About this file

This document contains a federal contract modification and related permits. The modification is for solicitation number 12445523B0009 to replace an existing 15-foot timber bridge with a new 18-foot timber bridge over Poplar Creek in Wexford County, Michigan. The USDA Forest Service has secured the necessary Part 301, Part 303 and Part 31 permits from the Michigan Department of Environment, Great Lakes, and Energy for the project. Bids are due by the hour and date specified in the solicitation, with acknowledgment of any amendments required prior to the due date. The contractor must adhere to all permit conditions, including work windows, erosion control measures, and disposal of dredged materials.

View the file

Other files for this federal contract opportunity

Other files attached to Poplar Creek Bridge Replacement, newest first.
File Type Posted
Solicitation Body 12445523B0009 Amended 9-12-23.pdf PDF
Solicitation 12445523B0009 Amended 9_7_23.pdf PDF
12445523B0009_SF30 Amendment 1.pdf PDF
Poplar Bridge_Construction_IFB_12445523B0009.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12445523B0009 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ATLANTA GA 30309-2449

STE 876S

1720 PEACHTREE ST NW

USDA-FS CSA EAST 13

GAOA08/29/20230003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/29/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of amendment 3 is to do the following:

1. Provide a response to the following question: "Section 157 SESC - Is the successful bidder/Contractor responsible for securing Part 301, Part 303 and Part 31 permits? Or is the USDA project either exempt from the permits, or has USDA already secured the permits?"

RESPONSE: The USDA Forest Service HAS secured the permits for the project. See attached for permits.

No other changes apply.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

CAROL D. NORTHROP

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12445523B0009/0003

Period of Performance: 01/29/2024 to 07/26/2024

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

This notice must be displayed at the site of work.

Laminating this notice or utilizing sheet protectors is recommended.

Please refer to the above permit number with any questions or concerns.

NOTICE OF AUTHORIZATION

Permit Number: WRP038675 v. 1 Date Issued: August 25, 2023 Site Name: 83-Henderson Twp-Wexford County Expiration Date: August 25, 2028

The Michigan Department of Environment, Great Lakes, and Energy (EGLE), Water Resources Division, P.O. Box 30458, Lansing, Michigan 48909-7958, under provisions of the Natural Resources and Environmental Protection Act, 1994 PA 451, as amended; specifically:

Part 31, Floodplain Regulatory Authority of the Water Resources Protection.

Part 301, Inland Lakes and Streams.

Part 303, Wetlands Protection.

Part 315, Dam Safety.

Part 323, Shorelands Protection and Management.

Part 325, Great Lakes Submerged Lands.

Part 353, Sand Dunes Protection and Management.

Authorized activity:

At 44.1804, -85.6439, in Wexford County, Michigan 49601, remove an existing 15-foot-long by 20-foot-span by 5.07-foot-rise timber bridge and construct a new 18-foot-long by 32-foot-span by 6.35-foot-rise timber bridge. Place 105 cubic yards of riprap along the abutments and along the upstream portion of the stream bank. All work shall be completed in accordance with the approved plans dated August 23, 2023, and the specifications of this permit.

To be conducted at property located in: Wexford County, Waterbody: Poplar Creek Section 28, Town 21N, Range 11W, Henderson Township

Permittee:

Jeff Rypka US Forest Service 8901 Grand Avenue Duluth, Minnesota 55808

Keenan Cooper Cadillac District Office Water Resources Division 989-370-7350

EGLE

WRP038675 v1.0

Approved Issued On:08/25/2023

Expires On:08/25/2028

Digitally signed by: Keenan Cooper DN: CN = Keenan Cooper email = CooperK9@michigan.gov C = US

O = WRD OU = EGLE

Date: 2023.08.25 14:23:01 -04'00'

Keenan Cooper

MICHIGAN DEPARTMENT OF ENVIRONMENT, GREAT LAKES, AND ENERGY

WATER RESOURCES DIVISION

GENERAL PERMIT AUTHORIZATION

Issued To:

Jeff Rypka US Forest Service 8901 Grand Avenue Duluth, Minnesota 55808

Permit No.: WRP038675 v.1 Submission No.: HPS-AYTR-VNZH9 Site Name: 83-Henderson Twp-Wexford County Issued: August 25, 2023 Expires: August 25, 2028

This permit is being issued by the Michigan Department of Environment, Great Lakes, and Energy (EGLE), Water Resources Division (WRD), under the provisions of the Natural Resources and Environmental Protection Act, 1994 PA 451, as amended (NREPA); specifically:

Part 301, Inland Lakes and Streams Part 323, Shorelands Protection and Management Part 303, Wetlands Protection Part 325, Great Lakes Submerged Lands Part 315, Dam Safety Part 353, Sand Dunes Protection and Management Part 31, Water Resources Protection (Floodplain Regulatory Authority)

EGLE certifies that the activities authorized under this permit are in compliance with the State Coastal Zone Management Program and certifies without conditions under the Federal Clean Water Act, Section 401 that the discharge from the activities authorized under this permit will comply with Michigan’s water quality requirements in Part 31, Water Resources Protection, of the NREPA and associated administrative rules, where applicable.

Permission is hereby granted, based on permittee assurance of adherence to State of Michigan requirements and permit conditions, to:

Authorized Activity:

At 44.1804, -85.6439, in Wexford County, Michigan 49601, remove an existing 15-foot-long by 20-foot-span by 5.07-foot-rise timber bridge and construct a new 18-foot-long by 32-foot-span by 6.35-foot-rise timber bridge. Place 105 cubic yards of riprap along the abutments and along the upstream portion of the stream bank. All work shall be completed in accordance with the approved plans dated August 23, 2023, and the specifications of this permit.

Waterbody Affected: Poplar Creek Property Location: Wexford County, Henderson Township, Town/Range/Section

21N11W28, Property Tax No. N/A

WRP038675 v1.0 Approved

Issued On:08/25/2023 Expires On:08/25/2028

Jeff Rypka, US Forest Service 2 WRP038675 v.1

Authority granted by this permit is subject to the following limitations:

A. Initiation of any work on the permitted project confirms the permittee's acceptance and agreement to comply with all terms and conditions of this permit.

B. The permittee, in exercising the authority granted by this permit, shall not cause unlawful pollution as defined by Part 31 of the NREPA.

C. This permit shall be kept at the site of the work and available for inspection at all times during the duration of the project or until its date of expiration.

D. All work shall be completed in accordance with the approved plans and specifications submitted with the application and/or plans and specifications attached to this permit.

E. No attempt shall be made by the permittee to forbid the full and free use by the public of public waters at or adjacent to the structure or work approved.

F. It is made a requirement of this permit that the permittee give notice to public utilities in accordance with

2013 PA 174 (Act 174) and comply with each of the requirements of Act 174.

G. This permit does not convey property rights in either real estate or material, nor does it authorize any injury to private property or invasion of public or private rights, nor does it waive the necessity of seeking federal assent, all local permits, or complying with other state statutes.

H. This permit does not prejudice or limit the right of a riparian owner or other person to institute proceedings in any circuit court of this state when necessary to protect his rights.

I. Notification of project completion and digital photos of the completed project shall be e-mailed to CooperK9@michigan.gov within 30 days of completion of the project. Staff will use photos to assist in monitoring compliance with your permit.

J. This permit shall not be assigned or transferred without the written approval of EGLE.

K. Failure to comply with conditions of this permit may subject the permittee to revocation of permit and criminal and/or civil action as cited by the specific state act, federal act, and/or rule under which this permit is granted.

L. All dredged or excavated materials shall be disposed of in an upland site (outside of floodplains, unless exempt under Part 31 of the NREPA, and wetlands).

M. In issuing this permit, EGLE has relied on the information and data that the permittee has provided in connection with the submitted application for permit. If, subsequent to the issuance of a permit, such information and data prove to be false, incomplete, or inaccurate, EGLE may modify, revoke, or suspend the permit, in whole or in part, in accordance with the new information.

N. The permittee shall indemnify and hold harmless the State of Michigan and its departments, agencies, officials, employees, agents, and representatives for any and all claims or causes of action arising from acts or omissions of the permittee, or employees, agents, or representative of the permittee, undertaken in connection with this permit. The permittee's obligation to indemnify the State of Michigan applies only if the state: (1) provides the permittee or its designated representative written notice of the claim or cause of action within 30 days after it is received by the state, and (2) consents to the permittee's participation in the proceeding on the claim or cause of action. It does not apply to contested case proceedings under the Administrative Procedures Act, 1969 PA 306, as amended, challenging the permit. This permit shall not be construed as an indemnity by the State of Michigan for the benefit of the permittee or any other person.

O. Noncompliance with these terms and conditions and/or the initiation of other regulated activities not specifically authorized shall be cause for the modification, suspension, or revocation of this permit, in whole or in part. Further, EGLE may initiate criminal and/or civil proceedings as may be deemed necessary to correct project deficiencies, protect natural resource values, and secure compliance with statutes.

P. If any change or deviation from the permitted activity becomes necessary, the permittee shall request, in writing, a revision of the permitted activity from EGLE. Such revision request shall include complete documentation supporting the modification and revised plans detailing the proposed modification.

Proposed modifications must be approved, in writing, by EGLE prior to being implemented.

Q. This permit may be transferred to another person upon written approval of EGLE. The permittee must submit a written request to EGLE to transfer the permit to the new owner. The new owner must also submit a written request to EGLE to accept transfer. The new owner must agree, in writing, to accept all ept allept all

WRP038675 v1.0 Approved

Jeff Rypka, US Forest Service 3 WRP038675 v.1 conditions of the permit. A single letter signed by both parties that includes all the above information may be provided to EGLE. EGLE will review the request and, if approved, will provide written notification to the new owner.

R. Prior to initiating permitted construction, the permittee is required to provide a copy of the permit to the contractor(s) for review. The property owner, contractor(s), and any agent involved in exercising the permit are held responsible to ensure that the project is constructed in accordance with all drawings and specifications. The contractor is required to provide a copy of the permit to all subcontractors doing work authorized by the permit.

S. Construction must be undertaken and completed during the dry period of the wetland. If the area does not dry out, construction shall be done on equipment mats to prevent compaction of the soil.

T. does not waive permit requirements under the authority of Part 305, Natural Rivers, of the NREPA. A Natural Rivers Zoning Permit may be required for construction, land alteration, streambank stabilization, or vegetation removal along or near a natural river.

U. The permittee is cautioned that grade changes resulting in increased runoff onto adjacent property is subject to civil damage litigation.

V. Unless specifically stated in this permit, construction pads, haul roads, temporary structures, or other structural appurtenances to be placed in a wetland or on bottomland of the water body are not authorized and shall not be constructed unless authorized by a separate permit or permit revision granted in accordance with the applicable law.

W. For projects with potential impacts to fish spawning or migration, no work shall occur within fish spawning or migration timelines (i.e., windows) unless otherwise approved in writing by the Michigan Department of Natural Resources, Fisheries Division.

X. Work to be done under authority of this permit is further subject to the following special instructions and specifications:

1. Authority granted by this permit does not waive permit or program requirements under Part 91 of the

NREPA or the need to acquire applicable permits from the CEA. To locate the Soil Erosion Program Administrator for your county, visit https://www.michigan.gov/egle/about/organization/water-resources/soil-erosion/sesc-overview and select “Soil Erosion and Sedimentation Control Agencies”.

2. The authority to conduct the activity as authorized by this permit is granted solely under the provisions of the governing act as identified above. This permit does not convey, provide, or otherwise imply approval of any other governing act, ordinance, or regulation, nor does it waive the permittee's obligation to acquire any local, county, state, or federal approval or authorization necessary to conduct the activity.

3. No fill, excess soil, or other material shall be placed in any wetland, floodplain, or surface water area not specifically authorized by this permit, its plans, and specifications.

4. This permit does not authorize or sanction work that has been completed in violation of applicable federal, state, or local statutes.

5. The permit placard shall be kept posted at the work site in a prominent location at all times for the duration of the project or until permit expiration.

6. This permit is being issued for the maximum time allowed and no extensions of this permit will be granted. Initiation of the construction work authorized by this permit indicates the permittee's acceptance of this condition. The permit, when signed by EGLE, will be for a five-year period beginning on the date of issuance. If the project is not completed by the expiration date, a new permit must be sought.

7. The structure/bridge shall span the bank full width of the stream with the lowest bottom of beam elevation at or above the natural ground elevations on each bank. The approach fill shall slope to natural ground elevations within ten (10) feet of either end of the structure.

8. All dredge/excavated spoils including organic and inorganic soils, vegetation, and other material removed shall be placed on upland (non-wetland, non-floodplain or non-bottomland), prepared for stabilization, and revegetated and reseeded with native Michigan species appropriate to the site and mulched in such a manner so as to prevent and ensure against erosion of any material into any waterbody, wetland, or floodplain.

9. During removal or repair of the existing structure, every precaution shall be taken to prevent debris from entering any watercourse. Any debris reaching the watercourse during the removal and/or EGLE

WRP038675 v1.0 Approved

Jeff Rypka, US Forest Service 4 WRP038675 v.1 reconstruction of the structure shall be immediately retrieved from the water. All material shall be disposed of in an acceptable manner consistent with local, state, and federal regulations.

10. Prior to the removal of the existing structures, cofferdams of steel sheet piling, gravel bags, clean stone, coarse aggregate, concrete or other acceptable barriers shall be installed to isolate all construction activity from the water. The barriers shall be maintained in good working order throughout the duration of the project. Upon project completion, the accumulated materials shall be removed and disposed of at an upland site.

11. All cofferdam and temporary steel sheet pile shall then be removed in its entirety, unless specifically shown to be left in plan on the accepted plans. Cofferdam and sheet pile that is left in place shall be cut off at the elevation shown on the plans and shall be a minimum of one foot below the stream bottom.

12. Road fill side slopes terminating in the stream and any raw streambanks resulting from the construction, shall be stabilized with temporary measures in accordance with appropriate Best Management Practices based on site conditions, and if necessary, may be riprapped extending above the ordinary high water mark, before or upon commencement of the permitted activity.

Temporary stabilization measures shall be maintained until permanent measures are in place.

13. All other road fill slopes, ditches, and other raw areas draining directly to the stream may be protected with riprap, sod and/or seed and mulch as may be necessary to provide effective erosion protection. The placement of riprap shall be limited to the minimum necessary to ensure proper stabilization of the side slopes and fill in the immediate vicinity of the structure.

14. If the project, or any portion of the project, is stopped and lies incomplete for any length of time (other than that encountered in a normal work week) every precaution shall be taken to protect the incomplete work from erosion, including the placement of temporary gravel bag riprap, temporary seeding and mulching, or other acceptable temporary protection.

15. No work shall be done in the stream during periods of above-normal flows except as necessary to prevent erosion.

Issued By:

Keenan Cooper Cadillac District Office Water Resources Division 989-370-7350

THIS GENERAL PERMIT AUTHORIZATION MUST BE SIGNED BY THE PERMITTEE TO BE VALID.

I hereby assure that I have read, am familiar with, and agree to adhere to the terms and conditions of this authorization.

Permittee Signature Date kc/sh Attachment cc: Henderson Township Clerk

Wexford County SESC Brian Bury, DNR Natural Rivers

EGLE

WRP038675 v1.0

Approved Issued On:08/25/2023

Expires On:08/25/2028

Digitally signed by: Keenan Cooper DN: CN = Keenan Cooper email = CooperK9@michigan.

gov C = US O = WRD OU = EGLE Date: 2023.08.25 14:23:26 -04'00'

Keenan Cooper

File details come from the government source that posted it. Updated .