This document is a Statement of Work (SOW) for the Hapgood Pond Fishing Pier and Trail Step Replacement Project. The scope includes removal of existing railings and wood steps, construction of a new fishing pier and stone steps, with an optional line item for a metal handrail. The project is located on the Green Mountain National Forest in Vermont and must be completed between September 3, 2024 and November 29, 2024.
The related federal contract opportunity, Solicitation Number 12445524Q0087, is a 100% Small Business Set-Aside procurement for this construction project. Proposals are due by 1700 EST on July 10, 2024. The Department of Agriculture Forest Service is the procuring agency. All questions from offerors are due to the Contract Specialist by July 3, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
A. Scope The Hapgood Pond Fishing Pier and Trail Step Replacement Project shall include, but is not limited to, removal of the existing railings and wood steps; layout and construction of fishing pier, including all timber, connections, excavation, backfill, wood preservation, helical piers, hardware, and approach work. Work also includes layout and construction of stone steps, including an optional Line Item for metal handrail.
B. Project Schedule Onsite construction work shall start from September 3, 2024 and shall be completed no later than November 29, 2024. The Hapgood Pond will be drained after September 16, 2024.
Sourcing of required materials shall start immediately upon Purchase Order award to preclude delay in receiving, transport and delivery of materials to the jobsite.
Workdays shall be scheduled Monday through Friday. No work is permitted on weekends or on Federal Holidays without written authorization from the Contracting Officer’s Representative (COR).
C. Project Location Hapgood Pond is located on the Green Mountain National Forest in Peru, Bennington County, Vermont.
D. Project Requirements The Contractor shall furnish the necessary personnel, material, equipment, quality control, services and facilities (except as otherwise specified), to perform this Statement of Work and the Specifications, Plans and any other attachments to the solicitation. Each culvert replacement has its own Schedule of Items and Drawings. The Contractor shall coordinate all work and scheduling for the replacement of both culverts within the contract Period of Performance. The project must be completed no later than November 29, 2024.