SOL_1263A919R0007.pdf
PDF 2 MB Posted
- Attached to
- FR 170 Crescent to Brule Road Repair
- Solicitation number
- 1263A919R0007
About this file
Solicitation 1263A919R0007
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J2_-_Davis_Bacon_Wage_Determination_MN56.pdf | ||
| J1_-_FR_170_Crescent_to_Brule__Drawing_Package.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART I - SCHEDULE OF ITEMS
SECTION B – SERVICES AND PRICES
The Grade – Crescent Lake Campground to Brule Lake Road Resurfacing
FR 170
Superior National Forest
Cook County
B- 1 - SCHEDULE OF ITEMS
ITEM
NO.
DESCRIPTION PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
15101 Mobilization Lump Sum 1 $_________ $__________ 15201 Construction survey and staking, tolerance A Lump Sum 1 $_________ $__________ 15401 Contractor Testing Lump Sum 1 $_________ $__________ 20301 Removal of Existing Culverts, disposal method A Lump Sum 1 $_________ $__________
30207a 6” Aggregate Surfacing, grading P (MnDOT Class 1 Modified), Crescent Lake CG to Brule Lake Road (LV, Compaction A) Cubic Yard 15400 $_________ $__________
30207b Additional Aggregate Surfacing, Grading P, Compaction A Cubic Yard 620 $_________ $__________ 30302a Ditch Reconditioning – Cleaning Foot 4985 $_________ $__________ 31203 Calcium Chloride, .3gal./s.y., method 1 Gallons 19000 $_________ $__________ 31403 Development of government furnished source Lump Sum 1 $_________ $__________
60201a 18” diam polymer-coated pipe culvert, 14 ga (no bands) Foot 196 $_________ $__________ 60201b 21” diam polymer-coated pipe culvert, 14 ga (no bands) Foot 786 $_________ $__________ 60201c 24” diam polymer-coated pipe culvert, 14 ga (no bands) Foot 322 $_________ $__________ 60201d 30” diam polymer-coated pipe culvert, 12 ga (no bands) Foot 166 $_________ $__________ 60201e 36” diam polymer-coated pipe culvert, 12 ga (no bands) Foot 46 $_________ $__________ 60202a 17” x 13”, polymer-coated pipe culvert, 14 ga (no bands) Foot 54 $_________ $__________ 60202b 28” x 20”, polymer-coated pipe culvert, 14 ga (no bands) Foot 120 $_________ $__________ 62550 Turf establishment Lump Sum 1 $_________ $__________ 63501 Temporary Traffic Control Lump Sum 1 $_________ $__________
Total: $__ ______
Optional Items 31203a Calcium Chloride, .3gal./s.y., method 1 – Lk Cty 7 – FR 346 Gallons 14250 $_________ $__________ 31203b Calcium Chloride, .3gal./s.y., method 1 – FR 346 – Sawbill Trail Gallons 26300 $_________ $__________ 31203c Calcium Chloride, .3gal./s.y., method 1 – Sawbill – Crescent Lake Gallons 21500 $_________ $__________ 31401a Stockpiled Aggregate, grading P (MnDOT Class 1 modified) (LV) Cubic Yards 2500 $_________ $__________ 31401b Stockpiled Aggregate, grading P (MnDOT Class 1 modified) (LV) Cubic Yards 5000 $_________ $__________ 31401c Stockpiled Aggregate, grading P (MnDOT Class 1 modified) (LV) Cubic Yards 10000 $_________ $__________ 30207c 2” Aggregate surface course from Whitefish Pit Stockpile, Lake County 7 to FR 346, (LV), Compaction A Cubic Yard 3700 $_________ $__________
30207d Aggregate Surfacing, Grading P,(LV) Haul Road Maintenance Cubic Yards 1800 $_________ $__________ 60201a 18” diam polymer-coated pipe culvert, 14 ga STOCKPILED Foot 596 $_________ $__________ 60201b 24” diam polymer-coated pipe culvert, 14 ga STOCKPILED Foot 392 $_________ $__________ 60202a 21” x 15”, polymer-coated pipe culvert, 14 ga STOCKPILED Foot 300 $_________ $__________ 60202b 28” x 20”, polymer-coated pipe culvert, 14 ga STOCKPILED Foot 420 $_________ $__________ 60213a 18” diam polymer-coated pipe BAND (24”), 14 ga STOCKPILED EACH 10 $_________ $__________ 60213b 24” diam polymer-coated pipe BAND (24”), 14 ga STOCKPILED EACH 10 $_________ $__________ 60213c 21” x 15”, polymer-coated pipe BAND (24”), 14 ga STOCKPILED EACH 10 $_________ $__________ 60213d 28” x 20”, polymer-coated pipe BAND (24”), 14 ga STOCKPILED EACH 10 $_________ $__________
B-2 - NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.
Payment will be made on actual work performed as described in FP-14 109.01 unless otherwise noted.
1. The Standard Specifications for Construction of Roads and Bridges on Federal Highway Project FP-14 edition has been used for this contract. Copies of this book are available at the USFS engineering office in Ely or Grand Marais.
2. Contract will only be awarded if funds are available. All or none of the optional bid items may or may not be awarded based on bids and funds available.
3. Option #30207D may be awarded dependent on the pit and route contractor uses and spread as agreed with Government on haul road.
4. All clearing, grubbing, bedding, borrow, backfill, detours, diversions, signing, and other miscellaneous items not listed above with unique bid items shall be considered incidental to the contract. See 109.05
5. Quantities for crushed aggregate are loose volumes.
SOL NO 1263A919R0007
UNIT Gunflint RD PROJ NAME; FR 170 Crescent to Brule PAGE 3 of 54
CONSTRUCTION RFQ
CONSTRUCTION RFQ SOL NO 1263A919R0007
UNIT Gunflint RD PROJ NAME; FR 170 Crescent to Brule
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Table of Contents Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04
104.06 Use of Roads by Contractor
105 - Control of Material
105.02(a) Government-provided sources
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.02 Visual Inspection
107 - Legal Relations and Responsibility to the Public
Delete Subsection 107.05
108 - Prosecution and Progress
Delete Section 108
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09
109.02 Measurement Terms and Definitions
152 - Construction Survey and Staking
152.04 General
152.05 Survey and Staking Requirements
Table 152-1 Construction Survey and Staking Tolerances
153 - Contractor Quality Control
153.02 Qualifications
153.03 Quality Control Plan
153.07 Records and control charts
PROJ NAME; FR 170 Crescent to Brule
155 - Schedules for Construction Contracts
Delete Section 155
156 - Public Traffic
157 - Soil Erosion and Sediment Control
157.04 General
302 - Minor Crushed Aggregate
314 - Stockpiled Aggregates
314.01 Description
314.04 Stockpile Site
314.06 Acceptance
625 - Turf Establishment
703 - Aggregate
703.05 Subbase, Base, Surface Course, and Screened Aggregate
704 - Soil
704.02 Bedding Material
704.08 Select Granular Backfill
704.08 Select Granular Backfill. (a) Quality requirements. (2)
704.08 Select Granular Backfill. Table 704-2
707 – Metal Pipe
707.08 Polymer-Coated Steel Pipe
PROJ NAME; FR 170 Crescent to Brule
Preface
Preface_wo_02_08_2018
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.
101 - Terms¸ Format¸ and Definitions 101.01_National_9_15_2016
Add the following paragraph to Subsection 101.01:
101.01 Meaning of Terms.
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_National_4_7_2015
Add the following to Subsection 101.03:
101.03 Abbreviations.
(a) Acronyms.
AGAR — Agriculture Acquisition Regulations AFPA — American Forest and Paper Association FSAR — Forest Service Acquisition Regulations MSHA — Mine Safety and Health Administration NESC — National Electrical Safety Code WCLIB — West Coast Lumber Inspection Bureau
(f) Miscellaneous unit abbreviations.
MP — milepost location ppm — parts per million volume STA station location
101.04_National_10_23_2016
Make the following changes to Subsection 101.04:
101.04 Definitions.
Delete these definitions and replace the following:
Bid Schedule — The Schedule of Items.
Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.
Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.
Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.
PROJ NAME; FR 170 Crescent to Brule
Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.
Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.
Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.
Add the following definitions:
Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line — A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road — Temporary construction access built along the route of the project.
Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction.
Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.
Utilization Standards — The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid¸ Award¸ and Execution of Contract 102.00_National_9_15_2016
Delete Section 102 in its entirety.
Delete Section 102.
103 - Scope of Work 103.00_National_9_15_2016
Delete all of Section 103 except Subsection 103.01 Intent of Contract.
Delete Subsections 103.02, 103.03, 103.04, 103.05.
104 - Control of Work
104.00_National_9_15_2016 Delete Subsections 104.01, 104.02, and 104.04.
Delete Subsections 104.01, 104.02, 104.04.
104.06_National_9_16_2016
Add the following to Subsection 104.06:
104.06 Use of Roads by Contractor.
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_National_10_23_2016 Add the following to Subsection 105.02(a):
105.02(a) Government-provided sources.
Government-provided sources for this project are identified as follows:
(1) Government-provided mandatory sources.
Pay Item Description Material source number or name
(2) Government-provided optional sources for this project are identified as follows:
Pay Item Description Material source number or name All Crushed Aggregate Dog Tired Pit - T61nR4wS30
Mississippi Creek Pit – T62nR3wS25 Clara Lake Pit – T61nR3wS07
If the Contractor elects to obtain material from Forest Service pits the following applies:
(1) Materials may be used free of charge from Forest Service pits.
(2) If specified gradation cannot be met with materials available at Forest Service pit sites it will be the contractor’s responsibility to provide material from other sources at no additional cost to the Government. Quality and quantity is not guaranteed in Forest Service Pits.
(3) Clearing of vegetation will not be allowed during June and July
(4) Pit operation shall conform to section 314.
(5) Contractor may use non Forest Service sources.
106 - Acceptance of Work
106.01_National_7_18_2017 Delete Subsection 106.01 and replace with the following:
106.01 Conformity with Contract Requirements.
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range.
The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be
PROJ NAME; FR 170 Crescent to Brule considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project.
When the Government tests work, copies of test reports are furnished to the Contractor upon request.
Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive.
The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work;
providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
1. Sampling method;
2. Number of samples;
3. Sample transport;
4. Test procedures;
5. Testing laboratories;
6. Reporting;
7. Estimated time and costs; and
8. Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
1. Have the work accepted at a reduced price; or
2. Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.02_National_10_23_2016
Delete Subsection 106.02 and replace with the following:
106.02 Visual Inspection.
Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.
107 - Legal Relations and Responsibility to the Public 107.05_National_7_18_2017
Delete Subsection 107.05.
Delete Subsection 107.05.
108 - Prosecution and Progress 108.00_National_9_16_2016
Delete Section 108 in its entirety.
Delete Section 108.
109 - Measurement and Payment 109.00_National_9_16_2016
Delete Subsections 109.06, 109.07, 109.08, and 109.09:
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.02_National_9_16_2016
Add the following sentence to Subsection 109.02(b):
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
152 - Construction Survey and Staking 152.00_National_12_12_2016
Add the following to Subsection 152.04(c):
152.04 General.
(c) Material.
PROJ NAME; FR 170 Crescent to Brule
Use required stake dimensions and materials. Pre-paint the top 2 inches of all stakes and lath, or mark them with plastic flagging. Use designated colors for paint or flagging. Mark all stakes with a stake pencil that leaves a legible imprint, or with waterproof ink.
Do not use aerosol spray paints.
Use moisture-resistant paper for survey notes. Keep notes in books with covers that will protect the contents and retain the pages in numerical sequence.
Make the following changes to Subsection 152.05:
152.05 Survey and Staking Requirements.
Delete Subsection 152.05(d)(2) and replace with the following:
(d) Slope and reference stakes.
(2) Conventional survey methods. When required, locate slope stakes on designated portions of the road. Locate the slope stake catch points and use them to establish clearing limits and slope stake references.
Mark slope stakes with the station, the amount of cut or fill, the horizontal distance to centerline, and the slope ratios.
Place slope reference stakes at least 10 feet outside the clearing limit and mark with the offset distance to the slope stake. Place sight stakes when required.
Prior to clearing and grubbing operations, move the slope stake outside the clearing limit to the slope reference stake. After clearing and grubbing and before excavation, reset the slope stakes in their original position.
Use the designated method to establish the slope stake catchpoint.
Method I—Computed Method. Use the template information shown in the plans or other Government-provided data to calculate the actual location of the catchpoint. The slope stake “catchpoint distance” provided may be used as a trial location to initiate slope staking.
Recatch slope stakes on any section that does not match the staking report within the tolerances established in Table 152-2.
Method II—Catchpoint Measurement Method. Determine the location of slope stake catchpoints by measuring the catchpoint distances shown in the plans or other Government-provided data.
Add the following to Subsection 152.05(e):
(e) Clearing and grubbing limits.
Mark the clearing limits with flagging or tags on trees to be left standing, or on lath. Make markings intervisible, and no more than 90 feet apart.
After establishing clearing limits, move the location line stake outside the clearing limits for station identification purposes, and mark it with horizontal distance to location line.
Replace Table 152-1 with the following:
Table 152-1 Construction Survey and Staking Tolerances Table 152-1
Construction Survey and Staking Tolerances (1)
Staking Phase Horizontal Vertical
Control points set from existing Government control points- Tolerance Class A
±0.03 feet (±10 millimeters)
±0.01 feet × N
(±3 millimeters × N )(2)
Mapping, topography, and cross-section Points- Tolerance Class A
±0.16 feet (±50 millimeters)
±0.16 feet (±50 millimeters)
Centerline points (3) including (PC), (PT), (POT),(POC), and references- Tolerance Class A
±0.06 feet (±20 millimeters)
±0.06 feet (±20 millimeters)
Slope-stake and slope-stake references- Tolerance Class A (4)
±0.16 feet (±50 millimeters)
±0.16 feet ±50 millimeters)
Culverts, ditches, and minor drainage structures stakes- Tolerance Class A
±0.16 feet (±50 millimeters)
±0.06 feet (±20 millimeters)
Retaining walls stakes ±0.06 feet (±20 millimeters)
±0.03 feet (±10 millimeters)
Curb and gutter stakes ±0.06 feet (±20 millimeters)
±0.03 feet (±10 millimeters)
Bridge substructures stakes ±0.03 feet (±10 millimeters)(5)
±0.03 feet (±10 millimeters)
Bridge superstructures stakes ±0.03 feet (±10 millimeters)(5)
±0.03 feet (±10 millimeters)
Clearing and grubbing limit stakes- Tolerance Class A
±1.00 feet (±300 millimeters)
Roadway subgrade finish stakes- Tolerance Class A (6)
±0.16 feet (±50 millimeters)
±0.03 feet (±10 millimeters)
Roadway finish grade stakes (6) ±0.16 feet (±50 millimeters)
±0.03 feet (±10 millimeters)
Table 152-1 Construction Survey and Staking Tolerances (continued) (1)
Staking Phase Horizontal Vertical
Control points set from existing Government control points –Tolerance Class B (7)
±0.16 feet (±20 millimeters) ±0.16 feet × N
(±20 millimeters × N )(2)
PROJ NAME; FR 170 Crescent to Brule
Mapping, topography, and cross-section points– Tolerance Class B (7)
±1.00 feet (±300 millimeters)
±0.50 feet (±150 millimeters)
Centerline points including (PC), (PT), (POT),(POC), and references–Tolerance Class B (7)
±0.16 feet (±20 millimeters)
±0.16 feet (±20 millimeters)
Slope-stake and slope-stake references–Tolerance Class B (7)
±0.50 feet (±50 millimeters)
±0.16 feet ±50 millimeters)
Culverts, ditches, and minor drainage structures stakes–Tolerance Class B (7)
±0.50 feet (±150 millimeters)
±0.16 feet (±20 millimeters)
Clearing and grubbing limit stakes–Tolerance Class B (7)
±2.00 feet (±600 millimeters)
Roadway subgrade finish stakes–Tolerance Class B (7)
±0.50 feet (±50 millimeters)
±0.16 feet (±10 millimeters)
Roadway finish grade stakes–Tolerance Class B (7)
±0.50 feet (±50 millimeters)
±0.16 feet (±10 millimeters)
(1) At statistical 95 percent confidence level. Tolerances are relative to existing Government control points.
(2) N is the number of instrument setups.
(3) Centerline points: PC - point of curve, PT - point of tangent, POT - point on tangent, POC - point on curve.
(4) Take the cross-sections normal to the centerline ±1 degree.
(5) Bridge control is established as a local network and the tolerances are relative to that network.
(6) Includes paved ditches.
(7) Tolerance Class B for Very Low Volume Roads with an aggregate or native finished surface.
153 - Contractor Quality Control
153.02_National_9_15_2016 Delete Subsection 153.02 and replace with the following:
153.02 Qualifications.
Submit the following for approval with the quality control plan:
(a) Quality control manager (QCM). Furnish a QCM who has at least 2 years experience in construction, inspector, quality control and material testing on construction projects of similar type and scope.
(b) Testers. Provide testers with at least one year experience in the type of sampling and testing required, and with one of the following for the type of sampling and testing performed:
(1) NICET Level II certification in highway material or equivalent state or industry certification;
(2) Certification by a regional certification program (such as Western Alliance for Quality Transportation Construction (WAQTC), Northeast Transportation Technician Certification Program (NETTCP), Southeast Task Force for Technician Training and Qualification (STFTTQ), or Multi Regional Training and Certification (M-TRAC)); or
(3) At least one year employment by an AASHTO accredited laboratory performing equivalent sampling and testing.
153.03_National_9_15_2016 Add the following paragraph to the end of Subsection 153.03(b):
153.03 Quality Control Plan.
(b) Quality Control Procedures.
Submit written proposals for approval of alternate AASHTO or State approved test methods. Alternate methods may be allowed based on documented equivalence to the specified method.
153.07_National_9_15_2016
Delete Subsection 153.07 and replace with the following:
153.07 Records and control charts.
Maintain complete testing and inspection records by pay item number and make them accessible to the
CO.
155 - Schedules for Construction Contracts 155.00_National_9_14_2016
Delete Section 155 in its entirety.
Delete Section 155.
156 - Public Traffic 156.00_National_9_14_2016
Delete Section 156 in its entirety and replace with the following:
Description
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
PROJ NAME; FR 170 Crescent to Brule
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
Permanent Traffic Control 633 Traffic Signing and Marking Material 718 Concrete Barriers and Precast Guardwalls 618 Temporary plastic fence 710.11
Construction Requirements
156.03 General. Accommodate traffic according to MUTCD, approved traffic control plan and this section. Perform work in a manner that ensures safety and convenience of the public. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic.
Delays may not exceed 15 minutes at any one time followed by an open period of no less than 10 minutes. Accommodate public traffic on roads adjacent to and within the project until the project is accepted according to Subsection 106.07(b).
Submit traffic control plan at least 30 days prior to intended use. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved.
Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM 7100-15. All required signs will be in place and approved prior to beginning work on project.
If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.
156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations.
(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.
(c) Install only those traffic control devices needed for each stage or phase.
(d) Relocate temporary traffic control devices as necessary.
(e) Remove devices that no longer apply to the existing conditions.
(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(g) Keep temporary traffic control devices clean.
(h) Remove all temporary traffic control devices upon contract completion or when approved.
(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.
156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.
Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.
PROJ NAME; FR 170 Crescent to Brule
Table 156-1 Temporary Road Closures
Road Number
From Terminus
To Terminus
Maximum Consecutive Days of Closure
Minimum Consecutive Days Open
156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.07 Do not measure Public Traffic for payment. Payment for contract work is provided indirectly.
See Subsection 109.05.
157 - Soil Erosion and Sediment Control
157.04_National_9_14_2016 Delete Subsection 157.04 and replace with the following:
157.04 General.
Thirty (30) days prior to the start of construction, submit a written plan according to subsection 104.03 with all necessary permits that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control without approval.
When erosion control measures are not functioning as intended, take corrective action to eliminate or minimize pollutants in storm water discharges from the project.
302 - Minor Crushed Aggregate 302.00_Forest_3_7_2018
Delete Section 302 in its entirety and replace with following.
302.01 This work consists of constructing one or more courses of aggregate on a prepared surface. Work includes producing aggregate by grid rolling, screening, or crushing methods, or placing pit-run or Government-furnished aggregate.
Surface aggregate grading is designated as shown in Table 703-3.
Subbase and base aggregate grading is designated as shown in Table 703-2.
Screened aggregate grading is designated as shown in Table 703-16.
Size Ratio aggregate grading is designated as shown in Table 703-04.
Material
302.02 Conform to the following Subsections:
Aggregate 703.05 Water 725.01
302.03 General. Prepare the surface on which the aggregate course is placed according to Section 204 or 303 as applicable.
Request approval of the roadbed in writing before placing aggregate.
PROJ NAME; FR 170 Crescent to Brule
Submit target values within the gradation ranges shown in Table 703-2 or 703-3 for the required grading.
After reviewing the proposed target values the CO will determine the final values for the gradation and notify the Contractor in writing.
No quality requirements or gradation other than maximum size will be required for pit run and grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size.
After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 314. Establish stockpile sites at approved locations.
302.04 Mixing and Spreading. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for the specified compaction method. Spread and shape the mixture on the prepared surface in a uniform layer with no segregation of size, and to a loose depth that will provide the required compacted thickness.
Do not place in layers exceeding 6 inches in compacted thickness for aggregate base and surface courses or twice the maximum particle size for screened aggregate. When more than one layer is necessary, compact each layer according to Subsection 302.05 before placing the next layer. Route hauling and leveling equipment uniformly over the full width.
When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.
302.05 Compacting. Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travel-way.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(b)(2).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
302.06 Construction Tolerance. If grade finishing stakes are required, finish the surface to within ±0.10 feet from staked line and grade elevation.
If grade finishing stakes are not required, shape the surface to the required template and check the surface with a 10-foot straightedge. Defective areas are surface deviations in excess of 1/2 inch in 10 feet between any two contacts of the straightedge with the surface.
Correct all defective areas by loosening the material, adding or removing material, reshaping, and compacting.
Ensure that the compacted thickness is not consistently above or below the specified thickness. The maximum variation from the compacted specified thickness is ½ inch.
Ensure that the compacted width is not consistently above the specified width. The maximum variation from the specified width will not exceed +12 inches at any point.
302.07 Maintenance. Maintain the aggregate course to the correct line, grade, and cross-section by blading, watering, rolling, or any combination thereof until placement of the next course. Correct all defects according to Subsection 302.06.
302.08 Acceptance. See Table 302-1 for sampling and testing requirements.
Aggregate gradation and surface course plasticity index will be evaluated under Subsection 106.04. If the aggregate is obtained from a Government stockpile then the above characteristics will be evaluated under Subsection 106.02. Other aggregate quality properties will be evaluated under Subsections 106.02 and
106.04. Placement of aggregate courses will be evaluated under Subsections 106.02 and 106.04.
The allowable upper and lower aggregate gradation limits are the Target Value plus or minus the allowable deviations shown in Tables 703-2 and 703-3.
The allowable upper and lower Plasticity index limits for surface courses are stated in 703.05(c).
Preparation of the surface on which the aggregate course is placed will be evaluated under Section 204 or 303 as applicable.
Measurement
302.09 Measure the Section 302 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.
Measure square yard width horizontally to include the top of aggregate width including designed widening. Measure the square yard length horizontally along the centerline of the roadway.
If the measurement for aggregate is by cubic yard using contract quantities then measure aggregate by the cubic yard in-place once compacted, otherwise measurement for aggregate by the cubic yard is measured by the cubic yard in the hauling vehicle.
Measure thickness perpendicular to the grade of the travelway.
Measure width perpendicular to the centerline.
Payment
302.10 The accepted quantities will be paid at the contract price per unit of measurement for the Section 302 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.
T ab le
-1
Sa m pl in g an d T es tin g R eq ui re m en ts
R ep or tin g T im e
B ef or e us in g in w or k h ou rs
Sp lit pl e
Y es
, w he n re qu es te d
“ “ “ Y es
Po in t o f
Sa m pl in g
So ur ce o f m at er ia l
Fr om w in dr ow o r ro ad be d af te r pr oc es si ng o r fro m a pp ro ve d cr us he r s am pl in g de vi ce pl in g
Fr eq ue nc y pe r t yp e so ur ce o f m at er ia l pe r 1
To ns es t M et ho ds
Sp ec ifi ca tio ns
A
SH
TO
T
A A
SH
TO
T
SH
TO
T
ST
M D
A A
SH
TO
T
SH
TO
C at eg or y
C ha ra ct er is tic
LA
a br as io n
(c oa rs e)
So di um su lfa te so un dn es s l os s
(c oa rs e fi ne
D ur ab ili ty in de x
(c oa rs e fi ne
Fr ac tu re d fa ce s
G ra da tio n
Li qu id L im t
T yp e of cc ep ta nc e (S ub se ct io n)
M ea su re d an d te st ed fo r c on fo rm an
(1
.0
M ea su re d an d te st ed fo r c on fo rm an
(1
.0 4)
M at er ia l o r
Pr od uc t
A gg re ga te so ur ce q ua lit y
3.
Su bb as e, B as e, a nd S ur fa co ur se s
314 - Stockpiled Aggregates 314.00_National_7_17_2017
Add the following to Subsection 314.01:
PROJ NAME; FR 170 Crescent to Brule
314.01 Description.
Pit or quarry development work consists of clearing, grubbing, stripping topsoil, removing overburden, constructing access roads, conducting restoration activities, and performing other incidental work required for pit or quarry development.
Add the following to Subsection 314.04 after the first sentence of second paragraph:
314.04 Stockpile Site.
Submit a plan of operation according to Section 105.02. Perform the work in accordance with MSHA 30 CFR, part 56.
The following shall be included:
1. The actual source location shall be defined by the contractor with flagging prior to any clearing and grubbing.
2. Maintenance of the access road is the responsibility of the user and shall be maintained in a condition to support normal pit traffic.
3. Clearing and grubbing shall consist of removal of all trees, snags, down timber, brush and other vegetative and non-combustible debris within the flagged or staked areas. Slash treatment shall be in accordance with methods shown in Specification 203. Clearing will not be allowed in June and July due to roosting bat restrictions.
4. The topsoil shall be conserved and stockpiled in location agreed upon with Government.
5. Unsuitable material (including waste rock) shall be buried or stockpiled in the pit as directed.
6. Excavation will be allowed to a depth of 24” above ledge rock and the water table except as noted below:
If acceptable material is found below the water table in the pits, it is permissible to excavate below that line upon prior approval. The excavation should form a pond no more than five feet deep with sides sloped 10:1 and the bottom left rough. The location and size of these ponds shall be as staked by the engineer and shall not interfere with pit development.
7. Usable sections of the pit face shall be sloped 2:1 with the tops rounded to blend with the natural ground line. Pits in continuous use may be left vertical with approval.
8. Depleted sections of the pit shall be sloped to a minimum of 4:1 where practical, or less, as directed. These depleted areas of the pit should blend into the surrounding landscape.
Add the following to Subsection 314.06:
314.06 Acceptance.
Developing of government furnished sources will be evaluated under Section 105.
625 - Turf Establishment 625.00_National_10_6_2016
Delete Section 625 in its entirety and replace with the following:
PROJ NAME; FR 170 Crescent to Brule
625.01 This work consists of soil preparation, watering, fertilizing, seeding, and mulching. Seeding and mulching methods are designated as dry or hydraulic.
Material
625.02 Conform to the following Subsections:
Agricultural limestone 713.02 Fertilizer 713.03 Mulch 713.05 Seed 713.04 Tackifiers 713.11 Water 725.01(b)
625.03 General. Apply turf establishment to prepared ground or any disturbed area between May 15 to June 20 or between September 1 to October 15. Apply turf establishment to the areas shown on the plans or worklists within 10 days after completion of ground disturbing activities.
Seeded areas damaged by construction activities shall be reseeded within 10 days of the damage. Do not seed during windy weather or when the ground is excessively wet, frozen, or snow covered.
Assure that all seed and mulch used in the work conforms to the weed free requirements of Section 713.
625.04 Preparing Seedbed. Ensure that the surface soil is in a roughened condition favorable for germination and growth.
625.05 Watering. Maintain moisture as follows:
Moisten seeding areas before seeding and maintain the moisture until turf is established or until final acceptance.
625.06 Fertilizing. Apply fertilizer by the following methods:
(a) Dry Method. Apply the fertilizer with approved mechanical equipment. Hand operated methods are satisfactory on areas inaccessible to mechanical equipment.
(b) Hydraulic Method. Use hydraulic-type equipment capable of providing a uniform application using water as the carrying agent. Add fertilizer to the slurry and mix before adding seed. Add the tracer material when designated by the CO.
Apply fertilizer at the rate of (see below) pounds per acre. Insure that the fertilizer meets the following chemical analysis:
Seasonal Period Type Application Rate Spring 20-10-20 or 17-17-17 10#/1000SF Fall 10-10-20 or 10-20-30 10#/1000SF
625.07 Seeding. Apply seed by the following methods:
(a) Dry Method. Apply the seed with approved power driven seeders, drills, or other mechanical equipment. Hand-operated seeding methods are satisfactory on areas inaccessible to mechanical equipment; or
Furnish and apply 75#/acres the following kinds and amounts of pure live seed:
Common Name Botanical Name % of Mix
PROJ NAME; FR 170 Crescent to Brule
Brome, fringed Bromus ciliates 8 Oat-grass, wild Danthonia spicata 2.4 Wild-rye, Canadian Elymus Canadensis 6 Wheat-grass, slender Elymus tachycaulus 8 Bluegrass, fowl Poa palustris 5 Aster, large-leaved Aster macrophyllus .1 Black-eyed Susan Rudbeckia hirta .2 Vetch, American Vicia Americana .3 Oats Avena sativa 55 Rye grass, annual Lolium italicum 15
Determine the pounds of seed to be furnished per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.
625.08 Mulching. Apply Mulch within 2 hours after seeding by the following methods.
(a) Dry Method. Apply mulch with a hand spreader or a spreader utilizing forced air at a rate of 2000 pounds per acre. Do not mark or deface structure, pavements, utilities, or plant growth with tackifier.
625.09 Protecting and Caring for Seeded Areas. Protect and care for seeded areas including watering according to 625.05. Repair or apply supplemental applications of seed, mulch, fertilizer, and water according to 625.05 as many times as needed until turf is established or final acceptance.
625.10 Acceptance. Material for turf establishment will be evaluated under Subsections 106.02 and 106.03.
Placing of turf establishment will be evaluated under Subsections 106.02 and 106.04.
Measurement
625.11 Measure the Section 625 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable:
When measuring turf establishment and supplemental applications by the acre (hectare), measure on the ground surface.
When measuring water by volume or mass, measure in the hauling vehicle or by metering.
Payment
625.12 The accepted quantities will be paid at the contract price per unit of measurement for the Section 625 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
703 - Aggregate
703.05_National_12_15_2016 Delete 703.05 and replace with the following:
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-2
(2) Liquid limit, AASHTO T 89 25 max.
(3) Plastic limit, AASHTO T 90 Nonplastic
PROJ NAME; FR 170 Crescent to Brule
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 50% min.
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(b) Surface course aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-3
(2) Liquid limit, AASHTO T 89 35 max.
(3) Plastic Index, AASHTO T 90
a) If the percent passing the No. 200 sieve is less than 12% 2 to 9
b) If the percent passing the No. 200 sieve is greater than 12% Less than 2
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 75% min.
(9) Free from organic matter and lumps or balls of clay
Do not furnish material that contains asbestos fibers.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(c) Screened aggregate – Furnish hard, durable particles or fragments of stone, slag, or gravel conforming the following:
(1) Gradation Table 703-16
(2) Plastic Index, AASHTO T 90 Less than 9
(3) Los Angeles abrasion, AASHTO T 96 55% max.
(4) Free from organic matter and lumps or balls of clay.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
PROJ NAME; FR 170 Crescent to Brule
Delete Table 703-2 and replace with the following:
ab le
-2 ar ge t V al ue R an ge s f or
S ub ba se a nd
B as e G ra da tio n
Pe rc en t b y M as s P as si ng D es ig na te d Si ev e
(A A
SH
T
O T an d
T
1)
G ra di ng
D es ig na tio n
E (B as
(6
(6
(4
4.
7.
(3
T he v al ue in th e pa re nt he se s i s t he a llo w ab le d ev ia tio n
) f ro m th e ta rg et v al ue s..
D (B
(6
(6
(6
(4
4.
7.
(3
C (B
(6
(6
4.
–7 .0
(3
B (S ub ba se
(8
4.
.0 (4
A (S ub ba se
(7
(6
(4
4.
8.
(3
Si ev e Si ze
2½ ch
1½
3/
1/
N o.
N o.
PROJ NAME; FR 170 Crescent to Brule
Delete Table 703-3 and replace with the following:
T ab le
-3 ar ge t V al ue R an ge s f or
S ur fa ce
G ra da tio n Pe rc en t b y
M as s P as si ng
D es ig na te d
Si ev e (A
A
SH
T O
T an d T
1) ra di ng D es ig na tio n U
(6
(5
8.
.0 (4
T he v al ue in th e pa re nt he se s i s t he a llo w ab le d ev ia tio n
) f ro m th e ta rg et v al ue s.
If th e pl as tic ity in de x
(P I) is gr ea te r t ha n 0, th e
TV
ra ng e fo r t he N o.
si ev e siz e is
-1
(4
(5
8.
.0 (4
P
-9
-8
-7
-4
(5
.0
5.
(4
H
(6
(6
(5
9.
.0 (4
(6
(6
(5
.0
6.
(4
F 10
-1
-8
-6
(6
-5
-3
(6
-2
(5
.0
-1 6.
(4
Si ev e Si ze
N o.
N o.
N o.
PROJ NAME; FR 170 Crescent to Brule
Add Table 703-13:
Table 703-16 Gradation Requirements for Screened Aggregate
Sieve Size
Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)
Grading Designation
L M N O P Q R
6 inch 100 100
4 inch 100 100
3 inch 100 100
2 inch 100
No. 4 15-45 15-45 15-45
704 - Soil
704.02_National_10_6_2016 Delete Subsection 704.02(a) and replace with the following:
704.02 Bedding Material.
(a) Maximum particle size
3 in (75 millimeters) or half the corrugation depth, whichever is smaller
704.08_National_10_6_2016 Make the following changes to Subsection 704.08:
704.08 Select Granular Backfill.
Delete Subsection 704.08(a)(2)
704.08 Select Granular Backfill. (a) Quality requirements. (2)
Delete Table 704-2 and replace with the following:
704.08 Select Granular Backfill. Table 704-2
Table 704-2 Select Granular Backfill Gradation
Sieve Size
Percent by Mass Passing Designated Sieve
(AASHTO T 27 & AASHTO T 11)
4 inch (100 mm) 100 No. 40 (425 µm) 0 – 30 No. 200 (75 µm) 0.0 – 8.0
707 – Metal Pipe
Add the following to Subsection 707.08:
707.08 Polymer-Coated Steel Pipe.
All culverts shall be one continuous length with no bands allowed.
PROJ NAME; FR 170 Crescent to Brule