Past Performance Questionnaire.docx

DOCX document 17 KB Posted

Attached to
Green Mountain/Finger Lakes Supervisor’s Office Building
Solicitation number
12445521R0001
Issued by

About this file

This solicitation requests proposals for the design and construction of a new office building and optional storage garage for the Green Mountain National Forest. The firm fixed price contract seeks to construct an approximately 11,550 square foot two-story office building and 3,365 square foot unheated garage at the future Supervisor's Office site located in Mendon, Vermont for between $5 million and $7 million. The project has a NAICS code of 236220 with a small business size standard of $39.5 million and is set aside 100% for small businesses. The selected offeror must be registered in SAM and have completed online representations and certifications to receive award. The scope of work includes design, construction, and completion of the buildings between July 2021 and June 2022. Proposals are due by the Department of Agriculture Forest Service.

View the file

Other files

File Type Posted
12445521R0001 Vol. 1 of 2 final.pdf PDF
12445521R0001 Vol. 2 of 2 final.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Past Performance Questionnaire

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

E (EXCELLENT) – Performance meets contractual requirements and exceeds the Government’s expectations. The contractual performance of the element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

(HIGH CONFIDENCE)

G (GOOD) – Performance meets contractual requirements and exceeds some requirements to the Government’s benefit. The contractual performance of the element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective. (SIGNIFICANT CONFIDENCE) S (SATISFACTORY) – Performance meets contractual requirements. The contractual performance of the element contains some minor problems for which corrective action taken by the contractor appear or were satisfactory. (CONFIDENCE) M (MARGINAL) –Performance does not meet some contractual requirements. The contractual performance of the element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented. (LITTLE CONFIDENCE) P (POOR) – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective. (NO CONFIDENCE) N (NEUTRAL) – No relevant past performance record is identifiable upon which to base a meaningful performance risk prediction. A search was unable to identify any relevant past performance information for the contractor or their key personnel. (This is neither a negative or positive assessment.)

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. Was this a competitive Contract?
YES
NO
2. Role of contractor.
Prime
Sub
3. Ability to meet quality standards specified for technical performance.
E
G
S
M
P
N
4. Compliance with contractual terms and conditions.
E
G
S
M
P
N
5. Quality/integrity of technical data/report preparation efforts.
E
G
S
M
P
N
6. Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements.
E
G
S
M
P
N
7. Effectiveness of overall contract management (including ability to effectively lead, manage and control the program).
E
G
S
M
P
N
8. Effectiveness of on-site management, including management of subcontractors?
E
G
S
M
P
N

9. Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports).

E
G
S
M
P
N
10. Timeliness/effectiveness of contract problem resolution without extensive customer guidance.
E
G
S
M
P
N
11. Ability to successfully respond to emergency and/or surge situations.
E
G
S
M
P
N
12. Effectiveness of on-site management and control multidiscipline construction categories, including subcontractors.
E
G
S
M
P
N
13. Effectiveness of material management.
E
G
S
M
P
N
14. Effectiveness of acquisition management.
E
G
S
M
P
N
15. Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client.
E
G
S
M
P
N
16. Contractor safety record.
E
G
S
M
P
N
17. Responsiveness regarding safety issues.
E
G
S
M
P
N
18. If this is/was a Government cost type contract, the Contractor’s timeliness in submitting monthly invoices with appropriate back-up documentation and monthly status reports/budget variance reports.
E
G
S
M
P
N
19. If this is/was a Government cost type contract, the Contractor’s accuracy regarding monthly invoices with appropriate back-up documentation and monthly status reports/budget variance reports.
E
G
S
M
P
N
20. Ability to hire/apply a qualified workforce to this effort.
E
G
S
M
P
N

21. Ability to retain a qualified workforce on this effort

E
G
S
M
P
N
22. If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
E
G
S
M
P
N
23. Have there been any indications that the contractor has had any financial problem?
E
G
S
M
P
N
24. In summary, provide an overall rating for the work performed by this contractor.
E
G
S
M
P
N

COMMENTS: Objective Comments / concerns relating to this Offeror.