SolicitationAttachment2Specifications_124PCA27Q0005.pdf
PDF 1 MB Posted
- Attached to
- Parking Lots Repair, National Agricultural Library and Beltsville Agricultural Research Center West
- Solicitation number
- 124PCA27Q0005
About this file
This is a comprehensive specifications document for parking lot repair work at two USDA locations in Beltsville, Maryland. The contract encompasses milling, patching, re-paving, and re-striping of parking lots at the National Agricultural Library (NAL) and Beltsville Agricultural Research Center (BARC) West. Work includes five contract line items (CLINs): three for NAL parking lots (West, East, and Front with driveways) and two for BARC West (cleaning/restriping and optional milling/repaving of a 160-foot road section). The contractor must complete all work within 120 consecutive calendar days after Notice to Proceed and submit a detailed construction schedule within 14 calendar days of award.
The specifications establish extensive requirements including mandatory site visit attendance, preconstruction conference within 35 days of award, and formal partnering sessions with government personnel. The contractor must provide an OSHA-certified competent person on-site at all times, ensure all employees complete 10-hour OSHA construction safety training (30-hour for supervisors), and submit a site-specific safety plan covering OSHA and NFPA standards before work begins. Additional requirements include a Contractor Quality Control Plan, daily inspection reports, monthly progress photographs, construction waste management with minimum 10 percent landfill diversion, continuous monitoring for noise/dust/vibrations with noise exposure not exceeding 75 dB for ARS staff, Material Safety Data Sheets for all hazardous chemicals, and hot work permits for applicable operations. The project superintendent must have minimum 10 years construction experience with at least 5 years as superintendent on similar projects. A one-year warranty on all work is required from final acceptance, and the contractor is responsible for protecting existing equipment, managing traffic flow, and maintaining unobstructed emergency access throughout construction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
National Agricultural Library (NAL) & Beltsville Agricultural Research
Center (BARC) West Parking Lot Repairs
USDA-National Agricultural Library 10301 Baltimore Ave #115 Beltsville, MD 20705
USDA-BARC West 10300 Baltimore Ave.
Beltsville, MD 20705
Prepared For:
U.S. Department of Agriculture Agricultural Research Service (ARS)
Contract No.
TBD
Prepared By:
U.S. Department of Agriculture – ARS Beltsville, Maryland
October 27, 2026
Note: Disregard sections of this specification that are not applicable to the execution of this project.
NAL & BARC (West) Parking Lot Repairs
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF
CONTENTS DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24 SUMMARY OF WORK
01 30 00 11/20 ADMINISTRATIVE REQUIREMENTS
01 33 00 08/18 SUBMITTAL PROCEDURES
01 35 26 05/24 GOVERNMENTAL SAFETY
REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE
PUBLICATIONS
01 45 00 08/23 QUALITY CONTROL
01 50 00 11/20 TEMPORARY CONSTRUCTION
FACILITIES AND CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL
CONTROLS
01 78 00 05/19 CLOASEOUT SUBMITTALS
01 78 23 05/23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 01 16.71 11/22, COLD MILLING ASPHALT PAVING
32 12 13 05/24 BITUMINOUS TACK & PRIME COATS
32 12 16 16 11/12 ROAD-MIX/ HOT-MIX ASPHALT PAVING
32 17 23.16 11/24 ROAD & LOT PAVEMENT MARKINGS
-- End of Project Table of Contents --
NAL & BARC (West) Parking Lot Repairs
PROJECT TABLE OF CONTENTS Page 2
THIS PAGE INTENTIONALLY LEFT BLANK
NAL – BARC(West) Parking Lot Repairs
SECTION 01 11 00 Page 4
SECTION 01 11 00
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
1.1.1 Work To Be DoneThe work to be done consists of furnishing all labor, materials, and equipment and performing all work in strict accordance with these specifications for repairing the Parking Lots for the National Agricultural Library (NAL) and Beltsville Agricultural Research Center (BARC) West.
1.1.2 Location. There are two work sites:
1) National Agricultural Library (NAL)
10301 Baltimore Ave #115 Beltsville, MD 20705.
2) Beltsville Agricultural Research Center (BARC)West 10300 Baltimore Ave.
Beltsville, MD 20705
1.1.3 Principal Features of Work
The Base Bid shall be milling, patching, numbering, and re-striping of the NAL and BARC parking lots.
CLIN1 – NAL, Mill/ Repave/ Restripe Parking lot West.
CLIN2 – NAL, Mill/ Repave/ Restripe Parking Lot East.
CLIN3 – NAL, Mill/ Repave/ Restripe “Front” parking lot and driveways.
CLIN4 – BARC West, Clean/ Restripe Parking Lots:
CLIN5 (Option) – BARC West, Mill (4 Inches)/ repave road (160 Feet). See drawings.
1.2 SITE VISIT
A site visit and inspection tour will be held at the National Agricultural Library & BARC west, in Beltsville, MD. All potential bidders will be notified of the exact time and date and are strongly urged to attend the site visit. Inspection may only be made at this time, unless prior written approval is obtained to inspect at another date and time.
Contact:
U.S. Department of Agriculture, ARS Attn: Stan Koseki/ Jermaine Winstead National Agricultural Library (NAL) 10301 Baltimore, Beltsville, MD 20705.
1.3 COORDINATION OF WORK
1. Workspace and space available for storing materials shall be subject to the approval of the Contracting Officer. Do not store materials and equipment in other than assigned areas.
2. Execute work so as to minimize the normal functioning of the facility, including operations of utility services and any existing equipment, and with work being done by subcontractors. No work shall be done during the adverse weather.
3. Minimize interference of construction activities with the flow of traffic by keeping roads, walks and entrances to grounds, to parking areas and to occupied areas of buildings clear of construction materials, debris, construction equipment and vehicles except where noted on plans or in specifications. Provide unobstructed access to areas required to remain in operation.
4. Building will be occupied during performance of work under this Contract.
Occupancy notifications will be posted in a prominent location in the work area.
5. Before work starts, arrange with the Contracting Officer a sequence of procedures, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways. Contractor shall not mobilize and demolish the existing chiller until 1-2 weeks prior to the delivery of the new chiller.
6. The Contractor shall complete all work within 120 consecutive calendar days after Notice to Proceed. Within 14 calendar days after Contract Award, the Contractor shall provide the Government with a detailed schedule of dates on which the Contractor plans to accomplish the work. In addition, the Contractor shall notify the Contracting Officer 20 days in advance of starting work. A planned work schedule shall be submitted to the Contracting Officer for approval. The schedule shall include a detailed description of the methods and equipment to be used for each operation and the sequence of operations.
This schedule shall be updated monthly and submitted to the Contracting Officer for approval.
7. The Contractor shall take all measures and provide all material necessary for protecting existing equipment, property, and ongoing operations in affected areas of construction against dust, noise and debris.
8. Power sources for the Contractor's operations will be available and supplied by the Government to the Contractor as long as its use does not interfere with the operations of the Government's facilities. Water sources will be available and supplied by the Government to the Contractor as long as its use does not interfere with the operations of any building. The Contractor is responsible for extending utility sources to his work locations. Such extensions shall be removed after work is completed, to the satisfaction of the Contracting Officer.
9. All references in the specifications to the Contracting Officer and Contracting Officer's Representative shall constitute referrals initially to the Contracting Officer's Representative.
10. Contractor shall provide sanitary facilities for use by his/her employees and the employees of his subcontractors working on the job site.
1.4 DRAWINGS
All dimensions shown of existing work and all dimensions required for work, shall be verified by the Contractor. Any work of variance with that specified or shown on the drawings shall not be performed by the Contractor until the Contractor has received approval in writing from the Contracting Officer.
1.5 EXISTING WORK
Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remains.
Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer.
At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.6 MATERIAL SAFETY DATA SHEETS (MSDS)
Material Safety Data Sheets must be submitted to the Contracting Officer prior to the commencement of any work with any substance that may be considered hazardous.
1.7 UTILITIES OR STRUCTURAL ITEMS CONFLICTING WITH PROPOSED
CONSTRUCTION
In the event the Contractor finds an area where existing utilities or structural items conflict with proposed construction, the Contracting Officer shall be notified immediately.
The Contractor shall then propose a method of solving the problem. Work shall not resume in the problem area until the Contractor has received written approval from the Contracting Officer. There shall be no additional cost to the Government.
1.8 ACCEPTANCE OF WORK
1. Final inspection will not be made until the contract work is completed. The Contractor shall notify in writing the Contracting Officer fifteen working days prior to the date on which the work will be ready for final inspection.
2 Final inspection and acceptance of the work shown by the drawings and specifications forming a part of this contract shall not be binding or conclusive on the Government if it shall be shown that (1) the Contractor has willfully or through collusion with persons or firms engaged in the performance of the contract supplied inferior materials, equipment, or workmanship, or (2) the Contractor has otherwise departed from the terms of the contract.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 00 11 Page 4
SECTION 01 30 00 Page 4
PART 1 GENERAL REFERENCES
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 1: 08/2
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Progress and Completion Pictures
1.2 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Include aerial photographs. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 10 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice digital files of photographs and include a date designator in file names. Photographs provided are for unrestricted use by the Government.
1.3 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.4 SUPERVISION
1.4.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years of experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.4.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.4.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings.
The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.4.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.5 PRECONSTRUCTION MEETING CONFERENCE
Immediately after award, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference. The conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: Daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, Government acceptance, final inspections and contract close-out. The contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.5.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.6 PARTNERING
To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.
1.6.1 Facilitated (Formal) Partnering
a. Provide and host a Formal Partnering session with key personnel from the project team including both Contractor and Government personnel.
All costs associated with the Partnering session including the third-party independent Facilitator Consultant, meeting room and other incidental items are the responsibility of the Contractor.
b. Before the Facilitated (Formal) Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note pads, pens/pencils, colored flash cards) and have these items available at the Partnering session. Provide copies of any documents required for distribution to all attendees.
Participants will bear their own costs for meals, lodging and transportation associated with Partnering.
c. The Initial Partnering Session must be a duration of one day and be held at a location off base as agreed to by the Contracting Officer. Partnering session may take place concurrently with the
Pre-Construction Meeting.
d. Facilitator must be experienced in conducting corporate Partnering sessions and must be a third-party independent facilitating consultant
- not an employee of the Contractor. The Facilitator is responsible for leading all aspects of the Partnering session necessary to achieve the Partnering goal.
e. An outcome of the Partnering session must be an escalation matrix agreed upon by both the Government and Contractor, which identifies key Government and Contractor decision makers by name and anticipated decision durations.
f. Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less. Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the follow-on sessions unless an alternative is permitted by the Contractor Officer. All costs associated with follow-on Partnering sessions are the responsibility of the Contractor.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
NAL & BARC(West) Parking Lot Repairs
SECTION 01 35 26 Page 1
1.1 REFERENCES
SECTION 01 35 26
GOVERNMENTAL SAFETY
REQUIREMENTS
05/24
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E84 (2020) Standard Test Method for Surface Burning Characteristics of Building Materials
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2022; ERTA 1 2021) Standard for Portable Fire Extinguishers
NFPA 30 (2021; TIA 20-1; TIA 20-2) Flammable and Combustible Liquids Code
NFPA 51B (2019; TIA 20-1) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
NFPA 70 (2020; TIA 22-1; ERTA 1 2022)
National Electrical Code
NFPA 101 (2021) Life Safety Code
NFPA 241 (2022) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1926 Safety and Health Regulations for Construction
1.2 GENERAL INTENTION
A. Contractor shall completely prepare the site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work as required by the contract documents.
B. All employees of general contractor and subcontractors shall comply with ARS security management program, obtain permission of the ARS Location Manager, be identified by project and employer by wearing contractor issued identification badges at all times on ARS property, and restricted from unauthorized access.
C. Prior to commencing work:
SECTION 01 35 26 Page 2
1. The General Contractor shall provide proof that an OSHA certified "competent person" (CP) 29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
2. The General Contractor and Tradesmen shall receive an On-site Safety briefing from the location Facilities Manager or designated representative.
D. Training:
1. All employees of the general contractor or subcontractors shall have the 10-hour OSHA- certified Construction Safety course and /or other relevant competency training. Supervisors shall have completed the 30-hour OSHA training. Before work can begin, all contractors who will be working onsite must go through a 15-minute OSHA safety briefing by the Location Safety Officer before any work can begin.
2. Submit training records of all such employees to the Contracting Officer for approval before the start of work.
1.3 PROJECT COORDINATION
A. Construction Project Schedule: See contract, FAR 52.236-15 Schedules for Construction Contracts. The Contractor will not begin work on site until the construction project schedule has been approved by the Contracting Officer. The Contractor shall submit one electronic copy of the updated construction project schedule with each progress payment request.
B. Contract Inspector's Daily Report: Contractor shall submit to the Contracting Officer a daily report listing the names of all those present on the job site each day, along with their Job Classification, hours of work and a brief description of the work performed by each on that day. The Contract Inspector's Daily Report is to be submitted at the beginning of work each day for the previous day's work and shall be maintained throughout the term of the contract.
C. Formal Meetings: Any meeting (deemed formal by the contractor, the Contracting Officer Representative (COR) or the Contracting Officer will have the minutes of said meeting prepared by the contractor with copies provided to the COR and Contracting Officer within twenty-four (24) hours of meeting time. The minutes will include Date, Name of Attendees (with contact info), Old Business, and New Business subjects (or narratives).
Regardless of who requests a meeting (the COR or the Contractor or the Contracting Officer) the contractor may be required to provide hard copy pictures of the issues to be discussed. Each issue will be linked to a contract specification section number and/or subject area by page number. Issues discussed will also include an action/completion date.
1.4 SUBMITTALS - GENERAL
A. All submittals referenced by the procurement documents including but not limited to Plans, Specifications, Statements of Work (SOW), Supplemental Information, etc. shall be submitted electronically to the Contracting Officer (CO) and Construction Officer Representative (COR).
B. All material sample submittals referenced by the procurement documents including but not limited to Plans, Specifications, Statements of Work (SOW), Supplemental Information, etc. shall be provided to the Contracting
SECTION 01 35 26 Page 3
Officer (CO), Construction Officer Representative (COR) and Location Manager/Facilities Manager (LM/FM).
C. All items submitted shall be accompanied by the SUBMITTAL LOG appended to the
GENERAL SPECIFICATIONS.
1. The Contractor shall maintain one (1) log for all submittals and shall update the information as required by Construction Progress.
1.5 SAFETY SUBMITTALS
A. Contractor shall submit a "site specific" Safety Plan to the Contracting Officer that describes how the contractor is to comply with all applicable OSHA standards and NFPA codes pertaining to construction work to include, but not limited to: General Safety and Health Provisions, Occupational Health and Environmental Controls, Personal Protective and Life Saving Equipment, Hand and Power Tools, Welding and Cutting, Electrical, Scaffolds, Fall Protection, Excavations, Demolition, Stairways and Ladders, Toxic and Hazardous Substances, Confined Space Entry, Lockout/Tagout, Respiratory Protection, Hearing Protection. Safety Plan shall identify Contractor and sub-contractor employees who are authorized/qualified to perform electrical work. No work shall proceed until written approval of the Safety Plan by the Contracting Officer. Safety Plan shall describe how the Contractor and/or sub-contractors are to secure equipment, supplies, tools, and chemical products. Contractor and/or sub-contractor equipment, supplies, tools, and chemical products are to be under the control of the Contractor at all times, equipment, supplies tools, and chemical products found not to be under the control of the Contractor or sub-contractor are subject to confiscation and will be reported to the Contracting Officer.
B. The Contractor must follow all current Federal, State and Local Pandemic Specific Requirements for access to all BARC and USNA locations and worksites. Current requirements shall be provided by the Contracting Officer's Representative (COR), Location Coordinator (LC) or Safety and Occupational Health Unit (SOHU) Manager.
C. The Contractor shall inspect the entire construction site daily, including days without construction work if there are NFPA 101 Life Safety Code deficiencies existing while construction work is shut down, the results of that inspection shall be documented on the attachment "DAILY INSPECTION FORM", and the form is to be signed and submitted to the Contracting Officer.
D. The Contractor shall provide continuous monitoring for noise, dust, chemical vapor generation, volatile organic compounds, and vibration. At no time shall noise exposure to any ARS staff exceed 75 db. Contractor shall provide to the COR with copies to the Contracting Officer a written weekly update of the all test results in addition to the proposed work for the subsequent two weeks (a two week "look- ahead”) involving any construction activity that will produce loud noises, heavy vibrations, strong smells, or significant dust inside ARS staff occupied space.
E. Contractor and sub-contractors shall notify in writing the Contracting Officer at least one week prior to executing high risk work (this may be included in the two-week "look-ahead" update). High risk work includes, but is not limited to, tasks requiring Lockout/Tag Out, live electrical work, hot work, work at heights, trenching/ shoring, crane operations, and confined space entry. Contractor's Competent Person shall provide the COR
SECTION 01 35 26 Page 4 with a copy to the Contracting Officer written weekly documented safety inspection results.
F. Contractor shall provide to the Contracting Officer for approval, copies of Safety Data Sheets (SDS) for EVERY CHEMICAL WITHOUT EXCEPTION prior to bringing such chemical on the work site.
1.6 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Contractor Personnel
1. The required Contractor Personnel information and the security application procedures vary depending upon the project worksite location. Each Task Order Request for Proposal (RFP) will contain the Contractor Personnel information and security application procedures required for the specific site.
2. Each employee shall be furnished with a badge by the Government for access to construction site. This badge must be worn and be clearly visible on the work site.
C. Security Procedures:
1. Contractor's employees shall not enter the project site without appropriate badges. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the "regular hours" as defined in the contract, The Contractor shall give a ten (10) day notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of ARS premises is allowed without written permission of the Contracting Officer.
4. ARS reserves the right to close or shut down the project site and order the Contractor's employees off the premises in the event of a national emergency or Government shutdown. The Contractor may return to the site only with the written approval of the Contracting Officer.
D. Document Control:
1. The Contractor is responsible for safekeeping of all drawings, project manuals and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. These documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
3. All paper waste or electronic media such as CD's and diskettes shall be
SECTION 01 35 26 Page 5 shredded and destroyed in a manner acceptable to the ARS.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.
Access shall be restricted to picking up and dropping off materials and supplies and Contractor must be on site to receive all deliveries.
2. Separate permits shall be issued for Contractor and its employees for parking in designated areas only.
1.7 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
ASTM E84 Surface Burning Characteristics of Building Materials
2. National Fire Protection Association (NFPA):
NFPA 10 Standard for Portable Fire Extinguishers NFPA 30
Flammable and Combustible Liquids Code
NFPA 51B Standard for Fire Prevention during Welding, Cutting and Other Hot Work
NFPA 70 National Electrical Code
NFPA 241 Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to starting work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit them to the Contracting Officer for review for compliance with contract requirements. Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the contractor's competent person per OSHA requirements. This briefing shall include information on the construction limits, ARS safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of ARS equipment, etc. Documentation shall be provided to the Contracting Officer that individuals have undergone contractor's safety briefing.
SECTION 01 35 26 Page 6
C. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 20 feet exposing overall length, separate by 10 feet.
E. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.
F. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with Contracting Officer.
G. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to the Contracting Officer.
H. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA 241 and NFPA 10.
I. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.
J. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Provide fire watch for impairments more than 4 hours in a 24-hour period. Request interruptions in accordance with paragraph "OPERATIONS AND STORAGE AREAS", and coordinate with the Contracting Officer. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the Contracting Officer. Parameters for the testing and results of any tests performed shall be recorded by the General Contractor and copies provided to the Contracting Officer.
K. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with the Contracting Officer.
L. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Coordinate with the Contracting Officer. Designate contractor's responsible project- site fire prevention program manager to coordinate permit hot work.
M. Fire Hazard Prevention and Safety Inspections: Inspect entire construction area on a daily basis. Coordinate with and report findings and corrective actions weekly to the COR with a copy to the Contracting Officer. See USDA Standard Forms for Daily Inspection Form.
N. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
O. Dispose of waste and debris in accordance with NFPA 241. Remove from
SECTION 01 35 26 Page 7 buildings daily.
P. Perform other construction, alteration, and demolition operations in accordance with
29 CFR 1926.
1.8 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation.
When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
C. Working space and space available for storing materials shall be as determined by the Contracting Officer.
D. Workers are subject to rules of the Location applicable to their conduct which shall be provided by the Contracting Officer.
E. Execute work so as to interfere as little as possible with normal functioning of Location as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by Government. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied during construction except as permitted by the Contracting Officer where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by the ARS in quantities sufficient for not more than two (2) workdays.
3. Where access by ARS personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment may be permitted subject to fire and safety requirements.
F. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the ARS operations will not be hindered. Contractor shall permit access to ARS personnel through construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by ARS so that operations will continue during the construction period.
G. Utilities Services: Maintain existing utility services for ARS at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to ensure uninterrupted services. Where
SECTION 01 35 26 Page 8 necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the Contracting Officer.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior written approval of the Contracting Officer. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Contracting Officer's prior knowledge and written approval.
2. Contractor shall submit a request to interrupt any such services to the Contracting Officer, in writing, Two weeks advanced notice and again 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of ARS. Interruption time approved by ARS may occur at other than Contractor's normal working hours.
4. In case of a contract construction emergency, service will be interrupted on approval of the Contracting Officer. Such approval will be confirmed in writing as soon as practical.
H. To minimize interference of construction activities with flow of ARS traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
I. Coordinate the work for this contract with other construction operations as directed by Contracting Officer. This includes the scheduling of traffic and the use of roadways, as specified in paragraph "USE OF ROADWAYS".
1.9 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall conduct a thorough survey with the Contracting Officer or their designated representative, of areas of the building in which alterations occur and areas which are anticipated routes of access, and furnish a signed report to the COR with a copy to the Contracting Officer.
1. Shall note any discrepancies between drawings and existing conditions at site.
2. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and Contracting Officer.
SECTION 01 35 26 Page 9
1.10 DISPOSAL AND RETENTION
A. Materials and equipment accrued from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re- installation and reuse. Store such items where directed by Contracting Officer.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from ARS property.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the ARS during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
B. Upon completion of contract, deliver complete and undamaged work. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
1.11 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on ARS property and, when authorized by the Contracting Officer, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the Contractor at Contractor's expense.
1.12 AVAILABILITY AND USE OF UTILITY SERVICES
A. See contract, FAR Clause 52.236-14, Availability and Use of Utility Services.
1.13 TESTS
A. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
1.14 CONSTRUCTION WASTE MANAGEMENT
A. Responsibilities. The contractor shall employ processes that ensure the generation of as little waste as possible and shall avoid the
SECTION 01 35 26 Page 10 generation of waste due to the following:
1. Over-packaging.
2. Error.
3. Poor planning, layout.
4. Over ordering.
5. Breakage
6. Mishandling
7. Contamination
8. General weather damage, excluding extreme acts of nature (i.e. tornados, hurricanes, flash floods, blizzards, etc.).
B. Procedures.
1. Of the inevitable waste that is generated, as many of the waste materials as economically feasible shall be reused, salvaged or recycled.
2. Waste disposal in landfills shall be minimized to the greatest extent possible.
i. Waste Diversion Goals.
a) Demolition, Major Remodeling: Minimum 10% of total project waste shall be diverted from landfill.
b) Interior Remodeling: Minimum 10% of total project waste shall be diverted from landfill.
ii. The following waste categories, at a minimum, shall be diverted from landfill:
a) Green waste (biodegradable landscaping materials).
(i) Soil.
(ii) Inert material (concrete, asphalt, masonry).
(iii) Clean dimensional wood, palette wood.
(iv) Engineered wood products: plywood, particle board, I-joists, etc.
(v) Cardboard, paper, packaging.
(vi) Asphalt roofing materials.
(vii) Insulation.
(viii) Gypsum board.
(ix) Carpet and pad.
(x) Paint.
(xi) Plastics: ABS, PVC.
(xii) Beverage containers.
C. Description of Work.
1. Includes:
i. Waste Management Plan development and implementation.
ii. Meetings to discuss goals, issues and training for the Waste Management
Plan.
iii. Techniques to minimize waste generation.
iv. Sorting and separation of waste materials.
v. Reuse of salvaged materials on site.
vi. Salvage of existing materials and items for reuse or resale.
SECTION 01 35 26 Page 11
vii. Recycling of materials that cannot be reused or sold.
viii. Record keeping of receipts and records of salvaged, recycled or land filled materials.
2. Related Elements:
i. Alternates.
ii. Construction Waste Management.
iii. Site Demolition.
iv. Site Clearing.
v. Slope Protection/Erosion Control.
vi. Asphalt Concrete.
vii. Crushed Stone Paving.
viii. Portland Cement Concrete Paving.
ix. Valve Boxes.
x. Storm Sewers.
xi. Chain Link Fences and Gates.
xii. Walk, Road and Parking Appurtenances.
xiii. Miscellaneous Landscaping Materials.
xiv. Concrete, Concrete Formwork, and Concrete Reinforcement.
xv. Cast-in-Place Concrete.
xvi. Unit Masonry.
xvii. Structural Steel.
xviii. Steel Roof Deck/Steel Floor Deck.
xix. Cold Formed Metal Framing.
xx. Metal Fabrications.
xxi. Rough and Finish Carpentry.
xxii. Engineered Structural Wood.
xxiii. Plastic Lumber.
xxiv. Building Insulation.
xxv. Modified Bitumen Roofing.
xxvi. Metal Doors.
xxvii. Wood and Plastic Doors and Frames.
xxviii. Metal Support Systems.
xxix. Gypsum Wallboard.
xxx. Acoustical Treatment.
xxxi. Resilient Flooring.
xxxii. Tile and Carpet.
xxxiii. Painting.
xxxiv. Toilet Compartments.
xxxv. Louvers and Vents.
xxxvi. Signage and Graphics.
xxxvii. Ductwork and Ductwork Accessories
D. Definitions.
1. Class III Landfill: A landfill that accepts non-hazardous resources such as household, commercial and industrial waste resulting from construction, remodeling, repair and demolition operations.
2. Clean: Untreated and unpainted; uncontaminated with adhesives, oils, solvents, mastics and like products.
3. Construction and Demolition Waste: Includes all non-hazardous resources resulting from construction, remodeling, alterations, repair and demolition operations.
4. Dismantle: The process of parting out a building in such a way as to preserve the usefulness of its materials and components.
SECTION 01 35 26 Page 12
5. Disposal: Acceptance of solid waste at a legally operating facility for the purpose of land filling (including Class III landfills and inert fills).
6. Inert Backfill Site: A location, other than inert fill or other disposal facility, to which inert materials are taken for the purpose of filling an excavation, shoring or other soil engineering operation.
7. Inert Fill: A facility that can legally accept inert waste, such as asphalt and concrete exclusively for the purpose of disposal.
8. Inert Solids/Inert Waste: Non-liquid solid resources including, but not limited to, soil and concrete that do not contain hazardous waste or soluble pollutants at concentrations in excess of water-quality objectives established by a regional water board and do not contain significant quantities of decomposable solid resources.
9. Mixed Debris: Loads that include commingled recyclable and non-recyclable materials generated at the construction site.
10. Mixed Debris Recycling Facility: A solid resource processing facility that accepts loads of mixed construction and demolition debris for the purpose of recovering re-usable and recyclable materials and disposing non-recyclable materials.
11. Permitted Waste Hauler: A company that holds a valid permit to collect and transport solid waste from individuals or businesses for the purpose of recycling or disposal.
12. Recycling: The process of sorting, cleansing, treating, and reconstituting materials for the purpose of using the altered form in the manufacture of a new product. Recycling does not include burning, incinerating or thermally destroying solid waste.
i. On-site Recycling. Materials that are sorted and processed on site for use in an altered state in the work, i.e. concrete crushed for use as a sub-base in paving.
ii. Off-site Recycling. Materials hauled to a location and used in an altered form in the manufacture of new products.
13. Recycling Facility: An operation that can legally accept materials for the purpose of processing the materials into an altered form for the manufacture of new products.
Depending on the types of materials accepted and operating procedures, a recycling facility may or may not be required to have a solid waste facility permit or be regulated by the local enforcement agency.
14. Re-Use: Materials that are recovered for use in the same form, on-site or off-site.
15. Return: To give back reusable items or unused products to vendors for credit.
16. Salvage: To remove waste materials from the site for resale or re-use by a third party.
SECTION 01 35 26 Page 13
17. Source-Separated Materials: Materials that are sorted by type at the site for the purpose of reuse and recycling.
18. Solid Waste: Materials that have been designated as non-recyclable and are discarded for the purposes of disposal.
19. Transfer Station: A facility that can legally accept solid waste for the purpose of temporarily storing the materials for re-loading onto other trucks and transporting them to a landfill for disposal or recovering some materials for re-use or recycling.
E. Guides. No preference is given to the recycles listed below; they are listed for the convenience of the contractor.
1. Dirt/clean fill.
2. Green/landscaping waste.
3. Concrete, asphaltic concrete.
4. Cardboard, paper, packaging.
5. Clean dimensional wood, palette wood.
6. Usable palettes.
7. Metals from banding, ductwork, piping, rebar, roofing, other trim, steel, iron, galvanized sheet steel, stainless steel, aluminum, copper, zinc, lead, brass, and bronze.
8. Carpet and pad.
9. Gypsum board.
10. Paint.
11. Insulation.
12. Asphalt shingles.
13. Beverage containers.
F. Submittals.
1. Waste Management Plan. Prior to any waste removal, the Contractor shall submit their Waste Management Plan to the ARS. The Plan shall contain the following:
i. Analysis of the estimated job site waste to be generated, including types and quantities.
ii. Proposed alternatives to land filling. Contractor shall prepare a list of each material proposed to be salvaged, re-used, or recycled during the course of the project.
iii. Methods of handling materials to be recycled.
2. On Site:
i. Materials separation
ii. Materials storage
iii. Materials protection, where applicable
3. Off site:
i. Provide name of mixed debris recycling facility; include list of materials to be recycled.
ii. Procedures. A description of the means to be employed in recycling the above materials consistent with requirements for acceptance by designated facilities.
iii. Landfill Options. The name of the landfill(s) where trash will be disposed of.
SECTION 01 35 26 Page 14
a) Meetings: Contractor shall conduct Construction Waste Management meetings.
Meetings shall include the Subcontractor, the Project Manager and representatives as designated by the Contracting Officer. At a minimum, waste management goals and issues shall be discussed at pre-bid meetings, pre-construction meetings and regular job-site meetings.
b) Transportation: A description of the means of transportation of the recyclable materials (whether materials will be site-separated and self-hauled to designated facilities, or whether mixed materials will be collected by a waste hauler and removed from the site) and destination of materials.
c) Waste Management Plan Implementation.
(i) Manager. The contractor shall designate an on-site party (or parties) responsible for instructing workers and subcontractors and overseeing and documenting results of the Waste Management Plan for the project.
(ii) Distribution. The contractor shall distribute copies of the Waste Management Plan to the Contracting Officer and Location Manager.
(iii) Instruction. The contractor shall provide on-site instruction of appropriate separation, handling, recycling, salvage, reuse and return methods to be used by all parties at appropriate stages of the project.
(iv) Separation Facilities. The contractor shall lay out and label a specific area to facilitate separation of materials for reuse, salvage, recycling, and return. Recycling and waste bin areas are to be kept neat and clean and clearly marked in order to avoid contamination or mixing of materials.
(v) Hazardous Wastes. Hazardous wastes shall be separated, stored, and disposed of according to local, state and federal regulations.
4. Reports: The Contractor shall submit (monthly, quarterly, at end of job) a Waste Management Progress Report. The report shall contain the amount (in tons or cubic yards) of material land filled from the project, the identity of the landfill, the total amount of tipping fees paid at the landfill and the total disposal cost. Include legible copies of manifests, weight tickets, receipts and invoices.