Amendment 0001 (220526).pdf

PDF 88 KB Posted

Attached to
Tofte Fire/Timber Vehicle Garage Federal contract opportunity
Solicitation number
12445522R0007
Issued by
Department of Agriculture Forest Service

About this file

This document contains an amendment to a solicitation for the Tofte fire/timber vehicle garage project. The amendment provides responses to vendor questions seeking clarification on HVAC plans and electrical service details. For the bathroom and exercise room vent fans, the amendment specifies that the fans will need to be vented independently and preferably out the sidewalls. Regarding the site plan, the amendment discloses that the tree cooler has a 100-amp service box, the fuel shed had a single 20-amp breaker, and no additional information is available on panel sizing for the new fire garage. The period of performance for the project is July 5, 2022 through November 4, 2022.

View the file

Other files for this federal contract opportunity

Other files attached to Tofte Fire/Timber Vehicle Garage, newest first.
File Type Posted
Amendment 0003 (220613).pdf PDF
Amendment 0002 (220531).pdf PDF
12445522R0007.pdf PDF
J-2 Plans.pdf PDF
J-3 Wage Determination (220225).pdf PDF
J-1 Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12445522R0007 x x

0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ATLANTA GA 30309-2449

STE 876S

1720 PEACHTREE ST NW

USDA-FS CSA EAST 13

04/28/20220001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

04/28/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Questions from Vendors

Q: (1) Are there any additional HVAC Plans? As I didn't see where the bathroom fan is venting in DWG Sheet No. 17-- Hydronic Radiant Heat and it is not also reflected in DWG

Sheet No. 18 -- Lighting & Receptacle Plan. (2) Is the fan in the exercise room the same fan as in the bathroom? If so, where does that vent to?

A: The vent fans for both rooms will need to be vented independent and preferably vented out the sidewall.

Q: I had a few question on the site plan. It says that we need new underground power to the

Tree shed now do we know how big of panel I am reconnecting the same goes for Oil House I

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

CLARK A. BARTELT

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12445522R0007/0001 don¿t know the size of the service for these. The main service coming into the new fire Garage does not say what size panel is required. Do you have any information on this.

A: The Tree cooler has a 100A service box and the

Fuel shed had a single 20A Breaker.

Period of Performance: 07/05/2022 to 11/04/2022