Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
The purpose of this amendment is to:
1. Replace the Pricing Schedule and Statement of Work in their entirety with the attached versions.
2. Change the required response date and time to December 19, 2018 by 5 p.m. Eastern.
(See Continuation Pages for details.)
USDA APHIS
250 MARQUETTE AVE.
SUITE 410
MINNEAPOLIS, MN 55401
See Item 6
J
12639519Q0039
1 8
12/07/2018
11/28/2018
UNIT PRICE TOTAL
PRICING SCHEDULE (Amendment 0001)
ITEM QTY UNIT *
BASE PERIOD (Contract Award Date through September 30, 2019)
001 Weekly Laboratory Analysis Report: 38 Each ________ _________
Report includes the following:
Biological Oxygen Demands
Corrosivity pH
Total Suspended Solids
002 Monthly Laboratory Analysis Report: 12 Each ________ _________
Oil and Grease
003 Monthly Laboratory Analysis Report:
Total Organic Carbon 12 Each ________ _________
004 Annual Laboratory Analysis Report:
Lead and Copper 1 Each ________ _________
OPTION YEAR 1 (October 1, 2019 - September 30, 2020)
005 Weekly Laboratory Analysis Report: 52 Each ________ _________
Report includes the following:
Biological Oxygen Demands
Corrosivity pH
Total Suspended Solids
006 Monthly Laboratory Analysis Report: 12 Each ________ _________
Oil and Grease
007 Monthly Laboratory Analysis Report:
Total Organic Carbon 12 Each ________ _________
008 Annual Laboratory Analysis Report:
Lead and Copper 1 Each ________ _________
(CONTINUED)
* "Each" = Each Report
OPTION YEAR 2 (October 1, 2020- September 30, 2021)
009 Weekly Laboratory Analysis Report: 52 Each ________ _________
Report includes the following:
Biological Oxygen Demands
Corrosivity Ph
Total Suspended Solids
010 Monthly Laboratory Analysis Report: 12 Each ________ _________
Oil and Grease
011 Monthly Laboratory Analysis Report:
Total Organic Carbon 12 Each ________ _________
012 Annual Laboratory Analysis Report:
Lead and Copper 1 Each ________ _________
OPTION YEAR 3 (October 1, 2021 - September 30, 2022)
013 Weekly Laboratory Analysis Report: 52 Each ________ _________
Report includes the following:
Biological Oxygen Demands
Corrosivity Ph
Total Suspended Solids
014 Monthly Laboratory Analysis Report: 12 Each ________ _________
Oil and Grease
015 Monthly Laboratory Analysis Report:
Total Organic Carbon 12 Each ________ _________
016 Annual Laboratory Analysis Report:
Lead and Copper 1 Each ________ _________
(CONTINUED)
OPTION YEAR 4 (October 1, 2022 - September 30, 2023)
017 Weekly Laboratory Analysis Report: 52 Each ________ _________
Report includes the following:
Biological Oxygen Demands
Corrosivity pH
Total Suspended Solids
018 Monthly Laboratory Analysis Report: 12 Each ________ _________
Oil and Grease
019 Monthly Laboratory Analysis Report:
Total Organic Carbon 12 Each ________ _________
020 Annual Laboratory Analysis Report:
Lead and Copper 1 Each ________ _________
TOTAL PRICE (Items 001 - 020) _________
Statement of Work For
Waste Water & Finished Water Analyses
1. LOCATION: U.S. Department of Agriculture (USDA), Animal and Plant Health Inspection Service (APHIS), Plant Protection Quarantine (PPQ) Moore Air Base, 22675 N. Moorefield Road, Edinburg Texas 78541
2. PROJECT BACKGROUND: Moore Air Base has its own Potable and a Waste Water Treatment Plants which require water testing analysis. This work is performed for environmental compliance under federal regulations, and enforced by the TCEQ (Texas Commission on Environmental Quality). Samples are collected on a weekly and monthly basis depending on the type of test for analysis. These results are submitted by the Government to TCEQ on a monthly operator report (MOR) required by
TCEQ regulations. Additionally the MORs are maintained at the plant for TCEQ to review at their discretion when they conduct their yearly plant inspections.
3. PROJECT DESCRIPTION: The purpose of this Statement of Work (SOW) is to procure environmental analytical services from an accredited recognized laboratory registered with the National Environmental Laboratory Accreditation Program (NELAP) in accordance with Texas water code 5, subchapter R, Title 30, Texas administrative code chapter 25.
4. TYPE OF CONTRACT: This is a firm‐fixed‐price contract. The payment provided in the contract shall constitute full compensation for furnishing all materials, equipment, and labor, and performing all work in the contract in a complete and acceptable manner.
Payments will be made in accordance with clause 52.212‐4 based on the unit prices established in the Contract Pricing Schedule.
5. PERIOD OF PERFORMANCE: The contract period of performance includes a base period and four (4) option years. See clause 52.217‐9, Option to Extend the Term of the
Contract. Services are estimated to begin January 2019.
6. SPECIFIC REQUIREMENTS/TASKS:
6.1 Sample Analysis. The Contractor shall develop and submit a schedule for water sample collection, delivery, and analysis. The schedule shall be submitted to the Government water plant operator for approval within 14 days after award. The contractor shall pick up of the water samples on a weekly basis from Moore Air Base and deliver to the contractor’s lab for analysis. The contractor shall be responsible for all delivery costs, liability, and maintaining the integrity of samples during delivery. The Contractor shall label and package the samples for transporting to the contractor’s facility. The collection of the water samples will be performed by the Government and picked up by the
Contractor at the water plant building 6402. Sample analysis will be performed by the
Contractor at the contractor’s laboratory facility.
6.1.1 Waste Water Plant:
The services include weekly testing of the effluents at the two waste water evaporation ponds #2 and #3. Waste water samples are tested for biological oxygen demands (BODs), corrosivity pH, total suspended solids (TSS).
6.1.2 Analysis are to be performed monthly for oil and grease in the effluent waste water.
6.1.3 Water Plant:
Samples of the raw and finished water is tested monthly for total organic carbon
(TOC).
6.1.4 A yearly testing of the water distribution is collected and tested at five (5) building locations, bldg. 6407, 6418, 6414, 6402, and 6017 for lead and copper each.
6.2 The proper water collection bottles shall be provided by the Contractor on an as needed basis. The Contractor will be notified before arrival to bring additional supplies of proper bottles. The contractor shall determine the proper bottle sizes and quantities needed for the amount of water needed to perform the necessary tests.
6.3 The Contractor shall provide summary reports of the analyses within 5 to 7 business days following receipt of samples. Reports shall be submitted via e‐mail and followed by a hard copy within two (2) business days. Reports shall comply with NELAP.
Summary analysis reports shall be provided on a weekly basis for the following:
Waste Water Plant:
Biological Oxygen Demand
Corrosivity pH
Total Suspended Solids
Summary analysis reports shall be provided on a monthly basis for the following:
Oil and Grease
Water Plant: Total Organic Carbon
A summary analysis report shall be provided on an annual basis for the following:
Water Plant: Lead and Copper (includes 5 samples)
6.4 The contractor shall provide a “Chain of Custody Form” (CCF) either electronically or hard copy (electronic is preferred). The CCF is typically required with laboratories to assure reliability of reported results bound by legal or regulatory directives by the
Environmental Protection Agency. To meet those legal and regulatory requirements, the water plant Operator is required to keep detailed CFF records of all of the samples which shows a paper trail of the samples transferred from the Government to possession by the Contractor.
7. PROJECT CONTACT PERSONS:
Facilities Manager Gabriel Lopez
USDA, APHIS, PPQ
Moore Air Base 22675 North Moore Field Building 6407 Edinburg, TX 78541 Tel. No.: (956) 205‐7600
Water Plant Operators Jose Cabello & Hector Gomez
USDA, APHIS, PPQ
Moore Air Base 22675 North Moore Field Building 3702 Edinburg, TX 78541 Tel. No.: (956) 205‐7603
8. CONTRACTOR REQUIREMENTS
• Moore Air Base is a restricted facility
• Work Hours are M‐F from 7 am ‐3:30pm. All work outside of the mentioned days and hours shall be approved by the Facilities Manager in writing prior to entering the facility
• All contractors shall have a valid picture identification such as a driver’s license or a state identification card.
• All vehicles shall have proper insurance and registration for all vehicles entering the facility.
9. INVOICES
Invoices shall be submitted on a monthly basis through the Invoice Processing Platform (www.ipp.gov).