12447U19Q0015 Demolition, Removal, Disposal of the Existing Shed and Constructing a Larger Metal Shed at Ashe Seed Extractor in Desoto National Forest
ISSUING OFFICE: U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
200 S Lamar St 500N Jackson, MS 39201
SOLICITATION NO.: 12447U19Q0015
SET-ASIDE: 100% SMALL BUSINESS
IMPORTANT – NOTICE TO OFFEROR:
AT A MINIMUM, OFFEROR SHALL SUBMIT THE FOLLOWING DOCUMENTS BACK WITH
THEIR RESPONSE TO THIS SOLICITATION:
1. SF-18 – Solicitation, Offer and Award (Complete, Date, and Sign)
2. Part I, Section B-1, Schedule of Items
3. Part IV, Section K-1, 52.204-8 Annual Representations and Certifications
4. Part II, Section I-3 verification of Small Business
5. Part II, Section I-6, 52.225-9 Buy American Construction Materials (if applicable)
6. Exhibit #1, Experience and Equipment Questionnaire
7. Exhibit #2, Representation by Corporations Regarding an Unpaid Delinquent Tax Liability or a Felony Conviction
10. Attachment #3, Subcontractor Reporting Form (if applicable)
11. Responses to Experience, Technical Capability, Technical Approach, Past Performance & Biobase (Detailed in Sections L and M).
It is required that you write the solicitation number on the outside of your envelope. Offers must be mailed, hand delivered or E-mailed (faxed offers will not be accepted). Please keep a copy of your quote for your records. Return to: USFS - Region 4 - Utah Acquisition Support Center
ATTN: Cynthia Granderson 200 S Lamar St Suite 500N Jackson, MS 39201 Solicitation No:12447U19Q0015 Cynthia.granderson@usda.gov
IT IS REQUIRED THAT ALL CONTRACTOR’S BE REGISTERED AND VALID IN THE SYSTEM FOR
AWARD MANAGEMENT – SAM - DATABASE PRIOR TO AWARD UNDER THIS SOLICITATION.
THE WEBSITE IS WWW.ACQUISITION.GOV; CONTRACTORS SHALL ALSO BE REGISTERED IN THE SAM
DATABASE UNDER THE NAICS CODE THAT THIS SOLICITATION IS BEING ISSUED UNDER, OR
DEMONSTRATE THEIR ABILITY TO QUALIFY AS A SMALL BUSINESS UNDER THE IDENTIFIED NAICS CODE.
mailto:Christine.M.Hansen@usda.gov http://www.acquisition.gov/
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
969081
USDA FOREST SERVICE
NATIONAL FORESTS IN MISSISSIPPI
200 S LAMAR ST STE 500N BOX 44
JACKSON MS 39201
447U
CYNTHIA GRANDERSON 601-965-1619
12447U19Q0015
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Demolition, Removal, Disposal of the Existing Shed and Constructing a Larger Metal
Shed at Ashe Seed Extractor in Desoto National Forest
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 30 calendar days and complete it within ________________ ________________ calendar days after receiving
09/06/2019
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ _______ _______ _____ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
X
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12447U19Q0015
Delivery: 08/15/2019
Delivery Location Code: 446X
USDA FOREST SERVICE
DESOTO RANGER DISTRICT
PO BOX 248
WIGGINS MS 39577 US
0001 Construction of steel Building. 1 EA
Period of Performance: 09/09/2019 to 09/20/2019
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Demolition, Removal, Disposal of the Existing Shed and Constructing a Larger Metal Shed at Ashe Seed Extractor in Desoto National Forest
Cost Estimate for Demolishing, Removing, and Disposing of the Existing Shed and Construction of New Metal Shed at Ashe Nursery
Item No.
Description Unit Qty. Unit Price
Total
1 Mobilization and Demobilization L.S. 1 2 Demolish, remove, and dispose of existing pole shed S.F. 1,375
3 Construct a new metal shed with the dimensions of 90’-0” by 40’-0”, have a roof pitch of 2/12, and 23’ tall at the top of the peak of the roof.
S.F. 3,600
TOTAL
The offeror shall insert a quote in the Schedule opposite each pay name listed in the Schedule. An offer is not to be tendered for any item not listed. All other items not listed are incidental to one of the items listed above.
Name of Company Date:
Company Agent: DUNs
E-Mail Address:
Phone
* Designated Method of Measurement:
SF – Square Foot LS – Lump Sum
B- 2 Quote on all items. Only quotes to the nearest cent will be accepted.
B- 3 Written Acceptance: Any contract resulting from this solicitation will require written acceptance within 10 days of receipt by the Contractor.
Demolition, Removal, Disposal of the Existing Shed and Constructing a Larger Metal Shed at Ashe Seed Extractor in Desoto National Forest
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C- 1 Project Description, Scope, and Specifications
1.1 SCOPE OF CONTRACT
A. The project includes demolish, remove, dispose of existing pole shed and construct a new metal shed with the dimensions of 90’-0” by 40’-0”, have a roof pitch of 2/12, and 23’ tall at the top of the peak of the roof.
1.2 PROJECT LOCATION
A. Desoto Ranger District 654 West Frontage Rd Wiggins MS 39577.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction sites will be open to Forest Service employees during construction. The Contractor will be responsible for signing and limiting access where necessary. Contractor will be responsible to work with Contracting Officer on schedule and construction so as to disturb the users of the facilities as little as possible.
a. All work on-site shall be completed within 21 calendar days (14 is preferred), to minimize disturbance to the employees.
2. Water is available at the site for construction purposes.
3. Utilities are available at the site for construction purposes.
4. Bathroom facilities are not available onsite. The contractor shall provide temporary toilet facilities for the duration of the project.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the CO and Local Transportation Authority. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD).
All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
B. Signing and barricades shall be adequate enough to protect Forest Service employees and the public.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site.
Overnight camping on site will not be allowed.
B. Confine storage of materials and equipment as approved by the Contracting Officer.
C. Contractor shall maintain access to the facilities for Forest Service contracting personnel.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.7 START DATE
A. September 2019
1.8 CONTRACT TIME
A. 60 Calendar Days
1.9 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
Section 000050 - Project Description Section 011250 - Measurement And Payment Section 011900 - Mobilization Section 013300 - Submittal Procedures Section 024100 - Waste Material Disposal Section 064023 - Interior Architectural Woodwork Section 072100 - Building Insulation Section 092500 - Gypsum Board Section 096520 - Sheet Vinyl Floor Coverings Section 099123 - Painting Section 099300 - Staining And Transparent Finishing Section 224100 - Residential Plumbing Fixtures Section 260500 - Common Work Results For Electrical
C-2 Project Magnitude. Government’s estimated price range per FAR 36.204, is between $25,000 to $100,000.
C- 3 Biobased Product Utilization The Contractor must comply with the Agricultural Act of 2014; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C.
8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February 2012, to provide biobased products.
The Contractor shall utilize products and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer’s Representative (COR).
The following is an example list of products that may be used in this contract for which biobased products are available. The list is not all inclusive. It is desirable that Contractors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.
Adhesives Adhesive and Mastic Removers Cleaners Bathroom and Spa Cleaners Chemicals Cleaning Tools Disinfectants Exterior Paint and Coatings Floor Coverings (Non-Carpet)
Foams General Purpose Household Cleaners
Glass Cleaners Interior Paints and Coatings Loose Fill and Batt Lubricant Components Lumber Metal Cleaners and Corrosion Removers Microbial Cleaners Multipurpose Cleaners Paints and Coating Plastic Foams Plastic Resins
Biobased products that are designated for preferred procurement under USDA’s Biopreferred Program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material.
In addition to the biobased products designated by the U.S. Department of Agriculture in the Biopreferred Program, the Contractor is encouraged to use other commercially available biobased products.
The Contractor shall submit with the initial proposal a complete list of biobased products, indicating the name of the manufacturer, cost of each material, and the intended use of each of the materials that are to be used in carrying out the requirements of this contract (see Exhibit 1 - Experience Questionnaire).
http://www.biopreferred.gov/
Additionally, the winning Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes (see Section I, FAR Clause 52.223-2).
Within thirty (30) days of contract award, the Contractor shall submit an Operation Plan. This submittal will be approved by the COR in writing. The Contractor shall not commence work until this submittal is approved by the COR in writing. The Plan must be reviewed and updated annually, and as required by the COR. The Plan must contain and define the following elements:
• The Contractor’s written policy stating its commitment to the use of biobased products, employee health and safety, and sound environmental management practices.
• Detail on how the Contractor intends to keep abreast of the development and increasing availability of designated and non-designated biobased products and how any new or improved products will be incorporated on an ongoing basis into contract performance.
• Proposed biobased construction products which must be selected in accordance with the criteria included above. At a minimum, the Plan must identify products by brand name for each of the product types.
NOTE: A Contractor may propose more than one product within a product category and/or propose a product or products addressing more than one product category.
• The product guides which define standard operating procedures for instructing staff in the proper use, storage, and disposal of biobased products; proper maintenance of equipment; and other procedures/instructions to accomplish work under this contract.
The Contractor shall provide data on the quantity and dollar values of biobased products used in this contract. The data shall be submitted to the COR quarterly.
A demonstration of proper use, an effective training program, and technical assistance are essential to the success of the purchase and use of some biobased products that may function differently than a conventional product.
C- 4 Standard Specifications See Section J for the list of Standard Specifications that are incorporated into this solicitation and any resultant contract.
C- 6 Drawings See Section J for the listing of Drawings that are incorporated into this solicitation and any resultant contract.
SECTION E - INSPECTION AND ACCEPTANCE
E- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – https://www.dm.usda.gov/procurement/policy/agar_x/agar04.pdf
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996) 52.246-13 Inspection--Dismantling, Demolition, or Removal of Improvements (AUG 1996) http://www.acquisition.gov/far
SECTION F - DELIVERIES OR PERFORMANCE
F- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition
52.242-14 Suspension of Work (APR 1984)
F- 2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10-calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than Sixty (60) days from Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H- 1 Use of Premises
The Contractor shall comply with the regulations governing the operation of premises which are occupied and shall perform the contract in such a manner as not to interrupt or interfere with the conduct of Government business.
H- 2 AGAR 452.237-74 Key Personnel (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel: Site Superintendent
(b) During the first thirty (30) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 30-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
H- 3 AGAR 452.236-77 Emergency Response (NOV 1996)
(a) Contractor’s Responsibility for Fire Fighting.
(1) The Contractor, under the provisions of FAR clause 52.236-9, Protection of Existing
Vegetation, Structures, Equipment, Utilities, and Improvements, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work.
(2) The Contractor may be held liable for all damages and for all costs incurred by the
Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor’s agents or employees.
(b) Contractor’s Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.
(c) Contractor’s Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to fire fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the Changes Clause, FAR 52.243-4.
Demolition, Removal, Disposal of the Existing Shed and Constructing a Larger Metal Shed at Ashe Seed Extractor in Desoto National Forest
H- 4 Incidental Payment Items
The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
H- 5 Conformity with Drawings and Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.
H-6 Invoice Processing Platform (IPP)
The Forest Service is utilizing the Invoice Processing Platform (IPP) for the electronic submission and tracking of contracts/purchase orders, invoices, and payment information. IPP is a secure Government-wide, Web-based invoice processing service. Visit http://www.ipp.gov to learn more.
Upon award of a contract, Contractors will be enrolled automatically. Contractor will subsequently receive electronic notification from IPP of enrollment. IPP password will be delivered electronically to allow first login to IPP. Contractors shall submit all invoices electronically via IPP. Paper copies of invoices will no longer be accepted.
H-7 Prework Conference
Prior to commencement of work, the Contracting Officer will arrange a meeting with the Contractor to discuss the contract terms and work performance requirements. Also at this meeting such things as work progress schedule and fire prevention and suppression plans shall be developed and established in writing.
http://www.ipp.gov/
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition
52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN
2017) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2016) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.222-3 Convict Labor (JUNE 2003) 52.222-6 Construction Wage Rate Requirements (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (AUG 2018) 52.222-9 Apprentices and Trainees (JULY 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination--Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY
2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEPT 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-36 Equal Opportunity for Workers with Disabilities (JUL 2014) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (MAR 2015) 52.222-55 Minimum Wages Under Executive order 13658 (DEC 2015) 52.223-3 Hazardous Material Identification and Material Safety Data (JAN 1997) Alternate I (JULY
1995) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts
(AUG 2018)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011)
52.224-1 Privacy Act Notification (APR 1984) 52.225-11 Buy American – Construction Materials under Trade Agreement (OCT 2016) 52.225-13 Restrictions on Certain Foreign Purchases (JUNE 2008) 52.227-4 Patent Indemnity--Construction Contracts (DEC 2007) 52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer—System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) Alternate I (DEC 1991) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-26 Preconstruction Conference (FEB 1995) 52.243-4 Changes (JUNE 2007) 52.243-5 Changes and Changed Conditions (APR 1984) 52.244-2 Subcontracts (OCT 2010) 52.244-6 Subcontracts for Commercial Items (NOV 2017) 52.246-21 Warranty of Construction (MAR 1994) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (APR 1984) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.224-70 Confidentiality of Information (FEB 1988) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988)
I- 2 FAR 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (JUN 2016)
(a) Definitions. As used in this clause–
“Covered contractor information system” means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.
“Federal contract information” means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.
“Information” means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).
“Information system” means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).
“Safeguarding” means measures or controls that are prescribed to protect information systems.
(b) Safeguarding requirements and procedures.
(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:
(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).
(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.
(iii) Verify and control/limit connections to and use of external information systems.
(iv) Control information posted or processed on publicly accessible information systems.
(v) Identify information system users, processes acting on behalf of users, or devices.
(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.
(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.
(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.
(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.
(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.
(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.
http://uscode.house.gov/
(xii) Identify, report, and correct information and information system flaws in a timely manner.
(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.
(xiv) Update malicious code protection mechanisms when new releases are available.
(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.
(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.
(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.
I-3 FAR 52.219-28 Post-Award Small Business Program Representation (JUL 2013)
(a) Definitions. As used in this clause—
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts—
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor’s current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
Contractor Signature with authorized signer’s name and title Date
I-4 FAR 52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017)
(a) Definitions. As used in this clause (in accordance with 29 CFR 13.2)–
“Child”, “domestic partner”, and “domestic violence” have the meaning given in 29 CFR 13.2.
“Employee”–
(1) (i) Means any person engaged in performing work on or in connection with a contract covered by Executive Order (E.O.) 13706, and
Commercial and Institutional Building Construction assigned to contract number 1284N819C0016.
is not a small business concern under NAICS Code 236220 – is, The Contractor represents that it http://www.sba.gov/content/table-small-business-size-standards
(A) Whose wages under such contract are governed by the Service Contract Labor Standards statute (41 U.S.C. chapter 67), the Wage Rate Requirements (Construction) statute (40 U.S.C.
chapter 31, subchapter IV), or the Fair Labor Standards Act (29 U.S.C. chapter 8),
(B) Including employees who qualify for an exemption from the Fair Labor Standards Act's minimum wage and overtime provisions,
(C) Regardless of the contractual relationship alleged to exist between the individual and the employer; and
(ii) Includes any person performing work on or in connection with the contract and individually registered in a bona fide apprenticeship or training program registered with the Department of Labor’s Employment and Training Administration, Office of Apprenticeship, or with a State Apprenticeship Agency recognized by the Office of Apprenticeship.
(2) (i) An employee performs “on” a contract if the employee directly performs the specific services called for by the contract; and
(ii) An employee performs “in connection with” a contract if the employee’s work activities are necessary to the performance of a contract but are not the specific services called for by the contract.
“Individual related by blood or affinity whose close association with the employee is the equivalent of a family relationship” has the meaning given in 29 CFR 13.2.
“Multiemployer” plan means a plan to which more than one employer is required to contribute and which is maintained pursuant to one or more collective bargaining agreements between one or more employee organizations and more than one employer.
“Paid sick leave” means compensated absence from employment that is required by E.O. 13706 and 29 CFR part 13.
“Parent”, “sexual assault”, “spouse”, and “stalking” have the meaning given in 29 CFR 13.2.
“United States” means the 50 States and the District of Columbia.
(b) Executive Order 13706.
(1) This contract is subject to E.O. 13706 and the regulations issued by the Secretary of Labor in 29 CFR part 13 pursuant to the E.O.
(2) If this contract is not performed wholly within the United States, this clause only applies with respect to that part of the contract that is performed within the United States.
(c) Paid sick leave. The Contractor shall–
(1) Permit each employee engaged in performing work on or in connection with this contract to earn not less than 1 hour of paid sick leave for every 30 hours worked;
http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/
(2) Allow accrual and use of paid sick leave as required by E.O. 13706 and 29 CFR part 13;
(3) Comply with the accrual, use, and other requirements set forth in 29 CFR 13.5 and 13.6, which are incorporated by reference in this contract;
(4) Provide paid sick leave to all employees when due free and clear and without subsequent deduction (except as otherwise provided by 29 CFR 13.24), rebate, or kickback on any account;
(5) Provide pay and benefits for paid sick leave used no later than one pay period following the end of the regular pay period in which the paid sick leave was taken; and
(6) Be responsible for the compliance by any subcontractor with the requirements of E.O. 13706, 29 CFR part 13, and this clause.
(d) Contractors may fulfill their obligations under E.O. 13706 and 29 CFR part 13 jointly with other contractors through a multiemployer plan, or may fulfill their obligations through an individual fund, plan, or program (see 29 CFR 13.8).
(e) Withholding. The Contracting Officer will, upon his or her own action or upon written request of an authorized representative of the Department of Labor, withhold or cause to be withheld from the Contractor under this or any other Federal contract with the same Contractor, so much of the accrued payments or advances as may be considered necessary to pay employees the full amount owed to compensate for any violation of the requirements of E.O. 13706, 29 CFR part 13, or this clause, including–
(1) Any pay and/or benefits denied or lost by reason of the violation;
(2) Other actual monetary losses sustained as a direct result of the violation; and
(3) Liquidated damages.
(f) Payment suspension/contract termination/contractor debarment.
(1) In the event of a failure to comply with E.O. 13706, 29 CFR part 13, or this clause, the contracting agency may, on its own action or after authorization or by direction of the Department of Labor and written notification to the Contractor take action to cause suspension of any further payment, advance, or guarantee of funds until such violations have ceased.
(2) Any failure to comply with the requirements of this clause may be grounds for termination for default or cause.
(3) A breach of the contract clause may be grounds for debarment as a contractor and subcontractor as provided in 29 CFR 13.52.
(g) The paid sick leave required by E.O. 13706, 29 CFR part 13, and this clause is in addition to the Contractor's obligations under the Service Contract Labor Standards statute and Wage Rate Requirements (Construction) statute, and the Contractor may not receive credit toward its prevailing wage or fringe benefit obligations under those Acts for any paid sick leave provided in satisfaction of the requirements of E.O. 13706 and 29 CFR part 13.
(h) Nothing in E.O. 13706 or 29 CFR part 13 shall excuse noncompliance with or supersede any applicable Federal or State law, any applicable law or municipal ordinance, or a collective bargaining agreement requiring greater paid sick leave or leave rights than those established under E.O. 13706 and 29 CFR part 13.
(i) Recordkeeping
(1) The Contractor shall make and maintain, for no less than three (3) years from the completion of the work on the contract, records containing the following information for each employee, which the Contractor shall make available upon request for inspection, copying, and transcription by authorized representatives of the Administrator of the Wage and Hour Division of the Department of Labor:
(i) Name, address, and social security number of each employee.
(ii) The employee’s occupation(s) or classification(s).
(iii) The rate or rates of wages paid (including all pay and benefits provided).
(iv) The number of daily and weekly hours worked.
(v) Any deductions made.
(vi) The total wages paid (including all pay and benefits provided) each pay period.
(vii) A copy of notifications to employees of the amount of paid sick leave the employee has accrued, as required under 29 CFR 13.5(a)(2).
(viii) A copy of employees’ requests to use paid sick leave, if in writing, or, if not in writing, any other records reflecting such employee requests.
(ix) Dates and amounts of paid sick leave taken by employees (unless the Contractor’s paid time off policy satisfies the requirements of E.O. 13706 and 29 CFR part 13 as described in 29 CFR 13.5(f)(5), leave shall be designated in records as paid sick leave pursuant to E.O. 13706).
(x) A copy of any written responses to employees’ requests to use paid sick leave, including explanations for any denials of such requests, as required under 29 CFR 13.5(d)(3).
(xi) Any records reflecting the certification and documentation the Contractor may require an employee to provide under 29 CFR 13.5(e), including copies of any certification or documentation provided by an employee.
(xii) Any other records showing any tracking of or calculations related to an employee's accrual or use of paid sick leave.
(xiii) The relevant contract.
(xiv) The regular pay and benefits provided to an employee for each use of paid sick leave.
(xv) Any financial payment made for unused paid sick leave upon a separation from employment intended, pursuant to 29 CFR 13.5(b)(5), to relieve the Contractor from the obligation to reinstate such paid sick leave as otherwise required by 29 CFR 13.5(b)(4).
(2) (i) If the Contractor wishes to distinguish between an employee's covered and noncovered work, the Contractor shall keep records or other proof reflecting such distinctions. Only if the Contractor adequately segregates the employee’s time will time spent on noncovered work be excluded from hours worked counted toward the accrual of paid sick leave. Similarly, only if the Contractor adequately segregates the employee’s time may the Contractor properly refuse an employee’s request to use paid sick leave on the ground that the employee was scheduled to perform noncovered work during the time he or she asked to use paid sick leave.
(ii) If the Contractor estimates covered hours worked by an employee who performs work in connection with contracts covered by the E.O. pursuant to 29 CFR 13.5(a)(i) or (iii), the Contractor shall keep records or other proof of the verifiable information on which such estimates are reasonably based. Only if the Contractor relies on an estimate that is reasonable and based on verifiable information will an employee's time spent in connection with noncovered work be excluded from hours worked counted toward the accrual of paid sick leave. If the Contractor estimates the amount of time an employee spends performing in connection with contracts covered by the E.O., the Contractor shall permit the employee to use his or her paid sick leave during any work time for the Contractor.
(3) In the event the Contractor is not obligated by the Service Contract Labor Standards statute, the Wage Rate Requirements (Construction) statute, or the Fair Labor Standards Act to keep records of an employee’s hours worked, such as because the employee is exempt from the Fair Labor Standards Act’s minimum wage and overtime requirements, and the Contractor chooses to use the assumption permitted by 29 CFR 13.5(a)(1)(iii), the Contractor is excused from the requirement in paragraph (i)(1)(iv) of this clause and 29 CFR 13.25(a)(4) to keep records of the employee’s number of daily and weekly hours worked.
(4) (i) Records relating to medical histories or domestic violence, sexual assault, or stalking, created for purposes of E.O. 13706, whether of an employee or an employee’s child, parent, spouse, domestic partner, or other individual related by blood or affinity whose close association with the employee is the equivalent of a family relationship, shall be maintained as confidential records in separate files/records from the usual personnel files.
(ii) If the confidentiality requirements of the Genetic Information Nondiscrimination Act of 2008 (GINA), section 503 of the Rehabilitation Act of 1973, and/or the Americans with Disabilities Act (ADA) apply to records or documents created to comply with the recordkeeping requirements in this contract clause, the records and documents shall also be maintained in compliance with the confidentiality requirements of the GINA, section 503 of the Rehabilitation Act of 1973, and/or ADA as described in 29 CFR 1635.9, 41 CFR 60-741.23(d), and 29 CFR 1630.14(c)(1), respectively.
(iii) The Contractor shall not disclose any documentation used to verify the need to use 3 or more consecutive days of paid sick leave for the purposes listed in 29 CFR 13.5(c)(1)(iv) (as described in 29 CFR 13.5(e)(1)(ii)) and shall maintain confidentiality about any domestic abuse, sexual assault, or stalking, unless the employee consents or when disclosure is required by law.
(5) The Contractor shall permit authorized representatives of the Wage and Hour Division to conduct interviews with employees at the worksite during normal working hours.
(6) Nothing in this contract clause limits or otherwise modifies the Contractor’s recordkeeping obligations, if any, under the Service Contract Labor Standards statute, the Wage Rate Requirements (Construction) statute, the Fair Labor Standards Act, the Family and Medical Leave Act, E.O. 13658, their respective implementing regulations, or any other applicable law.
(j) Interference/discrimination.
(1) The Contractor shall not in any manner interfere with an employee’s accrual or use of paid sick leave as required by E.O. 13706 or 29 CFR part 13. Interference includes, but is not limited to–
(i) Miscalculating the amount of paid sick leave an employee has accrued;
(ii) Denying or unreasonably delaying a response to a proper request to use paid sick leave;
(iii) Discouraging an employee from using paid sick leave;
(iv) Reducing an employee’s accrued paid sick leave by more than the amount of such leave used;
(v) Transferring an employee to work on contracts not covered by the E.O. to prevent the accrual or use of paid sick leave;
(vi) Disclosing confidential information contained in certification or other documentation provided to verify the need to use paid sick leave; or
(vii) Making the use of paid sick leave contingent on the employee’s finding a replacement worker or the fulfillment of the Contractor’s operational needs.
(2) The Contractor shall not discharge or in any other manner discriminate against any employee for–
(i) Using, or attempting to use, paid sick leave as provided for under E.O. 13706 and 29 CFR part 13;
(ii) Filing any complaint, initiating any proceeding, or otherwise asserting any right or claim under E.O. 13706 and 29 CFR part 13;
(iii) Cooperating in any investigation or testifying in any proceeding under E.O. 13706 and
29 CFR part 13; or
(iv) Informing any other person about his or her rights under E.O. 13706 and 29 CFR part 13.
(k) Notice. The Contractor shall notify all employees performing work on or in connection with a contract covered by the E.O. of the paid sick leave requirements of E.O. 13706, 29 CFR part 13, and this clause by posting a notice provided by the Department of Labor in a prominent and accessible place at the worksite so it may be readily seen by employees. Contractors that customarily post notices to employees electronically may post the notice electronically, provided such electronic posting is displayed prominently on any website that is maintained by the Contractor, whether external or internal, and customarily used for notices to employees about terms and conditions of employment.
(l) Disputes concerning labor standards. Disputes related to the application of E.O.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.