About this file
This document is a Statement of Work (SOW) for the NRS Hubbard Brook Pierce Lab Roof Replacement project. The SOW outlines the scope of work, which includes the removal and legal disposal of the existing asphalt shingle roof on the Pierce Lab building (approximately 5,400 square feet) and the installation of a new synthetic underlayment, architectural shingle roof, and related components. There are two bid options: Option A for replacement of the approximately 220 square foot roof on the fuel shed, and Option B for replacement of any damaged sheathing discovered during the project. The contractor must have a minimum of 5 years of roofing construction experience, be licensed in the state of New Hampshire, and be fully insured. Key deliverables include mobilization, removal and disposal of the existing roof, and installation of the new roofing system. The project is being solicited by the Department of Agriculture Forest Service under Solicitation Number 12445524Q0082.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
NRS Hubbard Brook Pierce Lab Roof Replacement 234 Mirror Lake Rd
North Woodstock, NH 03262
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Deliverables / Schedule
Site Photos
Project NRS Hubbard Brook Pierce Lab Roof Replacement
General Information
1.0 Scope of Work
The NRS Hubbard Brook Pierce Lab Roof Replacement project shall consist of the removal and legal disposal of the approximately 5,400 square feet of existing asphalt shingles, underlayment, flashings, drip edge, and fasteners on the Pierce Lab. After removal, the work shall also include the installation of full replacement of synthetic underlayment, architectural shingle roof, drip edge, valley/ridge shingles, as well as the installation of step flashings, pipe/vent/chimney penetration flashings, and other items associated with a watertight roofing installation.
There is a bid option (Option A) for replacement and installation of a new roofing system on the approximately 220 square feet roof on the fuel shed.
There is a bid option (Option B) for replacement of damaged sheathing if discovered after roof removal. Replace sheathing only with COR approval.
2.0 Background
The Hubbard Brook Facility is located at 234 Mirror Lake Rd, North Woodstock, NH 03262. The Pierce Lab building has an existing asphalt shingle roof that is approximately 30 years old. The fuel shed also has an asphalt shingle roof of unknown age.
The government shall furnish access to the site between the hours of 7:00AM – 5:00PM on weekdays excluding Federal Holidays. Access to the site may be obtained outside of these hours with permission from the COR.
Contractor Requirements
3.0 Technical Requirements / Tasks
Contactor shall be:
• Experienced in roofing, with a minimum of 5 years of roofing construction experience.
• Licensed in the state of New Hampshire.
• Fully Insured.
4.0 Deliverables / Schedule
Key Deliverables
Item No. Deliverable Objective 1 Mobilization Contractor to mobilize/demobilize any and all equipment required for work.
2 Removal/Disposal of
Existing Pierce Lab Roof
Remove and legally dispose of the asphalt shingle roofing system, underlayment, flashings, fasteners, and other components of existing Pierce Lab roof. Roof is approximately 5,400 square feet.
3 Installation of New Pierce Lab Roofing System
Install new ice/water barrier, synthetic underlayment, architectural shingles, step flashings, pipe/penetration flashings, drip edge, ridge/valley shingles, other appurtenances related to watertight architectural shingle installation on the Pierce Lab roof. Roof area is approximately 5,400 square feet. Contractor shall verify roof dimensions prior to purchasing and installing roofing materials.
Option A Removal/Disposal and Installation of New Roofing System on Fuel Shed
Remove and legally dispose of the asphalt shingle roofing system, underlayment, flashings, fasteners, and other components of the existing fuel shed roof. Install new ice/water barrier, synthetic underlayment, architectural shingles, step flashings, pipe/penetration flashings, drip edge, ridge/valley shingles, other appurtenances related to watertight architectural shingle installation on the fuel shed roof. Roof is approximately 220 square feet. Contractor shall verify roof dimensions prior to purchasing and installing roofing materials.
Option B Replacement of Damaged Sheathing
Remove and legally dispose of damaged sheathing. This shall be paid as an actual quantity, to the nearest whole square foot of actual sheathing replaced. Existing sheathing is 5/8” plywood. Sheathing shall be replaced in-kind
Photo 1: Pierce Lab Building Front
Photo 2: Pierce Lab Building Rear
Photo 3: Fuel Shed
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Deliverables / Schedule |
File details come from the government source that posted it. Updated .