This is a Questions and Answers document for the FPL Starkville Sewer Replacement solicitation. The document addresses eight key inquiries from potential contractors regarding project scope, site access, technical specifications, and contractual requirements.
The document clarifies that no pre-scheduled site visit is mandated, though contractors may arrange one independently. Both sewer lines feeding into Manhole #1 are active and must remain operational during construction via bypass systems, with temporary shutdowns permitted upon 2 business-day notice to the facility contact. Contractors are responsible for field verification of the existing gravity sewer line size and must replace it with identical dimensions. The existing sewer line invert elevations are unknown, requiring contractor measurement in the field. The existing sewer lines into Manhole #1 will remain above the new concrete bottom and do not require relocation. No permits are required as this is a federally-owned property project, and a bid bond is not required. A critical correction notes that the sewer line length is 165 feet between manholes, not 65 feet as previously indicated.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A: FPL Starkville Sewer Replacement
1. Q: Is it a scheduled visit for this Solicitation or can I just schedule one?
A: No site visit has been scheduled; however, you can schedule one.
2. Q: Are the two (2) sewer lines feeding into Manhole #1 active?
A: Yes
3. Q: What size pipe needs to be installed to replace the existing gravity sewer line?
A: Unknown. Field verify & replace with same size as existing
4. Q: Will the inverts for the two (2) sewer lines that are feeding into Manhole #1 be above the proposed new concrete bottom or will these two (2) sewer lines need to be moved
A: Yes, the existing sewer lines into MH-1 are to remain and are above the new concrete bottom.
5. Q: What are the existing invert elevations for the two (2) Manholes and the Sewer
Pipes entering them?
A: Unknown. Contractor to measure as needed.
6. Q: Do you know what permits will be required to be secured by the contractor?
A: None. This is a project contained within federal property
7. Q: Will a bid bond be required for this work?
A: No, a bid bond is not required
8. Q: Will it be possible to stop the flow into sewer MH#1 from the two existing gravity sewer lines while the new line is being removed/replaced or will we need to set up a bypass for the two lines so they can stay active?
A: Sewage from both buildings must remain active via bypass. Temporary shutdowns will be permitted with a 2 business-day notice to the facility contact.
Note: A vendor pointed out that the length of the sewer line in 165' not 65' from manhole to manhole.