TellCity RD Schedule of Items.docx

DOCX document 79 KB Posted

Attached to
Hoosier NF Roads Maintenance and Reconstruction IDIQ
Solicitation number
1252B120R0001
Issued by

View the file

Other files

File Type Posted
Request for Proposals.pdf PDF
brownstown RD schedule of items.docx DOCX document
IDIQ_Road Maint_Hoosier_Tell City_PWS_QAP.docx DOCX document
IDIQ_Road Maint_Hoosier_Brownstown_PWS_QAP.docx DOCX document
Crawford Daviess Dubois Gibson Greene Jackson wage.docx DOCX document
monroe wage.docx DOCX document
DetailA.pdf PDF
Request for Proposals.pdf PDF
perry co wage.docx DOCX document
SpecialProjectSpecification_SPS_021518.doc DOC document
DetailB.pdf PDF
construction wage.docx DOCX document
DetailC.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Forest Service, Hoosier National Forest, Tell City Ranger District IDIQ-Roads and Roadway Maintenance and Reconstruction

SECTION B -SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

TELL CITY RANGER DISTRICT – BASE YEAR

Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0001
Roadway
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0001.a.1
Vegetation and debris removal
Opening up roadway by cutting trees, brush and shrubs within clearing limits and removing stumps, roots, and other obstructions. Material to be disposed of by chipping or piling & burning tops & limbs, piling stumps, and decking logs
2
Acre
$_________
$_________
0001.a.2
Vegetation removal – Roadway mowing
Mowing of road from 1’ outside edge of road to 1’ outside edge of road. On areas with ditch(s) mowing will include 1’ outside edge of road to the bottom of ditch. Vegetation to be mowed to a height of 6” or less. Work normally done with tractor & bush hog.
5
Mile
$_________
$_________
0001.a.3
Vegetation removal – Roadway clearing
Cutting and removing trees, shrubs, and brush from roadway and cut and fill slopes as shown in clearing typical. Larger material to be scattered on downhill side of road. Work normally done with tractor and A-boom mower or by hand.
2
Mile
$_________
$_________
0001.a.4
Vegetation removal – Individual tree
Cut and leave individually marked trees. Work will include cutting branches so all material lays on the ground
25
Each
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0001
Roadway
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0001.b.1
Erosion Control

Mulched Seeding

Place mulch and seed as directed (seed will normally be the Hoosier seed mix)
1.50
Acres
$_________
$_________
0001.b.2
Erosion Control

Silt Fence

Place 36” high silt fence for erosion control as directed
100
Lineal Feet
$_________
$_________
0001.b.3
Erosion Control

Hay Bales

Place staked hay bales for erosion control as directed
50
Lineal Feet
$_________
$_________
0001.c.1
Signs
Repair/Replace traffic control, route marker, and roadside info signs (FS provides sign panel – contractor provides treated or steel post and hardware, etc.)
5
Each Post
$_________
$_________
0001.d.1
Gates – Single rail gate and posts
Supply, install/replace, or repair pipe gates including markers, hardware, gate posts, and signs per HNF-Drawings.
3
Each
$_________
$_________
0001.d.2
Gates – Swing style gate
Supply, install/replace, or repair swing gates including markers, hardware, gate posts, signs, and tie backs per HNF-Drawings.
1
Each
$_________
$_________
0001.e.1
Barriers - Wood
Supply, install 7”-8” round, 6”x6” or 8”x8” treated wood posts. Barriers to be installed as shown on drawings and/or work descriptions. Post to include yellow object markers unless otherwise shown.
15
Each
$_________
$_________
0001.e.2
Barriers - Rock
Supply and place rock barriers in locations shown on Task Order. Unless otherwise designated rock to come from the old Derby Quarry in Perry County
5
Each
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0002
Roadbed
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0002.a.1
Grading
Grading an existing road surfaces, including existing ditches. Work also includes scarification to bottom of potholes when called for in the Task Order. Grading is normally done with a road grader
10
Mile
$_________
$_________
0002.a.2
Grading

(Short Sections)

Following the same description as Grading with the exception of roads are not located near other roads and are less than 1/3 mile in length. Smaller Grader or equivalent may be used for size and location
5
Mile
$_________
$_________
0002.a.3
Grading (Heavy)
Heavy Grading Road Surfaces, including existing ditches. Work also includes scarification to bottom of potholes and filling in eroded roadbed when called for in the Task Order. Grading is normally done with a dozer.
0.5
Mile
$_________
$_________
0002.a.3
Excavation – common material
Excavation of material with little or no rock. Rock can easily be pushed with a dozer.
500
Cubic Yard
$_________
$_________
0002.a.4
Excavation – rippable rock
Excavation of material consisting of large rock and/or fractured rock that can be broken up and moved with a dozer or excavator.
100
Cubic Yard
$_________
$_________
0002.a.5
Excavation – solid rock
Excavation of material where normal excavation equipment cannot break up rock. Rock may need to be jack hammered or drilled and shot.
TBD
Cubic Yard
TBD
TBD
0002.a.6
Borrow/Overhaul
Borrow may consist of excavating, loading, and hauling material from a designated source. Overhaul consists of transporting excavation material from one part of a project to another normally using a scrapper or truck.
TBD
TBD
TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0002
Roadbed
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED
0002.b.1
Aggregate (INDOT #1)
Provide and Place Aggregate meeting INDOT #1 Limestone aggregate specifications
100
Ton
$_________
$_________
0002.b.2
Aggregate (INDOT #2)
Provide and Place Aggregate meeting INDOT #2 Limestone aggregate specifications
100
Ton
$_________
$_________
0002.b.3
Aggregate (INDOT #23)
Provide and Place Aggregate meeting INDOT #23 Limestone aggregate specifications
500
Ton
$_________
$_________
0002.b.4
Aggregate (INDOT #53)
Provide and Place Aggregate meeting INDOT #53 Limestone aggregate specifications
500
Ton
$_________
$_________
0002.b.5
Aggregate (INDOT #73)
Provide and Place Aggregate meeting INDOT #73 Limestone aggregate specifications
100
Ton
$_________
$_________
0002.b.6
Aggregate (INDOT #7)
Provide and Place Aggregate meeting INDOT #7 Limestone aggregate specifications
60
Ton
$_________
$_________
0002.c.1
Riprap (INDOT Class 1)
Provide and Place Riprap, INDOT Class 1 rock as per specifications
20
Ton
$_________
$_________
0002.c.2
Riprap (INDOT Class 2)
Provide and Place Riprap, INDOT Class 2 as per specifications
20
Ton
$_________
$_________
0002.c.3
Riprap (INDOT Revetment)
Provide and Place Riprap, INDOT Revetment as per specifications
50
Ton
$_________
$_________
0002.d.1
Asphalt surface repair
Remove existing asphalt surface, excavate subgrade (average depth 18”), backfill with #2 aggregate and #53 aggregate, and top with 3” depth of #9 asphalt binder per drawings and specifications
TBD
Square Foot

TBD

TBD

0002.e.1
Geotextile
Provide and place 6-8 oz. geotextile material for road stabilization
200
Square Yard
$________
$_________
0002.f.1
Concrete - Repair
Provide, place, and finish concrete to dimensions shown on Task Order.
TBD
Square Foot
TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0003
Drainage
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0003.a.1
Dips - Hardened
Construct hardened drainage dip where directed by FS and as shown on Drawings. Aggregate is included in price of dip construction.
5
Each
$_________
$_________
0003.a.2
Dips – Native Surface
Construct drainage dip where directed by the FS and as shown on Drawings
5
Each
$_________
$_________
0003.a.3
Drainage crossing construction
Construct hardened drainage crossing where directed by the FS and as shown on Drawings. Aggregate is included in price of drainage construction.
5
Each
$_________
$_________
0003.b.1
Culvert (clean)
Clean inside culvert to maintain free flow
2
Each
$________
$__________
0003.c.1
Culvert 18” diameter
Supply, replace/install 18” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
120
Lineal

Foot

$_________
$_________
0003.c.2
Culvert 24” diameter
Supply, replace/install 24” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
40
Lineal

Foot

$_________
$_________
0003.c.3
Culvert 30” diameter
Supply, replace/install 30” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
40
Lineal

Foot

$_________
$_________
0003.c.4
Culvert 36” diameter
Supply, replace/install 36” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
40
Lineal

Foot

$_________
$_________
Item No.
Title
Description
0003
Drainage
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0003.c.5
Culvert 12” diameter
Supply, replace/install 12” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
40
Lineal

Foot

$_________
$_________
0003.c.6
Culvert 15” diameter
Supply, replace/install 15” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
40
Lineal

Foot

$_________
$_________
0003.c.7
Culvert – Other
Supply, replace/install pipe diameter and/or pipe type other than those shown and as stated in the Task Order
TBD
Lineal Foot
TBD
TBD
0003.d.1
Ditches
Construct ditches to widths and depths shown on the drawings and/or designated on the Task Order. Does not include existing ditches.
.50
Mile
$________
$_________
0003.e.1
Trench drain
Construct trench drain to lines and grades shown on drawings and stated in Task Order.
20
Lineal Foot
$________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0004
Equipment, Labor, & Testing
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0004.a.1.a
Motor Grader
Provide Grader fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 138 hp).
8
Hour
$_________
$_________
0004.a.1.b
Motor Grader

(Small)

Provide Grader fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 50 hp).
8
Hour
$_________
$_________
0004.a.2.a
Tracked Excavator
Provide Hydraulic Excavator fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 138 hp).
8
Hour
$_________
$_________
0004.a.2.b
Mini Excavator
Provide Hydraulic Excavator fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 38 hp).
24
Hour
$_________
$_________
0004.a.3
Rubber Tired Backhoe Loader
Provide Rubber Tired Backhoe fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 94 hp).
8
Hour
$_________
$_________
0004.a.4.a
Dump Truck

(Single Axle)

Provide Dump Truck fully operated as approved by FS, for road work not specifi-cally covered under other tasks or items.
8
Hour
$_________
$_________
0004.a.4.b
Dump Truck

(Dual Axle)

Provide Dump Truck fully operated as approved by FS, for road work not specifi-cally covered under other tasks or items.
8
Hour
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0004
Equipment, Labor, & Testing
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0004.a.4.c
Dump Truck

(Tri Axle)

Provide Dump Truck fully operated as approved by FS, for road work not specifi-cally covered under other tasks or items.
8
Hour
$________
$__________
0004.a.5
Dozer
Provide Dozer fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 96 hp).
8
Hour
$_________
$_________
0004.a.6.a
Roller – Vibratory steel drum
Provide steel drum vibratory roller fully operated for road work not specifically covered under other tasks or items. (minimum size Cat CS433 or equal)
8
Hour
$_________
$_________
0004.a.6.b
Roller – Sheep foot
Provide sheep foot roller fully operated for road work not specifically covered under other tasks or items.
8
Hour
$_________
$_________
0004.a.7
Water truck
Provide Water Truck fully operated as approved by FS, for road work not specifically covered under other tasks or items.
8
Hour
$_________
$_________
0004.a.8
Skid steer/Track loader
Provide skid steer with various implements fully operated for road work not specifically covered under other tasks or items. (Minimum 50 hp)
16
Hour
$_________
$_________
0004.a.9
Tractor
Provide tractor with various implements fully operated for road work not specifically covered under other tasks or items. (Minimum 50 hp)
8
Hour
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0004
Equipment, Labor, & Testing
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0004.b.1
Laborer
Provide Laborer(s) for road work not specifically covered under other tasks or items.
24
Hour
$_________
$_________
0004.c.1
Sampling & Testing
Testing of aggregates, soil, concrete, and asphalt on samples taken by soil borings, individual sampling, or other designated means. Doing approximately 6 compaction tests on culvert installation
1
Lump Sum
$________
$__________
0005
Mobilization
PROVIDE ALL LABOR, TRANSPORT VEHICLES, EQUIPMENT CLEANING, SIGNS, BONDING, AND OTHER ESSENTIALS FOR MAINTENANCE AND RECONSTRUCTION OF ROADS.
0005
Mobilization
Mobilization for Items No. 0001 through 0004, as well as Item No.0006.

Contractors shall mobilize from business location to project site. Mobilization is only chargeable once for each task order, no additional fee will be charged for movement between sites. The mobilization is based on 50 mile, with up to 5 pieces of equipment.

1
Lump Sum
$_________
$_________

TOTAL

BASE YEAR

TOTAL PRICE FOR ALL PRICED ITEMS #0001 through #0004 “BASE YEAR”. (All items that are not indicated as “TBD”)

Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0006.a.
Other Equipment
PROVIDE OTHER FULLY OPERATED EQUIPMENT AS FOR ROAD WORK NOT SPECIFICALLY COVERED UNDER OTHER TASKS AND ITEMS OR SHOWN ABOVE IN THIS ITEM. CONTRACTOR TO LIST AND PRICE EACH PIECE OF EQUIPMENT TO BE FURNISHED. USE OF THIS EQUIPMENT TO BE APPROVED BY COR

NOTE: Offeror fill-in as necessary.

If no additional equipment is anticipated enter “N/A” Here: ___________

0006.a.1.a

TBD
Hour
$________
$_________

0006.a.1.b

TBD
Hour
$________
$_________

0006.a.1.c

TBD
Hour
$________
$_________

0006.a.1.d

TBD
Hour
$________
$_________

0006.a.1.e

TBD
Hour
$________
$_________

SECTION B -SUPPLIES OR SERVICES AND PRICES/COSTS

TELL CITY RANGER DISTRICT – OPTION YEAR #1

Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0001
Roadway
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0001.a.1
Vegetation and debris removal
Opening up roadway by cutting trees, brush and shrubs within clearing limits and removing stumps, roots, and other obstructions. Material to be disposed of by chipping or piling & burning tops & limbs, piling stumps, and decking logs
2
Acre
$_________
$_________
0001.a.2
Vegetation removal – Roadway mowing
Mowing of road from 1’ outside edge of road to 1’ outside edge of road. On areas with ditch(s) mowing will include 1’ outside edge of road to the bottom of ditch. Vegetation to be mowed to a height of 6” or less. Work normally done with tractor & bush hog.
5
Mile
$_________
$_________
0001.a.3
Vegetation removal – Roadway clearing
Cutting and removing trees, shrubs, and brush from roadway and cut and fill slopes as shown in clearing typical. Larger material to be scattered on downhill side of road. Work normally done with tractor and A-boom mower or by hand.
2
Mile
$_________
$_________
0001.a.4
Vegetation removal – Individual tree
Cut and leave individually marked trees. Work will include cutting branches so all material lays on the ground
25
Each
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0001
Roadway
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0001.b.1
Erosion Control

Mulched Seeding

Place mulch and seed as directed (seed will normally be the Hoosier seed mix)
1.50
Acres
$_________
$_________
0001.b.2
Erosion Control

Silt Fence

Place 36” high silt fence for erosion control as directed
100
Lineal Feet
$_________
$_________
0001.b.3
Erosion Control

Hay Bales

Place staked hay bales for erosion control as directed
50
Lineal Feet
$_________
$_________
0001.c.1
Signs
Repair/Replace traffic control, route marker, and roadside info signs (FS provides sign panel – contractor provides treated or steel post and hardware, etc.)
5
Each Post
$_________
$_________
0001.d.1
Gates – Single rail gate and posts
Supply, install/replace, or repair pipe gates including markers, hardware, gate posts, and signs per HNF-Drawings.
3
Each
$_________
$_________
0001.d.2
Gates – Swing style gate
Supply, install/replace, or repair swing gates including markers, hardware, gate posts, signs, and tie backs per HNF-Drawings.
1
Each
$_________
$_________
0001.e.1
Barriers - Wood
Supply, install 7”-8” round, 6”x6” or 8”x8” treated wood posts. Barriers to be installed as shown on drawings and/or work descriptions. Post to include yellow object markers unless otherwise shown.
15
Each
$_________
$_________
0001.e.2
Barriers - Rock
Supply and place rock barriers in locations shown on Task Order. Unless otherwise designated rock to come from the old Derby Quarry in Perry County
5
Each
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0002
Roadbed
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0002.a.1
Grading
Grading an existing road surfaces, including existing ditches. Work also includes scarification to bottom of potholes when called for in the Task Order. Grading is normally done with a road grader
10
Mile
$_________
$_________
0002.a.2
Grading

(Short Sections)

Following the same description as Grading with the exception of roads are not located near other roads and are less than 1/3 mile in length. Smaller Grader or equivalent may be used for size and location
5
Mile
$_________
$_________
0002.a.3
Grading (Heavy)
Heavy Grading Road Surfaces, including existing ditches. Work also includes scarification to bottom of potholes and filling in eroded roadbed when called for in the Task Order. Grading is normally done with a dozer.
0.5
Mile
$_________
$_________
0002.a.3
Excavation – common material
Excavation of material with little or no rock. Rock can easily be pushed with a dozer.
500
Cubic Yard
$_________
$_________
0002.a.4
Excavation – rippable rock
Excavation of material consisting of large rock and/or fractured rock that can be broken up and moved with a dozer or excavator.
100
Cubic Yard
$_________
$_________
0002.a.5
Excavation – solid rock
Excavation of material where normal excavation equipment cannot break up rock. Rock may need to be jack hammered or drilled and shot.
TBD
Cubic Yard
TBD
TBD
0002.a.6
Borrow/Overhaul
Borrow may consist of excavating, loading, and hauling material from a designated source. Overhaul consists of transporting excavation material from one part of a project to another normally using a scrapper or truck.
TBD
TBD
TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0002
Roadbed
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED
0002.b.1
Aggregate (INDOT #1)
Provide and Place Aggregate meeting INDOT #1 Limestone aggregate specifications
100
Ton
$_________
$_________
0002.b.2
Aggregate (INDOT #2)
Provide and Place Aggregate meeting INDOT #2 Limestone aggregate specifications
100
Ton
$_________
$_________
0002.b.3
Aggregate (INDOT #23)
Provide and Place Aggregate meeting INDOT #23 Limestone aggregate specifications
300
Ton
$_________
$_________
0002.b.4
Aggregate (INDOT #53)
Provide and Place Aggregate meeting INDOT #53 Limestone aggregate specifications
500
Ton
$_________
$_________
0002.b.5
Aggregate (INDOT #73)
Provide and Place Aggregate meeting INDOT #73 Limestone aggregate specifications
100
Ton
$_________
$_________
0002.b.6
Aggregate (INDOT #7)
Provide and Place Aggregate meeting INDOT #7 Limestone aggregate specifications
60
Ton
$_________
$_________
0002.c.1
Riprap (INDOT Class 1)
Provide and Place Riprap, INDOT Class 1 rock as per specifications
20
Ton
$_________
$_________
0002.c.2
Riprap (INDOT Class 2)
Provide and Place Riprap, INDOT Class 2 as per specifications
20
Ton
$_________
$_________
0002.c.3
Riprap (INDOT Revetment)
Provide and Place Riprap, INDOT Revetment as per specifications
50
Ton
$_________
$_________
0002.d.1
Asphalt surface repair
Remove existing asphalt surface, excavate subgrade (average depth 18”), backfill with #2 aggregate and #53 aggregate, and top with 3” depth of #9 asphalt binder per drawings and specifications
TBD
Square Foot

TBD

TBD

0002.e.1
Geotextile
Provide and place 6-8 oz. geotextile material for road stabilization
200
Square Yard
$_________
$_________
0002.f.1
Concrete - Repair
Provide, place, and finish concrete to dimensions shown on Task Order.
TBD
Square Foot
TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0003
Drainage
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0003.a.1
Dips - Hardened
Construct hardened drainage dip where directed by FS and as shown on Drawings. Aggregate is included in price of dip construction.
4
Each
$_________
$_________
0003.a.2
Dips – Native Surface
Construct drainage dip where directed by the FS and as shown on Drawings
4
Each
$_________
$_________
0003.a.3
Drainage crossing construction
Construct hardened drainage crossing where directed by the FS and as shown on Drawings. Aggregate is included in price of drainage construction.
2
Each
$_________
$_________
0003.b.1
Culvert (clean)
Clean inside culvert to maintain free flow
2
Each
$________
$__________
0003.c.1
Culvert 18” diameter
Supply, replace/install 18” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
120
Lineal

Foot

$_________
$_________
0003.c.2
Culvert 24” diameter
Supply, replace/install 24” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
40
Lineal

Foot

$_________
$_________
0003.c.3
Culvert 30” diameter
Supply, replace/install 30” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
40
Lineal

Foot

$_________
$_________
0003.c.4
Culvert 36” diameter
Supply, replace/install 36” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
40
Lineal

Foot

$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0003
Drainage
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0003.c.5
Culvert 12” diameter
Supply, replace/install 12” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
40
Lineal

Foot

$_________
$_________
0003.c.6
Culvert 15” diameter
Supply, replace/install 15” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
40
Lineal

Foot

$_________
$_________
0003.c.7
Culvert – Other
Supply, replace/install pipe diameter and/or pipe type other than those shown and as stated in the Task Order
TBD
Lineal Foot
TBD
TBD
0003.d.1
Ditches
Construct ditches to widths and depths shown on the drawings and/or designated on the Task Order. Does not include existing ditches.
.50
Mile
$_________
$_________
0003.e.1
Trench drain
Construct trench drain to lines and grades shown on drawings and stated in Task Order.
20
Lineal Foot
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0004
Equipment, Labor, & Testing
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0004.a.1.a
Motor Grader
Provide Grader fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 138 hp).
8
Hour
$_________
$_________
0004.a.1.b
Motor Grader

(Small)

Provide Grader fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 50 hp).
8
Hour
$_________
$_________
0004.a.2.a
Tracked Excavator
Provide Hydraulic Excavator fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 138 hp).
8
Hour
$_________
$_________
0004.a.2.b
Mini Excavator
Provide Hydraulic Excavator fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 38 hp).
24
Hour
$_________
$_________
0004.a.3
Rubber Tired Backhoe Loader
Provide Rubber Tired Backhoe fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 94 hp).
8
Hour
$_________
$_________
0004.a.4.a
Dump Truck

(Single Axle)

Provide Dump Truck fully operated as approved by FS, for road work not specifi-cally covered under other tasks or items.
8
Hour
$_________
$_________
0004.a.4.b
Dump Truck

(Dual Axle)

Provide Dump Truck fully operated as approved by FS, for road work not specifi-cally covered under other tasks or items.
8
Hour
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0004
Equipment, Labor, & Testing
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0004.a.4.c
Dump Truck

(Tri Axle)

Provide Dump Truck fully operated as approved by FS, for road work not specifi-cally covered under other tasks or items.
8
Hour
$________
$__________
0004.a.5
Dozer
Provide Dozer fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 96 hp).
8
Hour
$_________
$_________
0004.a.6.a
Roller – Vibratory steel drum
Provide steel drum vibratory roller fully operated for road work not specifically covered under other tasks or items. (minimum size Cat CS433 or equal)
8
Hour
$_________
$_________
0004.a.6.b
Roller – Sheep foot
Provide sheep foot roller fully operated for road work not specifically covered under other tasks or items.
8
Hour
$_________
$_________
0004.a.7
Water truck
Provide Water Truck fully operated as approved by FS, for road work not specifically covered under other tasks or items.
8
Hour
$_________
$_________
0004.a.8
Skid steer/Track loader
Provide skid steer with various implements fully operated for road work not specifically covered under other tasks or items. (Minimum 50 hp)
16
Hour
$_________
$_________
0004.a.9
Tractor
Provide tractor with various implements fully operated for road work not specifically covered under other tasks or items. (Minimum 50 hp)
8
Hour
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0004
Equipment, Labor, & Testing
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0004.b.1
Laborer
Provide Laborer(s) for road work not specifically covered under other tasks or items.
24
Hour
$_________
$_________
0004.c.1
Sampling & Testing
Testing of aggregates, soil, concrete, and asphalt on samples taken by soil borings, individual sampling, or other designated means. Doing approximately 6 compaction tests on culvert installation
1
Lump Sum
$________
$__________
0005
Mobilization
PROVIDE ALL LABOR, TRANSPORT VEHICLES, EQUIPMENT CLEANING, SIGNS, BONDING, AND OTHER ESSENTIALS FOR MAINTENANCE AND RECONSTRUCTION OF ROADS.
0005
Mobilization
Mobilization for Items No. 0001 through 0004, as well as Item No.0006.

Contractors shall mobilize from business location to project site. Mobilization is only chargeable once for each task order, no additional fee will be charged for movement between sites. The mobilization is based on 50 mile, with up to 5 pieces of equipment.

1
Lump Sum
$_________
$_________

TOTAL OPTION YEAR #1

TOTAL PRICE FOR ALL PRICED ITEMS #0001 through #0004 “OPTION YEAR 1”. (All items that are not indicated as “TBD”)

Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0006.a.
Other Equipment
PROVIDE OTHER FULLY OPERATED EQUIPMENT AS FOR ROAD WORK NOT SPECIFICALLY COVERED UNDER OTHER TASKS AND ITEMS OR SHOWN ABOVE IN THIS ITEM. CONTRACTOR TO LIST AND PRICE EACH PIECE OF EQUIPMENT TO BE FURNISHED. USE OF THIS EQUIPMENT TO BE APPROVED BY COR
TBD
Hour
$________
$_________
TBD
Hour
$________
$_________
TBD
Hour
$________
$_________
TBD
Hour
$________
$_________

0006.a.1.e

TBD
Hour
$________
$_________

TELL CITY RANGER DISTRICT – OPTION YEAR #2

Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0001
Roadway
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0001.a.1
Vegetation and debris removal
Opening up roadway by cutting trees, brush and shrubs within clearing limits and removing stumps, roots, and other obstructions. Material to be disposed of by chipping or piling & burning tops & limbs, piling stumps, and decking logs
1
Acre
$_________
$_________
0001.a.2
Vegetation removal – Roadway mowing
Mowing of road from 1’ outside edge of road to 1’ outside edge of road. On areas with ditch(s) mowing will include 1’ outside edge of road to the bottom of ditch. Vegetation to be mowed to a height of 6” or less. Work normally done with tractor & bush hog.
5
Mile
$_________
$_________
0001.a.3
Vegetation removal – Roadway clearing
Cutting and removing trees, shrubs, and brush from roadway and cut and fill slopes as shown in clearing typical. Larger material to be scattered on downhill side of road. Work normally done with tractor and A-boom mower or by hand.
2
Mile
$_________
$_________
0001.a.4
Vegetation removal – Individual tree
Cut and leave individually marked trees. Work will include cutting branches so all material lays on the ground
25
Each
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0001
Roadway
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0001.b.1
Erosion Control

Mulched Seeding

Place mulch and seed as directed (seed will normally be the Hoosier seed mix)
1.50
Acres
$_________
$_________
0001.b.2
Erosion Control

Silt Fence

Place 36” high silt fence for erosion control as directed
100
Lineal Feet
$_________
$_________
0001.b.3
Erosion Control

Hay Bales

Place staked hay bales for erosion control as directed
50
Lineal Feet
$_________
$_________
0001.c.1
Signs
Repair/Replace traffic control, route marker, and roadside info signs (FS provides sign panel – contractor provides treated or steel post and hardware, etc.)
5
Each Post
$_________
$_________
0001.d.1
Gates – Single rail gate and posts
Supply, install/replace, or repair pipe gates including markers, hardware, gate posts, and signs per HNF-Drawings.
3
Each
$_________
$_________
0001.d.2
Gates – Swing style gate
Supply, install/replace, or repair swing gates including markers, hardware, gate posts, signs, and tie backs per HNF-Drawings.
1
Each
$_________
$_________
0001.e.1
Barriers - Wood
Supply, install 7”-8” round, 6”x6” or 8”x8” treated wood posts. Barriers to be installed as shown on drawings and/or work descriptions. Post to include yellow object markers unless otherwise shown.
15
Each
$_________
$_________
0001.e.2
Barriers - Rock
Supply and place rock barriers in locations shown on Task Order. Unless otherwise designated rock to come from the old Derby Quarry in Perry County
5
Each
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0002
Roadbed
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0002.a.1
Grading
Grading an existing road surfaces, including existing ditches. Work also includes scarification to bottom of potholes when called for in the Task Order. Grading is normally done with a road grader
10
Mile
$_________
$_________
0002.a.2
Grading

(Short Sections)

Following the same description as Grading with the exception of roads are not located near other roads and are less than 1/3 mile in length. Smaller Grader or equivalent may be used for size and location
5
Mile
$_________
$_________
0002.a.3
Grading (Heavy)
Heavy Grading Road Surfaces, including existing ditches. Work also includes scarification to bottom of potholes and filling in eroded roadbed when called for in the Task Order. Grading is normally done with a dozer.
0.5
Mile
$_________
$_________
0002.a.3
Excavation – common material
Excavation of material with little or no rock. Rock can easily be pushed with a dozer.
500
Cubic Yard
$_________
$_________
0002.a.4
Excavation – rippable rock
Excavation of material consisting of large rock and/or fractured rock that can be broken up and moved with a dozer or excavator.
100
Cubic Yard
$_________
$_________
0002.a.5
Excavation – solid rock
Excavation of material where normal excavation equipment cannot break up rock. Rock may need to be jack hammered or drilled and shot.
TBD
Cubic Yard
TBD
TBD
0002.a.6
Borrow/Overhaul
Borrow may consist of excavating, loading, and hauling material from a designated source. Overhaul consists of transporting excavation material from one part of a project to another normally using a scrapper or truck.
TBD
TBD
TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0002
Roadbed
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED
0002.b.1
Aggregate (INDOT #1)
Provide and Place Aggregate meeting INDOT #1 Limestone aggregate specifications
TBD
Ton
TBD
TBD
0002.b.2
Aggregate (INDOT #2)
Provide and Place Aggregate meeting INDOT #2 Limestone aggregate specifications
TBD
Ton
TBD
TBD
0002.b.3
Aggregate (INDOT #23)
Provide and Place Aggregate meeting INDOT #23 Limestone aggregate specifications
300
Ton
$_________
$_________
0002.b.4
Aggregate (INDOT #53)
Provide and Place Aggregate meeting INDOT #53 Limestone aggregate specifications
500
Ton
$_________
$_________
0002.b.5
Aggregate (INDOT #73)
Provide and Place Aggregate meeting INDOT #73 Limestone aggregate specifications
TBD
Ton
TBD
TBD
0002.b.6
Aggregate (INDOT #7)
Provide and Place Aggregate meeting INDOT #7 Limestone aggregate specifications
TBD
Ton
TBD
TBD
0002.c.1
Riprap (INDOT Class 1)
Provide and Place Riprap, INDOT Class 1 rock as per specifications
TBD
Ton
TBD
TBD
0002.c.2
Riprap (INDOT Class 2)
Provide and Place Riprap, INDOT Class 2 as per specifications
TBD
Ton
TBD
TBD
0002.c.3
Riprap (INDOT Revetment)
Provide and Place Riprap, INDOT Revetment as per specifications
TBD
Ton
TBD
TBD
0002.d.1
Asphalt surface repair
Remove existing asphalt surface, excavate subgrade (average depth 18”), backfill with #2 aggregate and #53 aggregate, and top with 3” depth of #9 asphalt binder per drawings and specifications
TBD
Square Foot

TBD

TBD

0002.e.1
Geotextile
Provide and place 6-8 oz. geotextile material for road stabilization
200
Square Yard
$_________
$_________
0002.f.1
Concrete – Repair
Provide, place, and finish concrete to dimensions shown on Task Order.
TBD
Square Foot
TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0003
Drainage
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED
0003.a.1
Dips - Hardened
Construct hardened drainage dip where directed by FS and as shown on Drawings. Aggregate is included in price of dip construction.
TBD
Each
TBD
TBD
0003.a.2
Dips – Native Surface
Construct drainage dip where directed by the FS and as shown on Drawings
2
Each
$_________
$_________
0003.a.3
Drainage crossing construction
Construct hardened drainage crossing where directed by the FS and as shown on Drawings. Aggregate is included in price of drainage construction.
TBD
Each
TBD
TBD
0003.b.1
Culvert (clean)
Clean inside culvert to maintain free flow
2
Each
$________
$__________
0003.c.1
Culvert 18” diameter
Supply, replace/install 18” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
100
Lineal

Foot

$_________
$_________
0003.c.2
Culvert 24” diameter
Supply, replace/install 24” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
40
Lineal

Foot

$_________
$_________
0003.c.3
Culvert 30” diameter
Supply, replace/install 30” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
TBD
Lineal

Foot

TBD
TBD
0003.c.4
Culvert 36” diameter
Supply, replace/install 36” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
TBD
Lineal

Foot

TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0003
Drainage
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0003.c.5
Culvert 12” diameter
Supply, replace/install 12” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
TBD
Lineal

Foot

TBD
TBD
0003.c.6
Culvert 15” diameter
Supply, replace/install 15” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
TBD
Lineal

Foot

TBD
TBD
0003.c.7
Culvert – Other
Supply, replace/install pipe diameter and/or pipe type other than those shown and as stated in the Task Order
TBD
Lineal Foot
TBD
TBD
0003.d.1
Ditches
Construct ditches to widths and depths shown on the drawings and/or designated on the Task Order. Does not include existing ditches.
.50
Mile
$_________
$_________
0003.e.1
Trench drain
Construct trench drain to lines and grades shown on drawings and stated in Task Order.
TBD
Lineal Foot
TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0004
Equipment, Labor, & Testing
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0004.a.1.a
Motor Grader
Provide Grader fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 138 hp).
8
Hour
$_________
$_________
0004.a.1.b
Motor Grader

(Small)

Provide Grader fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 50 hp).
8
Hour
$_________
$_________
0004.a.2.a
Tracked Excavator
Provide Hydraulic Excavator fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 138 hp).
8
Hour
$_________
$_________
0004.a.2.b
Mini Excavator
Provide Hydraulic Excavator fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 38 hp).
16
Hour
$_________
$_________
0004.a.3
Rubber Tired Backhoe Loader
Provide Rubber Tired Backhoe fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 94 hp).
8
Hour
$_________
$_________
0004.a.4.a
Dump Truck

(Single Axle)

Provide Dump Truck fully operated as approved by FS, for road work not specifi-cally covered under other tasks or items.
8
Hour
$_________
$_________
0004.a.4.b
Dump Truck

(Dual Axle)

Provide Dump Truck fully operated as approved by FS, for road work not specifi-cally covered under other tasks or items.
8
Hour
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0004
Equipment, Labor, & Testing
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0004.a.4.c
Dump Truck

(Tri Axle)

Provide Dump Truck fully operated as approved by FS, for road work not specifi-cally covered under other tasks or items.
8
Hour
$________
$__________
0004.a.5
Dozer
Provide Dozer fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 96 hp).
8
Hour
$_________
$_________
0004.a.6.a
Roller – Vibratory steel drum
Provide steel drum vibratory roller fully operated for road work not specifically covered under other tasks or items. (minimum size Cat CS433 or equal)
8
Hour
$_________
$_________
0004.a.6.b
Roller – Sheep foot
Provide sheep foot roller fully operated for road work not specifically covered under other tasks or items.
8
Hour
$_________
$_________
0004.a.7
Water truck
Provide Water Truck fully operated as approved by FS, for road work not specifically covered under other tasks or items.
8
Hour
$_________
$_________
0004.a.8
Skid steer/Track loader
Provide skid steer with various implements fully operated for road work not specifically covered under other tasks or items. (Minimum 50 hp)
8
Hour
$_________
$_________
0004.a.9
Tractor
Provide tractor with various implements fully operated for road work not specifically covered under other tasks or items. (Minimum 50 hp)
8
Hour
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0004
Equipment, Labor, & Testing
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0004.b.1
Laborer
Provide Laborer(s) for road work not specifically covered under other tasks or items.
16
Hour
$_________
$_________
0004.c.1
Sampling & Testing
Testing of aggregates, soil, concrete, and asphalt on samples taken by soil borings, individual sampling, or other designated means. Doing approximately 6 compaction tests on culvert installation
1
Lump Sum
$________
$__________
0005
Mobilization
PROVIDE ALL LABOR, TRANSPORT VEHICLES, EQUIPMENT CLEANING, SIGNS, BONDING, AND OTHER ESSENTIALS FOR MAINTENANCE AND RECONSTRUCTION OF ROADS.
0005
Mobilization
Mobilization for Items No. 0001 through 0004, as well as Item No.0006.

Contractors shall mobilize from business location to project site. Mobilization is only chargeable once for each task order, no additional fee will be charged for movement between sites. The mobilization is based on 50 mile, with up to 5 pieces of equipment.

1
Lump Sum
$_________
$_________

TOTAL

OPTION YEAR #2

TOTAL PRICE FOR ALL PRICED ITEMS #0001 through #0004 “OPTION YEAR #2”. (All items that are not indicated as “TBD”)

Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0006.a.
Other Equipment
PROVIDE OTHER FULLY OPERATED EQUIPMENT AS FOR ROAD WORK NOT SPECIFICALLY COVERED UNDER OTHER TASKS AND ITEMS OR SHOWN ABOVE IN THIS ITEM. CONTRACTOR TO LIST AND PRICE EACH PIECE OF EQUIPMENT TO BE FURNISHED. USE OF THIS EQUIPMENT TO BE APPROVED BY COR
TBD
Hour
$________
$_________
TBD
Hour
$________
$_________
TBD
Hour
$________
$_________
TBD
Hour
$________
$_________

TELL CITY RANGER DISTRICT – OPTION YEAR #3

Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0001
Roadway
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0001.a.1
Vegetation and debris removal
Opening up roadway by cutting trees, brush and shrubs within clearing limits and removing stumps, roots, and other obstructions. Material to be disposed of by chipping or piling & burning tops & limbs, piling stumps, and decking logs
TBD
Acre
TBD
TBD
0001.a.2
Vegetation removal – Roadway mowing
Mowing of road from 1’ outside edge of road to 1’ outside edge of road. On areas with ditch(s) mowing will include 1’ outside edge of road to the bottom of ditch. Vegetation to be mowed to a height of 6” or less. Work normally done with tractor & bush hog.
5
Mile
$_________
$_________
0001.a.3
Vegetation removal – Roadway clearing
Cutting and removing trees, shrubs, and brush from roadway and cut and fill slopes as shown in clearing typical. Larger material to be scattered on downhill side of road. Work normally done with tractor and A-boom mower or by hand.
2
Mile
$_________
$_________
0001.a.4
Vegetation removal – Individual tree
Cut and leave individually marked trees. Work will include cutting branches so all material lays on the ground
25
Each
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0001
Roadway
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0001.b.1
Erosion Control

Mulched Seeding

Place mulch and seed as directed (seed will normally be the Hoosier seed mix)
1.50
Acres
$_________
$_________
0001.b.2
Erosion Control

Silt Fence

Place 36” high silt fence for erosion control as directed
100
Lineal Feet
$_________
$_________
0001.b.3
Erosion Control

Hay Bales

Place staked hay bales for erosion control as directed
50
Lineal Feet
$_________
$_________
0001.c.1
Signs
Repair/Replace traffic control, route marker, and roadside info signs (FS provides sign panel – contractor provides treated or steel post and hardware, etc.)
5
Each Post
$_________
$_________
0001.d.1
Gates – Single rail gate and posts
Supply, install/replace, or repair pipe gates including markers, hardware, gate posts, and signs per HNF-Drawings.
3
Each
$_________
$_________
0001.d.2
Gates – Swing style gate
Supply, install/replace, or repair swing gates including markers, hardware, gate posts, signs, and tie backs per HNF-Drawings.
1
Each
$_________
$_________
0001.e.1
Barriers - Wood
Supply, install 7”-8” round, 6”x6” or 8”x8” treated wood posts. Barriers to be installed as shown on drawings and/or work descriptions. Post to include yellow object markers unless otherwise shown.
15
Each
$_________
$_________
0001.e.2
Barriers - Rock
Supply and place rock barriers in locations shown on Task Order. Unless otherwise designated rock to come from the old Derby Quarry in Perry County
5
Each
$_________
$_________
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0002
Roadbed
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED.
0002.a.1
Grading
Grading an existing road surfaces, including existing ditches. Work also includes scarification to bottom of potholes when called for in the Task Order. Grading is normally done with a road grader
10
Mile
$_________
$_________
0002.a.2
Grading

(Short Sections)

Following the same description as Grading with the exception of roads are not located near other roads and are less than 1/3 mile in length. Smaller Grader or equivalent may be used for size and location
5
Mile
$_________
$_________
0002.a.3
Grading (Heavy)
Heavy Grading Road Surfaces, including existing ditches. Work also includes scarification to bottom of potholes and filling in eroded roadbed when called for in the Task Order. Grading is normally done with a dozer.
0.5
Mile
$_________
$_________
0002.a.3
Excavation – common material
Excavation of material with little or no rock. Rock can easily be pushed with a dozer.
500
Cubic Yard
$_________
$_________
0002.a.4
Excavation – rippable rock
Excavation of material consisting of large rock and/or fractured rock that can be broken up and moved with a dozer or excavator.
100
Cubic Yard
$_________
$_________
0002.a.5
Excavation – solid rock
Excavation of material where normal excavation equipment cannot break up rock. Rock may need to be jack hammered or drilled and shot.
TBD
Cubic Yard
TBD
TBD
0002.a.6
Borrow/Overhaul
Borrow may consist of excavating, loading, and hauling material from a designated source. Overhaul consists of transporting excavation material from one part of a project to another normally using a scrapper or truck.
TBD
TBD
TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0002
Roadbed
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED
0002.b.1
Aggregate (INDOT #1)
Provide and Place Aggregate meeting INDOT #1 Limestone aggregate specifications
TBD
Ton
TBD
TBD
0002.b.2
Aggregate (INDOT #2)
Provide and Place Aggregate meeting INDOT #2 Limestone aggregate specifications
TBD
Ton
TBD
TBD
0002.b.3
Aggregate (INDOT #23)
Provide and Place Aggregate meeting INDOT #23 Limestone aggregate specifications
300
Ton
$_________
$_________
0002.b.4
Aggregate (INDOT #53)
Provide and Place Aggregate meeting INDOT #53 Limestone aggregate specifications
500
Ton
$_________
$_________
0002.b.5
Aggregate (INDOT #73)
Provide and Place Aggregate meeting INDOT #73 Limestone aggregate specifications
TBD
Ton
TBD
TBD
0002.b.6
Aggregate (INDOT #7)
Provide and Place Aggregate meeting INDOT #7 Limestone aggregate specifications
TBD
Ton
TBD
TBD
0002.c.1
Riprap (INDOT Class 1)
Provide and Place Riprap, INDOT Class 1 rock as per specifications
TBD
Ton
TBD
TBD
0002.c.2
Riprap (INDOT Class 2)
Provide and Place Riprap, INDOT Class 2 as per specifications
TBD
Ton
TBD
TBD
0002.c.3
Riprap (INDOT Revetment)
Provide and Place Riprap, INDOT Revetment as per specifications
TBD
Ton
TBD
TBD
0002.d.1
Asphalt surface repair
Remove existing asphalt surface, excavate subgrade (average depth 18”), backfill with #2 aggregate and #53 aggregate, and top with 3” depth of #9 asphalt binder per drawings and specifications
TBD
Square Foot

TBD

TBD

0002.e.1
Geotextile
Provide and place 6-8 oz. geotextile material for road stabilization
200
Square Yard
$_________
$_________
0002.f.1
Concrete - Repair
Provide, place, and finish concrete to dimensions shown on Task Order.
TBD
Square Foot
TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0003
Drainage
PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS FOR ROAD WORK AS DIRECTED
0003.a.1
Dips - Hardened
Construct hardened drainage dip where directed by FS and as shown on Drawings. Aggregate is included in price of dip construction.
TBD
Each
TBD
TBD
0003.a.2
Dips – Native Surface
Construct drainage dip where directed by the FS and as shown on Drawings
2
Each
$_________
$_________
0003.a.3
Drainage crossing construction
Construct hardened drainage crossing where directed by the FS and as shown on Drawings. Aggregate is included in price of drainage construction.
TBD
Each
TBD
TBD
0003.b.1
Culvert (clean)
Clean inside culvert to maintain free flow
2
Each
$________
$__________
0003.c.1
Culvert 18” diameter
Supply, replace/install 18” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
120
Lineal

Foot

$_________
$_________
0003.c.2
Culvert 24” diameter
Supply, replace/install 24” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
40
Lineal

Foot

$_________
$_________
0003.c.3
Culvert 30” diameter
Supply, replace/install 30” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
TBD
Lineal

Foot

TBD
TBD
0003.c.4
Culvert 36” diameter
Supply, replace/install 36” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in the Task Order.
TBD
Lineal

Foot

TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0003
Drainage
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0003.c.5
Culvert 12” diameter
Supply, replace/install 12” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
TBD
Lineal

Foot

TBD
TBD
0003.c.6
Culvert 15” diameter
Supply, replace/install 15” diameter corrugated polyethylene smooth wall pipe (N-12) where directed by FS and as stated in Task Order.
TBD
Lineal

Foot

TBD
TBD
0003.c.7
Culvert – Other
Supply, replace/install pipe diameter and/or pipe type other than those shown and as stated in the Task Order
TBD
Lineal Foot
TBD
TBD
0003.d.1
Ditches
Construct ditches to widths and depths shown on the drawings and/or designated on the Task Order. Does not include existing ditches.
.50
Mile
$_________
$_________
0003.e.1
Trench drain
Construct trench drain to lines and grades shown on drawings and stated in Task Order.
TBD
Lineal Foot
TBD
TBD
Item No.
Title
Description
Estimated

Annual Quantity

Unit
Unit

Price Total Price

0004
Equipment, Labor, & Testing
PROVIDE ALL LABOR AND EQUIPMENT FOR ROAD WORK AS DIRECTED.
0004.a.1.a
Motor Grader
Provide Grader fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 138 hp).
8
Hour
$_________
$_________
0004.a.1.b
Motor Grader

(Small)

Provide Grader fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 50 hp).
8
Hour
$_________
$_________
0004.a.2.a
Tracked Excavator
Provide Hydraulic Excavator fully operated as approved by FS, for road work not specifically covered under other tasks or items. (Minimum 138 hp).
8
Hour
$_________
$_________
0004.a.2.b
Mini Excavator

This is the start of the file's text. The full file is on GovTribe.