001.pdf PDF
Fish Camp 10a10d Site Prep Contract Fy2022.pdf PDF
127EAS23Q0124.pdf PDF
SAM WD.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and answers for

RFQ 127EAS23Q0124

Sierra NF Buffin Meadow Site Prep

Q. I see that the contract should be completed in 33 days. But is there a date for completion? IE December 31, 2023?

A. That is correct. The estimated days to complete is 33 days. I posted the estimated completion date for the project as 31 December 23 as an estimate and placeholder for our system.

The 33 days to complete is a more accurate estimate of the project scope and should be referenced to assist in developing a project completion timeline.

Additionally, if the actual completion date shifts forward or backward due to a reasonable delay caused by conditions outside of the control of the contractor or a stop work order is issued by the FS, it is the intent of the FS to give an extension to the timeline and not hold the contractor responsible for the delays outside of the contractor's control.