More RFIs and Responses.docx

DOCX document 27 KB Posted

Attached to
Installation of Predator Fence
Solicitation number
12639526Q0127
Issued by

About this file

This is a Questions and Answers document containing clarifications on technical specifications and contractor responsibilities for a high-tensile woven wire fence installation project for wolf abatement in Bayfield County, Wisconsin, sponsored by USDA's Animal and Plant Health Inspection Service, Wildlife Services.

Key clarifications address ditch crossings, electric fence requirements, and terrain conditions. Regarding ditch crossings, the landowner will be responsible for constructing any required culvert crossings; the contractor should expect little to no sizeable ditch crossings outside of designated break-away fence areas. The break-away fence portion (Section M) maintains the same installation specifications as the main fence, utilizing posts and all standard components but in isolated sections designed to separate and minimize flood damage. For electric fence specifications, the contractor is responsible for supplying the charger with standard output of 3 joules per mile of high-tensile fence, powered by AC rather than solar. Regarding terrain conditions at the Ashland County site, minimal rock requiring drilling is anticipated; the site predominantly consists of clay soil.

View the file

Other files

File Type Posted
RFIs and Responses.docx DOCX document
Attachment 3_Federal Construction Wage Rates.txt TXT text file
Attachment 2_aerial photos.pdf PDF
12639526Q0127.docx DOCX document
Attachment 1_ statement of work.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

More RFIs and Responses

1. Ditch crossings:

0. Outside of the Break-away fence, how prevalent are large ditch crossings? There should be little to no other sizeable ditch crossing besides the break-away locations. The break-away areas are for addressing the ditches large enough to be a concern.

0. The specs note potential need to build culverts for larger crossings - would that be the responsibility of the Contractor? If so, are any of the ditches from the above question expected to require that?

0. We ask because that would theoretically require different equipment/process than a typical water gap. The landowner will be responsible for constructing a culvert crossing.

0. The Break-away fence (Section M) mentions it "must adhere to the previously described installation specifications required of the main fence". However, the ditch crossings (Section N) seem to imply that there will be no posts driven and will instead be on a guide wire. Can you help to confirm our understanding of the Break-away? The breakaway portion is designed to be exactly the same as the main fence, just isolated. Still using posts and all of the components, just not a continuous section, but isolated so in the event of severe flooding, only the isolated portion will be affected.

1. Electric fence:

0. Is the Contractor responsible for supplying the charger? If so, how many joules? Yes, and standard practice would be 3 joules of output per mile of high tensile fence. Will it be solar powered or AC? AC

1. Terrain:

Based on a review of our software, there does not appear to be much rock that would require drilling. If possible, can you please confirm your understanding of that? The site in Ashland County that I am working with has very little rock. Just lots of clay.