12445522Q0191 0001 MOF Cranberry Mountain Roof.pdf
PDF 567 KB Posted
- Solicitation number
- 12445522Q0191
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12445522Q0191 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
64R4
ROLLA MO 65401
401 FAIRGROUNDS ROAD
MARK TWAIN NATIONAL FOREST
ATLANTA GA 30309-2449
STE 876S
1720 PEACHTREE ST NW
USDA-FS CSA EAST 13
09/06/20220001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
09/06/2022
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Period of Performance: 10/03/2022 to 11/30/2022
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
JOHN V. SWIZDOR
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Amended to include an updated Specifications attachment and provide Pre-Bid Q&A.
16SEP2022
SECTION 011000 - SUMMARY
SECTION 070150.19 - PREPARATION FOR REROOFING
SECTION 073113 - ASPHALT SHINGLES
SECTION 077100 - ROOF SPECIALTIES
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Phased construction.
4. Work under Owner's separate contracts.
5. Owner-furnished/Contractor-installed (OFCI) products.
6. Contractor's use of site and premises.
7. Coordination with occupants.
8. Work restrictions.
9. Specification and Drawing conventions.
1.2 PROJECT INFORMATION
A. Project Identification: CMNC Roof Replacement Project.
1. Project Location: Cranberry Mountain Nature Center, Pocahontas County WV.
B. Owner: USDA Forest Service.
1. Contracting Officer’s Representative (COR): Jacob Hise (Jacob.Hise@usda.gov).
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Removal and disposal of existing roof, and replacement of roof (architectural shingles), underlayment, drip edge, gutter, flashing, ridge cap, etc. at the Cranberry Mountain Nature Center (CMNC) The above listed items and other Work indicated in the Contract Documents.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.4 CONTRACTOR'S USE OF SITE AND PREMISES
A. Restricted Use of Site: Contractor shall have limited use of Project site for construction operations as indicated in the attached documents.
B. Limits on Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits on Use of Site: Confine construction operations to areas immediately in the area of work, unless otherwise approved by the COR.
2. Driveways, Walkways, and Entrances: Keep driveways, garage, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials. Location for materials and Contractor designated parking to be coordinated with the COR.
C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations. Contractor responsible for repairing any weather-related damages (rain, snow, wind, etc.) to roof sheathing or other parts of the building during construction activities.
D. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
1.5 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and existing building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
1.6 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Working Hours shall be 7:00AM-7:00PM, unless otherwise approved by
COR. No work shall be done on weekends or Federal Holidays without written approval of the Contracting Officer. Hours that the facility are open to the public for recreation: Thursday- Monday 9:00AM-4:00PM.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify COR not less than two days in advance of proposed utility interruptions.
2. Obtain COR’s written permission before proceeding with utility interruptions.
D. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.
1. Notify COR not less than two days in advance of proposed disruptive operations.
2. Obtain COR’s written permission before proceeding with disruptive operations.
E. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances on Owner's property is not permitted.
1.7 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.
3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.
4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SELECTIVE DEMOLITION
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:
1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping.
Temporarily cover openings to remain.
2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
3. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
4. Dispose of demolished items and materials promptly.
B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by COR, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
END OF SECTION 011000
SECTION 070150.19 - PREPARATION FOR REROOFING
1. Full tear-off of entire roof system.
2. Re-cover preparation of entire roof area.
3. Removal of flashings and counterflashings.
1.2 ALLOWANCES
A. Any discovery of existing deteriorated wood roof deck, existing deteriorated wood nailers and curbs should be immediately brought to the attention of the COR. No work shall be paid for without prior approval from the CO.
1.3 PREINSTALLATION MEETINGS
A. Preliminary Roofing Conference: Before starting removal Work, conduct pre-construction meeting at Project site.
1.4 INFORMATIONAL SUBMITTALS
A. Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including exterior and interior finish surfaces, that might be misconstrued as having been damaged by reroofing operations.
1. Submit before Work begins.
1.5 FIELD CONDITIONS
A. Existing Roofing System: Asphalt Shingle roofing.
B. Owner will occupy portions of building immediately below reroofing area.
1. Conduct reroofing so Owner's operations are not disrupted.
2. Provide Owner with not less than 72 hours' written notice of activities that may affect Owner's operations.
C. Protect building to be reroofed, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from reroofing operations.
D. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
E. Conditions existing at time of inspection for bidding will be maintained by Owner as far as practical.
F. Weather Limitations: Proceed with reroofing preparation only when existing and forecasted weather conditions permit Work to proceed without water entering existing roofing system or building.
1. Remove only as much roofing in one day as can be made watertight in the same day.
Contractor responsible for repairing any weather-related damages (rain, snow, wind, etc.)
to roof sheathing or other parts of the building during construction activities.
PART 2 - PRODUCTS
3.1 PREPARATION
A. Seal or isolate windows that may be exposed to airborne substances created in removal of existing materials.
B. Coordinate with Owner to shut down air-intake equipment in the vicinity of the Work.
1. Cover air-intake louvers before proceeding with reroofing work that could affect indoor air quality or activate smoke detectors in the ductwork.
C. During removal operations, have sufficient and suitable materials on-site to facilitate rapid installation of temporary protection in the event of unexpected rain.
3.2 ROOF TEAR-OFF
A. Notify Owner each day of extent of roof tear-off proposed for that day and obtain COR authorization to proceed.
B. Full Roof Tear-off: Remove existing roofing and other roofing system components down to the existing sheathing.
1. Remove existing shingles and underlayment.
2. Remove perimeter edge flashing.
3. Remove flashings at pipes, curbs, mechanical equipment, and other penetrations and remove selected vents identified in the SOW Attachment.
4. Remove fasteners from deck.
3.3 DECK PREPARATION
A. Inspect deck after tear-off of roofing system.
B. If deck surface is unsuitable for receiving new roofing or if structural integrity of deck is suspect, immediately notify COR.
1. Do not proceed with installation until directed by CO.
2. Any damaged sheathing not suitable for shingling over will be replaced with like materials at the line item rate listed in the Schedule based on whole board dimensions, i.e.
4'x8' sheet would be calculated at 32 sq ft. or a 1"x6"x10' would be calculated at 5 sq ft depending on the existing material.
END OF SECTION 070150.19
SECTION 073113 - ASPHALT SHINGLES
1.1 SUMMARY
A. Section Includes:
1. Glass-fiber-reinforced asphalt shingles.
2. Underlayment materials.
3. Ridge vents.
4. Metal flashing and trim.
1.2
PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.3
ACTION SUBMITTALS
A. Product Data: For the following:
1. Asphalt shingles.
2. Underlayment materials.
3. Ridge caps/vents.
4. Asphalt roofing cement.
5. Elastomeric flashing sealant.
B. Shop Drawings: For metal flashing and trim.
C. Samples: For each exposed product and for each color and blend specified.
1.4
INFORMATIONAL SUBMITTALS
A. Product test reports.
B. Research reports for synthetic underlayment.
C. Sample warranty.
1.5
CLOSEOUT SUBMITTALS
A. Maintenance data.
1.6 QUALITY ASSURANCE
A. Installer Qualifications: An installer which meets the requirements of the roofing materials manufacturer to maintain owner eligibility for the manufacturer’s standard warranty.
1.7 WARRANTY
A. Materials Warranty: Manufacturer agrees to repair or replace asphalt shingles that fail within specified warranty period.
1. Materials Warranty Period: A minimum of 30 years from the date of Substantial
Completion during a portion of which the warranty may be prorated, with a minimum of the first 5 years non-prorated.
2. Wind-Speed Warranty Period: Asphalt shingles will resist blow-off or damage caused by wind speeds of up to 110 mph (49 m/s) for five years from date of Substantial Completion.
3. Workmanship Warranty Period: Two years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Exterior Fire-Test Exposure: Provide asphalt shingles and related roofing materials identical to those of assemblies tested for Class A fire resistance in accordance with ASTM E108 or UL 790 by Underwriters Laboratories or another testing and inspecting agency acceptable to authorities having jurisdiction. Identify products with appropriate markings of applicable testing agency.
B. Wind Resistance: Provide asphalt shingles that comply with requirements of ASTM
D3161/D3161M, Class F, and with ASTM D7158/D7158M, Class H.
2.2 GLASS-FIBER-REINFORCED ASPHALT SHINGLES
A. Laminated-Strip Asphalt Shingles: ASTM D3462/D3462M, laminated, multi-ply overlay construction; glass-fiber reinforced, mineral-granule surfaced, and self-sealing.
1. Manufacturers: Subject to compliance with requirements, provide products by the following or provide submittal with color options and warranty information with your quote:
a. Owens Corning.
1) Oak Ridge Series
2. Butt Edge: Straight cut.
3. Strip Size: Manufacturer's standard.
4. Algae Resistance: Granules resist algae discoloration.
5. Color and Blends: “Brownwood”
B. Hip and Ridge Shingles: Manufacturer's standard units to match asphalt shingles.
2.3 UNDERLAYMENT MATERIALS
A. Synthetic Underlayment: UV-resistant polypropylene, polyolefin, or polyethylene polymer fabric with surface coatings or treatments to improve traction underfoot and abrasion resistance;
evaluated and documented to be suitable for use as a roof underlayment under applicable codes by a testing and inspecting agency acceptable to authorities having jurisdiction.
1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:
a. Certainteed; SAINT-GOBAIN.
b. GAF.
c. Owens Corning.
2.4 RIDGE VENTS
A. Rigid Ridge Cap/Vent: Manufacturer's standard, rigid-section, high-density, UV-stabilized plastic ridge vent for use under ridge shingles.
1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following or provide submittal with color options and warranty information with your quote:
a. Owens Corning.
2. Width: Manufacturers Standard.
3. Thickness: Manufacturers Standard.
2.5 ACCESSORIES
A. Asphalt Roofing Cement: ASTM D4586/D4586M Type II, asbestos free.
B. Elastomeric Flashing Sealant: ASTM C920, Type S, Grade NS, one-part, non-sag, elastomeric polymer sealant; of class and use classifications required to seal joints and remain watertight;
recommended in writing by manufacturer for installation of flashing systems.
C. Roofing Nails: ASTM F1667, aluminum, stainless steel, copper, or hot-dip galvanized-steel wire shingle nails, minimum 0.120-inch- (3-mm-) diameter, sharp-pointed, with a 3/8- to 7/16-inch- (10- to 11-mm-) diameter flat head and of sufficient length to penetrate 3/4 inch (19 mm) into solid wood decking or extend at least 1/8 inch (3 mm) through sheathing less than 3/4 inch (19
mm) thick.
1. Where nails are in contact with metal flashing, use nails made from same metal as flashing.
D. Underlayment Nails: Aluminum, stainless steel, or hot-dip galvanized-steel wire nails with low-profile metal or plastic caps, 1-inch- (25-mm-) minimum diameter.
1. Provide with minimum 0.0134-inch- (0.34-mm-) thick metal cap, 0.010-inch- (0.25-mm-) thick power-driven metal cap, or 0.035-inch- (0.89-mm-) thick plastic cap; and with minimum 0.083-inch- (2.11-mm-) thick ring shank or 0.091-inch- (2.31-mm-) thick smooth shank of length to penetrate at least 3/4 inch (19 mm) into roof sheathing or to penetrate through roof sheathing less than 3/4 inch (19 mm) thick.
2.6 METAL FLASHING AND TRIM
B. Utilize pre-fabricated or fabricate sheet metal flashing and trim to comply with recommendations in SMACNA's "Architectural Sheet Metal Manual" that apply to design, dimensions, metal, and other characteristics of the item unless otherwise indicated on Drawings.
1. Vent-Pipe Flashings: Vent Pipes should be flashed with appropriate metal or rubber boot and collar and extending at least 4 inches (102 mm) from pipe onto roof to prevent water intrusion.
3.1 INSTALLATION OF UNDERLAYMENT MATERIALS
A. Comply with asphalt shingle and underlayment manufacturers' written installation instructions and with recommendations in NRCA's "The NRCA Roofing Manual: Steep-Slope Roof Systems" applicable to products and applications indicated unless more stringent requirements are specified in this Section or indicated on Drawings.
B. Synthetic Underlayment:
1. Install on roof deck parallel with and starting at the eaves.
a. Lap sides and ends as recommended in writing by manufacturer, but not less than 4 inches (102 mm) for side laps and 6 inches (152 mm) for end laps.
b. Stagger end laps between succeeding courses at interval recommended in writing by manufacturer, but not less than 72 inches (1829 mm).
c. Fasten with underlayment nails in accordance with manufacturer's written instructions.
d. Cover underlayment within period recommended in writing by manufacturer.
2. Install in single layer on roofs sloped at 4:12 and greater.
3. Install in double layer on roofs sloped at less than 4:12.
4. Install synthetic underlayment on roof deck not covered by self-adhering, polymer-modified bitumen sheet unless otherwise specified in this Section or indicated on Drawings.
a. Lap sides of underlayment over self-adhering sheet not less than 4 inches (102 mm) in direction to shed water.
b. Lap ends of underlayment not less than 6 inches (152 mm) over self-adhering sheet.
5. Install fasteners in a grid pattern of 12 inches (305 mm) between side laps with 6-inch (152-
mm) spacing at side and end laps.
6. Terminate synthetic underlayment flush against sidewalls, curbs, chimneys, and other roof projections.
C. Metal-Flashed, Open-Valley Underlayment: Install two layers of minimum 36-inch- (914-mm-) wide underlayment centered in valley.
1. Use same underlayment as installed on field of roof.
2. Stagger end laps between layers at least 72 inches (1829 mm).
3. Lap ends of each layer at least 12 inches (305 mm) in direction that sheds water, and seal with asphalt roofing cement.
4. Fasten each layer to roof deck with underlayment nails located as far from valley center as possible and only to extent necessary to hold underlayment in place until installation of valley flashing.
5. Lap roof-deck underlayment over first layer of valley underlayment at least 6 inches (152 mm).
3.2 INSTALLATION OF METAL FLASHING AND TRIM
A. Install metal flashings and trim to comply with requirements in Section 076200 "Sheet Metal Flashing and Trim."
1. Install metal flashings in accordance with recommendations in NRCA's "NRCA
Guidelines for Asphalt Shingle Roof Systems."
2. Bed flanges of metal flashings using asphalt roofing cement or elastomeric flashing sealant.
B. Pipe Flashings: Form flashing around pipe penetrations and asphalt shingles. Fasten and seal to asphalt shingles as recommended by manufacturer.
3.3 INSTALLATION OF ASPHALT SHINGLES
A. Install asphalt shingles in accordance with manufacturer's written instructions and recommendations in NRCA's "NRCA Guidelines for Asphalt Shingle Roof Systems."
B. Install starter strip along lowest roof edge, consisting of an asphalt shingle strip with tabs removed at least 7 inches (178 mm) wide with self-sealing strip face up at roof edge.
1. Extend asphalt shingles 3/4 inch (19 mm) over fasciae at eaves and rakes.
2. Install starter strip along rake edge.
C. Install first and remaining courses of laminated asphalt shingles stair-stepping diagonally across roof deck with manufacturer's recommended offset pattern at succeeding courses, maintaining uniform exposure.
E. Fasten asphalt shingle strips with a minimum of four roofing nails, but not less than the number indicated in manufacturer's written instructions for roof slope and design wind speed indicated on Drawings and for warranty requirements specified in this Section.
1. Locate fasteners in accordance with manufacturer's written instructions.
2. When ambient temperature during installation is below 50 deg F (10 deg C), hand seal self-sealing asphalt shingles by applying asphalt roofing cement spots between course overlaps after nailing the upper course.
F. Closed-Cut Valleys: Extend asphalt shingle strips from one side of valley 12 inches (305 mm) beyond center of valley.
1. Use one-piece shingle strips without joints in valley.
2. Fasten with extra nail in upper end of shingle. Install asphalt shingle courses from other side of valley and cut back to a straight line 2 inches (51 mm) short of valley centerline.
3. Trim upper concealed corners of cut-back shingle strips.
4. Do not nail asphalt shingles within 6 inches (152 mm) of valley center.
5. Set trimmed, concealed-corner asphalt shingles in a 3-inch- (76-mm-) wide bed of asphalt roofing cement.
G. Ridge Vents: Install continuous ridge vents over asphalt shingles in accordance with manufacturer's written instructions. Fasten with roofing nails of sufficient length to penetrate sheathing. Match existing configuration of ridge vent/cap utilization.
H. Hip and Ridge Shingles: Maintain same exposure of cap shingles as roofing-shingle exposure.
Lap cap shingles at ridges to shed water away from direction of prevailing winds.
1. Fasten with roofing nails of sufficient length to penetrate sheathing.
2. Fasten ridge cap asphalt shingles to cover ridge vent without obstructing airflow.
END OF SECTION 073113
SECTION 077100 - ROOF SPECIALTIES
1. Copings.
2. Roof-edge specialties.
3. Roof-edge drainage systems.
4. Reglets and counterflashings.
B. Preinstallation Conference: Conduct conference at Project site.
1.2
ACTION SUBMITTALS
A. Product Data: For each type of product.
B. Samples: For each type of roof specialty and for each color and texture specified.
1.3
INFORMATIONAL SUBMITTALS
A. Product Test Reports: For tests performed by a qualified testing agency.
B. Sample warranty.
1.4
CLOSEOUT SUBMITTALS
A. Maintenance Data: For roofing specialties to include in maintenance manuals.
1.5
QUALITY ASSURANCE
A. Manufacturer Qualifications: A qualified manufacturer offering products meeting requirements that are FM Approvals listed for specified class.
2.1 PERFORMANCE REQUIREMENTS
A. FM Approvals' Listing: Manufacture and install roof-edge specialties that are listed in FM Approvals' "RoofNav" and approved for windstorm classification, Class 1-
105. Identify materials with FM Approvals' markings.
B. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes to prevent buckling, opening of joints, hole elongation, overstressing of components, failure of joint sealants, failure of connections, and other detrimental effects. Provide clips that resist rotation and avoid shear stress as a result of thermal movements. Base calculations on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss.
1. Temperature Change (Range): 120 deg F (67 deg C), ambient; 180 deg F
(100 deg C), material surfaces.
2.2 ROOF-EDGE DRAINAGE SYSTEMS
A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:
1. ATAS International, Inc.
2. Architectural Products Company.
3. Berger; division of OmniMax International, Inc.
4. Castle Metal Products.
5. OMG Roofing Products; a Division of OMG, Inc., a subsidiary of Steel
Partners Holdings L.P.
6. RDCA; Roof Drainage Components & Accessories.
7. SAF (Southern Aluminum Finishing Company, Inc.).
B. Seamless Gutters: Manufacture Seamless gutters with matching corner units, ends, outlet tubes, and other accessories. Elevate back edge at least 1 inch (25 mm) above front edge. Furnish flat-stock gutter straps, gutter brackets, expansion joints, and expansion-joint covers fabricated from same metal as gutters.
1. Zinc-Coated Steel: Nominal 0.028-inch (0.71-mm) thickness.
2. Aluminum Sheet: 0.032 inch (0.81 mm) thick.
3. Gutter Profile: Style K according to SMACNA's "Architectural Sheet Metal Manual."
4. Corners: Factory mitered and sealed via manufacturers recommendations.
5. Gutter Supports: Manufacturer's standard supports as selected by COR with finish matching the gutters. If there is no standard manufacturer support, use appropriate hidden gutter hangers made of the same material as the guttering.
C. Downspouts: Corrugated rectangular complete with machine-crimped elbows, manufactured from the following exposed metal. Furnish with metal hangers, from same material as downspouts, and anchors.
1. Zinc-Coated Steel: Nominal 0.028-inch (0.71-mm) thickness.
2. Formed Aluminum: 0.032 inch (0.81 mm) thick.
D. Zinc-Coated Steel Finish: Two-coat fluoropolymer.
1. Color: As selected by COR from manufacturer's full range.
E. Aluminum Finish: Two-coat fluoropolymer.
1. Color: As selected by COR from manufacturer's full range.
2.3 MATERIALS
A. Zinc-Coated (Galvanized) Steel Sheet: ASTM A653/A653M, G90 (Z275) coating designation.
B. Aluminum Sheet: ASTM B209 (ASTM B209M), alloy as standard with manufacturer for finish required, with temper to suit forming operations and performance required.
C. Stainless Steel Sheet: ASTM A240/A240M or ASTM A666, Type 304.
D. Copper Sheet: ASTM B370, cold-rolled copper sheet, H00 or H01 temper.
2.4 MISCELLANEOUS MATERIALS
A. Fasteners: Manufacturer's recommended fasteners, suitable for application and designed to meet performance requirements. Furnish the following unless otherwise indicated:
1. Exposed Penetrating Fasteners: Gasketed screws with hex washer heads matching color of sheet metal.
2. Fasteners for Copper Sheet: Copper, hardware bronze, or passivated Series
300 stainless steel.
3. Fasteners for Aluminum: Aluminum or Series 300 stainless steel.
4. Fasteners for Stainless Steel Sheet: Series 300 stainless steel.
5. Fasteners for Zinc-Coated (Galvanized) Steel Sheet: Series 300 stainless steel or hot-dip zinc-coated steel according to ASTM A153/A153M or
ASTM F2329.
B. Elastomeric Sealant: ASTM C920, elastomeric polyurethane or silicone polymer sealant of type, grade, class, and use classifications required by roofing-specialty manufacturer for each application.
C. Butyl Sealant: ASTM C1311, single-component, solvent-release butyl rubber sealant; polyisobutylene plasticized; heavy bodied for hooked-type joints with limited movement.
D. Bituminous Coating: Cold-applied asphalt emulsion complying with ASTM D1187/D1187M.
E. Asphalt Roofing Cement: ASTM D4586, asbestos free, of consistency required for application.
2.5 FINISHES
A. Coil-Coated Galvanized-Steel Sheet Finishes:
1. High-Performance Organic Finish: Prepare, pretreat, and apply coating to exposed metal surfaces to comply with ASTM A755/A755M and coating and resin manufacturers' written instructions.
a. Two-Coat Fluoropolymer: AAMA 621. Fluoropolymer finish containing not less than 70 percent polyvinylidene fluoride (PVDF) resin by weight in color coat.
b. Three-Coat Fluoropolymer: AAMA 621. Fluoropolymer finish containing not less than 70 percent polyvinylidene fluoride (PVDF) resin by weight in both color coat and clear topcoat.
c. Two-Coat Mica Fluoropolymer: AAMA 621. Fluoropolymer finish with suspended mica flakes containing not less than 70 percent polyvinylidene fluoride (PVDF) resin by weight in color coat.
d. Three-Coat Metallic Fluoropolymer: AAMA 621. Fluoropolymer finish with suspended metallic flakes containing not less than 70 percent polyvinylidene fluoride (PVDF) resin by weight in both color coat and clear topcoat.
B. Coil-Coated Aluminum Sheet Finishes:
1. High-Performance Organic Finish: Prepare, pretreat, and apply coating to exposed metal surfaces to comply with coating and resin manufacturers' written instructions.
a. Two-Coat Fluoropolymer: AAMA 2605. Fluoropolymer finish containing not less than 70 percent polyvinylidene fluoride (PVDF) resin by weight in color coat.
b. Three-Coat Fluoropolymer: AAMA 2605. Fluoropolymer finish containing not less than 70 percent polyvinylidene fluoride (PVDF) resin by weight in both color coat and clear topcoat.
c. Two-Coat Mica Fluoropolymer: AAMA 2605. Fluoropolymer finish with suspended mica flakes containing not less than 70 percent polyvinylidene fluoride (PVDF) resin by weight in color coat.
d. Three-Coat Metallic Fluoropolymer: AAMA 2605. Fluoropolymer finish with suspended metallic flakes containing not less than 70 percent polyvinylidene fluoride (PVDF) resin by weight in both color coat and clear topcoat.
2. Clear Anodic Finish: AAMA 611, or thicker.
3. Color Anodic Finish: AAMA 611, or thicker.
C. Copper Sheet Finishes:
1. Non-Patinated Finish: Mill finish.
2. Pre-Patinated Finish: Chemically treated according to ASTM B882.
3.1 INSTALLATION OF UNDERLAYMENT
A. Synthetic Underlayment: Install with adhesive for temporary anchorage to minimize use of mechanical fasteners under roof specialties. Apply in shingle fashion to shed water, with lapped joints of not less than 2 inches (50 mm).
B. Slip Sheet: Install with tape or adhesive for temporary anchorage to minimize use of mechanical fasteners under roof specialties. Apply in shingle fashion to shed water, with lapped joints of not less than 2 inches (50 mm).
3.2 INSTALLATION, GENERAL
A. Install roof specialties according to manufacturer's written instructions. Anchor roof specialties securely in place, with provisions for thermal and structural movement.
Use fasteners, solder, protective coatings, separators, underlayments, sealants, and other miscellaneous items as required to complete roof-specialty systems.
1. Install roof specialties level, plumb, true to line and elevation; with limited oil-canning and without warping, jogs in alignment, buckling, or tool marks.
2. Provide uniform, neat seams with minimum exposure of solder and sealant.
3. Install roof specialties to fit substrates and to result in weathertight performance. Verify shapes and dimensions of surfaces to be covered before manufacture.
4. Torch cutting of roof specialties is not permitted.
5. Do not use graphite pencils to mark metal surfaces.
B. Expansion Provisions: Allow for thermal expansion of exposed roof specialties.
1. Space movement joints at a maximum of 12 feet (3.6 m) with no joints within
18 inches (450 mm) of corners or intersections unless otherwise indicated on Drawings. Movement joint spacing is increased to 50’ for gutter installation.
2. When ambient temperature at time of installation is between 40 and 70 deg F (4 and 21 deg C), set joint members for 50 percent movement each way.
Adjust setting proportionately for installation at higher ambient temperatures.
C. Fastener Sizes: Use fasteners of sizes that penetrate substrate not less than recommended by fastener manufacturer to achieve maximum pull-out resistance.
D. Seal concealed joints with butyl sealant as required by roofing-specialty manufacturer.
E. Seal joints as required for weathertight construction. Place sealant to be completely concealed in joint. Do not install sealants at temperatures below 40 deg F (4 deg C).
F. Soldered Joints: Clean surfaces to be soldered, removing oils and foreign matter. Pre-tin edges of sheets to be soldered to a width of 1-1/2 inches (38 mm); however, reduce pre-tinning where pre- tinned surface would show in completed Work. Tin edges of uncoated copper sheets using solder for copper. Do not use torches for soldering.
Heat surfaces to receive solder and flow solder into joint. Fill joint completely.
Completely remove flux and spatter from exposed surfaces.
3.3 INSTALLATION OF COPING
A. Install cleats, anchor plates, and other anchoring and attachment accessories and devices with concealed fasteners.
B. Anchor copings with manufacturer's required devices, fasteners, and fastener spacing to meet performance requirements.
3.4 INSTALLATION OF ROOF-EDGE SPECIALITIES
A. Install cleats, cants, and other anchoring and attachment accessories and devices with concealed fasteners.
B. Anchor roof edgings with manufacturer's required devices, fasteners, and fastener spacing to meet performance requirements.
3.5 INSTALLATION OF ROOF-EDGE DRAINAGE SYSTEMS
A. Install components to produce a complete roof-edge drainage system according to manufacturer's written instructions. Coordinate installation of roof perimeter flashing with installation of roof- edge drainage system.
B. Gutters: Join and seal gutter lengths. Allow for thermal expansion. Attach gutters to firmly anchored gutter supports spaced not more than 24 inches (610 mm) apart.
Attach ends with rivets and seal with sealant to make watertight. Slope to downspouts with a minimum slope of ¼ inch vertical for every 10 feet of run.
1. Install gutter with expansion joints at locations indicated but not exceeding 50 feet (15.2 m) apart. Install expansion-joint caps.
C. Downspouts: Join sections with manufacturer's standard telescoping joints. Provide hangers with fasteners designed to hold downspouts securely to walls and 1 inch (25
mm) away from walls; locate fasteners at top and bottom and at approximately 60 inches (1500 mm) o.c.
1. Provide elbows at base of downspouts at grade to direct water away from building at CMNC.
2. Connect downspouts to underground drainage system where an original connection exists.
3.6 CLEANING AND PROTECTION
A. Clean exposed metal surfaces of substances that interfere with uniform oxidation and weathering.
B. Clean and neutralize flux materials. Clean off excess solder and sealants.
C. Remove temporary protective coverings and strippable films as roof specialties are installed.
END OF SECTION 077100
12445522Q0191 MOF Cranberry Mountain Nature Center Roofing– Pre-Bid Questions and Answers
1. Will buildings on the site other than the Cranberry Mountain Nature Center (CMNC) be re-roofed in this project?
a. No, this project is for roof replacement on the Cranberry Mountain Nature Center itself.
2. Will the only guttering installation be to replace the existing gutters?
a. Yes, this project is only to replace the gutters already existing on the CMNC. No gutters should be installed that does not replace guttering already existing.
3. What size gutter will be used to replace the existing guttering?
a. 5 inch seamless guttering meeting the specifications in the contract documents shall be installed to replace the existing guttering.
4. What gutter hangers will be used for this project?
a. Manufacturer's standard supports as selected by COR with finish matching the gutters. If there is no standard manufacturer support, use appropriate hidden gutter hangers made of the same material as the guttering.
5. What color shall the gutters be?
a. The COR shall make the final color selection. In general, it should closely match existing.
6. What shingles shall be used?
a. Owens Corning – Oakridge Series – Brownwood color or COR pre-approved equivalent.
7. Will the fascia or soffit be replaced as part of this project?
a. No fascia or soffit should be replaced as part of this project. Contractor should notify the COR if rotten or damaged fascia or soffit is discovered.
8. What vents will be removed from the roof as part of the project?
a. 2 large metal vents described and pictured in the SOW shall be removed as part of this project. All other vents shall remain and be flashed around in a manner complying with the specifications.
9. Was the pre-bid mandatory?
a. No, the pre-bid meeting was not mandatory.
10. When is the CMNC open to the public?
a. Thursdays-Mondays 9am-4pm.
11. Will the copper drain pipe at the front (parking lot side) entrance to the CMNC be removed and replaced as well?
a. No, the copper pipe shall not be removed as part of this project. The guttering above the door and a section of the downspout shall be replaced. The installation of the replacement gutter shall include a watertight connection to the copper drainpipe by one of the following methods: soldering, cementing, or by using a section of the current downspout already connected to the copper drainpipe. The connection must be watertight.
12. How big is the roof?
a. The SOW states the roof is approximately 6700 square feet.
13. Is there cell service at the site?
a. There is no cell service at the site, but public Wi-Fi is available.
14. What are the working hours at the site?
a. The specifications show working hours of 7am-7pm Monday-Friday unless otherwise approved by COR. CO permission would be required to work weekends or Federal holidays.
| 12445522Q0191 |
| CMNC Roofing Specifications - Updated 9.15.22 |
| CMNC Roofing Pre-Bid Q+A & Attendance Sheet - 9.13.22 |
| Pre-Bid Q+A - Gauley Storage Const. |
| CMNC Roofing Pre-Bid Attendance Sheet - 9.13.22 |
File details come from the government source that posted it. Updated .