Vendor Questions.pdf
PDF 69 KB Posted
- Attached to
- Soybean Oil
- Solicitation number
- 124PSA27Q0006
About this file
This is a Vendor Questions and Answers document for a federal contract opportunity issued by the U.S. Department of Agriculture (USDA). The solicitation requires 12 tons of crude degummed soybean oil with a minimum of 99% fat content, to be delivered via bulk tanker to Clay Center, Nebraska. The requirement specifies U.S.-made oil, and vendors must clarify that the reference to soybean hulls in the original specification was a clerical error. Delivery must occur approximately 30 days after award. The contractor's trailer must be equipped to unload the product from the tanker, with hose and connection requirements to be confirmed with the government point of contact prior to delivery. One 12-ton load is acceptable.
Vendors must submit quotations electronically via email to david.tibbs@usda.gov in PDF, Word, or Excel format, and must include a Product Specification sheet and Certificate of Analysis with their quote to confirm acceptability. Payment terms are Net 30, with invoices submitted electronically through the Invoice Processing Platform (IPP) after vendor enrollment at https://www.ipp.gov/vendors/enrollment. All payments will be made by electronic funds transfer (EFT) in accordance with the Debt Collection Improvement Act of 1996. The solicitation clarifies that FAR 52.219-14 and 52.219-33 are not applicable, and the below-threshold exception does not apply, requiring that oil must be U.S.-made regardless of the vendor's business size classification.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Vendor Questions
Question #1 We understand the requirement to be 12 tons of crude degummed soybean oil with a minimum of 99% fat delivered to Clay Center, Nebraska. Could you please clarify whether delivery is bulk tanker or packaged?
Response: Bulk Tanker
Question #2 Could you please clarify whether TN means U.S. short tons (12 TN equals 24,000 lbs.)?
Response: TN means US tons. 12 TN equals 24,000 lbs.
Question #3 Could you please clarify whether the specification's reference to soybean hulls is a clerical error?
Response: Yes, this is a clerical error. Apologies. This need is for Soybean Oil.
Question #4 Could you please clarify whether we should price tanker delivery within 30 days of award as Attachment 1 states, with the exact date coordinated at award as the solicitation says?
Please price tanker delivery within 30 days of award.
Response: Delivery in the range of approximately 30 days after the award.
Question #5 Please confirm whether one 12-ton load is acceptable and whether any unloading connection, pump, hose or delivery equipment requirements exist?
Response: Contractor’s trailer must be equipped to unload the product from the tanker.
Awardee to confirm hose and connection requirements with Gov’t POC prior to delivery.
Question #6 Please confirm the quotation submission email/method?
Response: Please submit electronically via email to david.tibbs@usda.gov; acceptable formats for attachments are PDF, Word, or Excel.
Question #7 Could you please clarify whether a product specification sheet or certificate of analysis is required with the quote or at delivery?
Response: Product Specification and Certificate of Analysis should be submitted with the quote to confirm that your quote is acceptable.
Question #8 FAR 52.219-14 and 52.219-33 are not checked. Please confirm whether the below-threshold exception applies, allowing an otherwise eligible small-business reseller to quote U.S.-made oil from a large processor.
Response: Correct, FAR 52.219-14 and 52.219-33 are not applicable. Oil must be U.S.
made.
Question #9 The notice lists AGAR 452.232-72 as Electronic Submission of Payment Requests. Please confirm the correct invoice clause, invoice system and payment timing.
Response: Payment Net 30. The following with be added to the solicitation terms and conditions:
“Invoices: To invoice, a vendor must first enroll in the Invoice Processing Platform (IPP) by visiting https://www.ipp.gov/vendors/enrollment. Once enrolled, all invoices must be submitted electronically through IPP. The IPP is a government-wide secure web-based payment information service oƯered free of charge to government agencies and their suppliers by the U.S. Department of Treasury’s Financial Management Service (FMS).
EƯective May 6, 2013, payment requests must be submitted electronically through the U.S.
Department of the Treasury’s Invoice Processing Platform (IPP).
“Payment Request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions—Commercial Items included in commercial item contracts.
The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. Contractor assistance with enrollment, UserIDs and Passwords can be obtained by contacting the IPP Helpdesk via email at IPP Customer Support Desk at 1- 866-973-3131.
In accordance with the requirements of the Debt Collection Improvement Act of 1996, all payments under this order will be made by electronic funds transfer (EFT). The Contractor shall provide financial institution information to the Finance OƯice designated above in accordance with FAR 52.232-33 Payment by Electronic Funds Transfer - System for Award Management.”