Attachment 2 - rev SOW North Culverts.pdf
PDF 462 KB Posted
- Solicitation number
- 12445226Q0047
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for the FY26 Pisgah North Ranger District Ditch Culvert Replacements and Road Rehabilitation project, issued by the USDA Forest Service for work in Buncombe, Haywood, Henderson, and Transylvania Counties, North Carolina.
The contract scope involves the removal of 285 ditch relief culverts spanning 57 miles of roadway and replacement with 9,873 linear feet of 24-inch aluminized corrugated metal pipe (CMP) culverts, along with comprehensive road rehabilitation to Forest Service standards. Work includes roadway rehabilitation and surfacing using NCDOT ABC aggregate, clearing and grubbing of fallen trees and debris, shoulder and embankment repair, ditch maintenance and reshaping, and installation of associated drainage structures including drop inlets, catch basins, headwalls, and rip-rap. The project is part of Hurricane Helene Recovery efforts and is expected to be awarded through open market competition. The contract period is 730 days (2 years), with work restricted to 6 a.m. to 6 p.m. Eastern Daylight Time, Monday through Friday, excluding federal holidays. Key deliverables include a project schedule within 5 business days of award, weekly status reports submitted every Monday by 3:00 PM EDT, and digital submissions of material tickets and receipts for stone, asphalt, culverts, drop inlets, and headwalls within 5 business days of purchase and placement. The contractor must maintain proficiency with ArcGIS Field Maps and ArcGIS Online to capture and sync field data to the Enterprise server every 24 hours, with progress payment processing contingent upon GIS data submission and acceptance. The contract incorporates Federal Project Standard Specifications (FP-24) and Forest Service Supplemental Specifications (FSSS), with reference specifications and detailed standard drawings provided. Environmental protection requirements include erosion control measures, invasive species prevention, pollution prevention, and compliance with Endangered Species Act protections for sensitive and endangered species in the project vicinity.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2026 Culvert Replacement Parent SOW
US Department of Agriculture (USDA)
US Forest Service
Statement of Work
NATIONAL FORESTS IN NORTH CAROLINA
FY26 PISGAH NORTH RANGER DISTRICT DITCH CULVERT
REPLACEMENTS AND ROAD REHABILITATION
BUNCOMBE, HAYWOOD, HENDERSON, TRANSYLVANIA
COUNTIES
NORTH CAROLINA
Contents Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Reference Specifications
7.0 Reference Drawings/Plans
8.0 Quality Control Plan
9.0 Government Quality Assurance
10.0 Contractor’s Key Personnel
11.0 Environmental Protection
12.0 Fire Protection
Attachments/References
Project FY26 Pisgah North Ranger District Ditch Culvert Replacements and Road Rehabilitation.
General Information
1.0 Scope of Work
The FY26 Pisgah North Ranger District Ditch Culvert Replacements and Road Rehabilitation contract will cover all work related to the ultimate deliverable for the removal of 285 ditch relief culverts spanning over 57 miles of roadway and replacement with 9,873 linear feet of 24” culverts (Corrugated Metal Pipe) and road rehabilitation within the Pisgah Ranger District of the Pisgah National Forest in North Carolina to current Forest Service Standards.
The road rehabilitation, ditch relief culvert installations/replacements contract will include all associated work related to the installation of 24 inch aluminized corrugated metal ditch relief pipes (CMP), removal and disposal of existing culverts off government land, reshaping/reforming ditches for positive drainage; rip-rap for outlet structures and sediment and erosion control; sediment traps; lined ditches; drop inlets; catch basins;
flanged culvert inlets; headwalls; road elevation alterations; excavation and backfill (in situ cut/fill materials including soil, rock, water); removal and disposal of existing culverts; installation of new or replacement culvert (with attention to cover over culvert, skew, inverts, slope and grade); and clearing/unclogging culvert or ditch.
2.0 Background
The contract is part of Hurricane Helene Recovery efforts, mainly focused on damaged culverts, ditches or other drainage structures. Work expected to be awarded through open market.
Contractor Requirements
3.0 Technical Requirements / Tasks
Work will consist of a variety of items related to the installation/replacement of Forest Services ditch relief culverts. List of culverts, IDs, road maintenance level, locations and special considerations will be itemized, described, quantified and/or specified on the Summary of Quantities, Summary of Activities and Work List Sheets provided in the project drawings attached. Other work items not listed may be ordered if mutually agreed by the Contracting Officer and Contractor. Work Items Include:
1. Roadway rehabilitation: Blade and shape the existing traveled way and shoulders, to produce a uniform surface, consistent to grade, and crowned or cross-sloped as indicated in the plans and existing surface to design specifications. Scarify roadbed to remove ruts, potholes, corrugations and berms to a depth up to 6 inches or to the bottom of potholes if deeper than 6 inches. Maintain ditches, including lead-off ditches, by removing rock, soil, wood and other materials. Maintain or re-shape ditches to achieve proper drainage. Suitable materials up to 4 inches may be blended into road surface. Remove waste materials and debris from roadway. Compact entire road after surfacing.
2. Roadway surfacing: Spread and compact NCDOT ABC aggregate per the activity schedule and specifications.
3. Clearing and grubbing: Remove fallen trees and debris within the clearing limits and mow the roadway as per details and specifications.
4. Shoulder/Embankment rehabilitation: Repair uphill slope or embankment at discharge per the Federal Project Standard Specifications (FP-24) and Forest Service Supplemental Specifications (FSSS) Section 204 as specified.
5. Ditch Relief Culvert Installs/Replacements as per details shown on the attached drawings and specifications on assets approved by COR. Locations shown on the attached Georeferenced Map.
6. Geospatial Support Services: Contractor must be able to use ArcGIS Field Maps to capture, update, and sync field data. Mobile workers will need to obtain account access and have the capability to handle offline map areas and ensure data integrity during synchronization to the ArcGIS Maps provided by the
Government. The GIS Lead and Field Data Collectors shall be proficient with ArcGIS Field Maps and ArcGIS Online (AGOL). Specific naming conventions and attribute fields are to be adhered. All field data must be synced to the Enterprise server every 24 hours to ensure real-time oversite of the project.
Processing of Progress Payments will be subject to submittal and acceptance of GIS data.
Quantity adjustments may be mutually agreed upon without further competition depending on pricing and funding availability. All modifications will be finalized on an SF30.
Offerors are required to submit a price quote as specified in Section L, Instructions to Offerors, of this Solicitation.
Protection of Sensitive and Endangered Species Refer to the attachment Biological Assessment for Federally Listed Species and Critical Habitat for Pisgah National Forest in full for guidance with attention to Appendix A for special considerations. Endangered Species Act (ESA) requirements during culvert replacement also include the following:
1. General Identification and Avoidance: The Government has identified protected plant and animal species within the project vicinity. The Contractor shall restrict all ground-disturbing activities, equipment staging, and material storage to the designated areas.
2. Physical Protection Measures Flagging and Fencing: The Contractor shall maintain all Government installed flagging or orange construction fencing. If any flagging or fencing is damaged or removed, the Contractor must stop work in that immediate area and notify the Contracting Officer Representative (COR) for replacement. No-Entry Zones: Areas shall be flagged to represent "No-Entry" zones for personnel and equipment. No soil, debris, or equipment shall be pushed into or stored within these zones. Contact COR when entry into these areas are unavoidable to discuss potential options.
3. Mitigation and Best Management Practices (BMPs) Erosion Control: Since the project involves upsizing culverts on a slope, the Contractor must use weed-free certified straw wattles or silt fencing to prevent sediment runoff from entering sensitive habitat or downstream reaches. Invasive Species Prevention: To protect native plant species, all heavy equipment must be pressure-washed and inspected for weed seeds and soil before entering National Forest System lands. Pollution Prevention: All refueling must occur at least 100 feet away from the drainage inlet and sensitive plant zones. All heavy equipment (excavators, loaders) must be inspected daily for hydraulic or fuel leaks. Any equipment found leaking must be removed from the project site immediately. Refueling Zones: No refueling or hazardous material storage shall occur within 100 feet of the stream, sensitive plant zones, or any drainage leading to the culvert inlet. A spill kit must always be on-site and readily available.
4.0 Government Furnished
Majority of roads are closed to the public. The Government will supply a key to the Contractor for roads closed by Forest Service gates. It is the contractor’s responsibility to obtain all keys for closed roads from the District Ranger Office prior to start of work and must be returned when the work included in the project is completed.
The contractor shall establish and implement methods of ensuring that all keys issued to the contractor by the Government are not lost or misplaced and are not used by unauthorized persons. No keys issued to the contractor by the Government shall be duplicated. The contractor shall develop procedures covering key control that shall be included in the quality control plan. ALL keys issued by the Government are to be returned prior to final payment request.
5.0 Deliverables / Schedule
Key Deliverables include but are not limited to the items listed in the following table:
Key Deliverables
Item No.
Deliverable Objective Due
Proposed Project
Schedule
Defining the responsibilities, timeline, risks and milestones of contract objectives.
No later than five (5) business days after Contract Award is issued. To be updated no later than 30 days from the last project schedule.
Relief Culvert Asset Status and Location
Report
Update the Ditch Culvert Asset ARCGIS digital platform
No later than five (5) business days after each culvert installation is completed.
Stone Tickets
Submittals
Email digital copies of Stone Tickets to COR(s) and inspector(s) with a cumulative count list of how much has gone into each road.
No later than five (5) business days after stone being purchased and placed.
Asphalt Material
Submittals
Email digital copies of Asphalt Material Tickets to COR(s) and inspector(s) with a cumulative count list of how much has gone into each road.
No later than five (5) business days after asphalt road material being purchased and placed.
Culvert Material
Submittals
Email digital copies of Culvert Material Purchase receipts to COR(s) and inspector(s) with a cumulative count list of how much has been installed into each road.
No later than five (5) business days after culvert material being purchased and placed.
6 Drop Inlet Material
Email digital copies of Drop Inlet Material Purchase receipts to COR(s) and inspector(s) with a cumulative count list of how much has been installed into each road.
No later than five (5) business days after drop inlet material being purchased and placed.
7 Headwall Material
Email digital copies of Headwall Material Purchase receipts to COR(s) and inspector(s) with a cumulative count list of how much has been installed into each road.
No later than five (5) business days after headwall material being purchased and placed.
Weekly Status
Report Report documenting tasks and issues weekly.
Weekly, every Monday, by 3:00 PM EDST until the contract expires
1. Contractor shall submit a project schedule within 5 days of contract award before the NTP can be issued. Contract has a Period of Performance of 730 days (2 years), and work shall be accomplished within the allotted timeframe.
2. Contractors shall update the digital Ditch Culvert Asset ARCGIS Map for each feature as specified: A.
Culvert Feature Size and installation date.
B. Condition Rating to be marked as “UNKNOWN”, as a notification to the COR(s) and/or inspectors that they need to be inspected.
C. Additional remarks are to include inlet considerations, location, skew and slope if update is required.
3. Contractor shall submit Stone Tickets in Digital Format to COR(s) and inspector(s) with a breakdown of quantities invoiced and to be invoiced no later than 5 days after stone being purchased, placed and compacted.
4. Contractor shall submit Asphalt Road Material Tickets in Digital Format to COR(s) and inspector(s) with a breakdown of quantities invoiced and to be invoiced no later than 5 days after material being purchased, placed and compacted.
5. Contractor shall submit Culvert Material Purchase Receipts in Digital Format to COR(s) and inspector(s) with a breakdown of quantities invoiced and to be invoiced no later than 5 days after culverts being purchased and installed.
6. Contractor shall submit Drop Inlet Material Purchase Receipts in Digital Format to COR(s) and inspector(s) with a breakdown of quantities invoiced and to be invoiced no later than 5 days after culverts being purchased and installed.
7. Contractor shall submit Headwall Material Purchase Receipts in Digital Format to COR(s) and inspector(s) with a breakdown of quantities invoiced and to be invoiced no later than 5 days after culverts being purchased and installed.
8. Contractor shall submit a weekly status report to COR(s) and inspector(s) in the form of an email delineating the amount of work items completed on individual roads.
6.0 Reference Specifications
This project makes use of Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24) U.S. Customary Units. FP-24 is included by reference only and can be found on the internet at the following website: https://flh.fhwa.dot.gov/resources/specs/.
The Forest Service Supplemental Specifications provided in the table below are a part of this solicitation and resulting contract and are provided as a separate attachment. Supplemental Specifications (FSSS) include additions and revisions to the Standard Specifications (FP-24).
FSSS
No.
Description
100 General Requirements
101 Terms, Format, and Definitions
102 Bid, Award, and Execution of Contract
103 Scope of Work
104 Control of Work
105 Control of Material
106 Acceptance of Work
107 Legal Relations and Responsibility to the Public
108 Prosecution and Progress
109 Measurement and Payment
150 Project Requirements
151 Mobilization
152 Construction Survey and Staking
153 Contractor Quality Control
155 Schedules for Construction Contracts
156 Public Traffic
157 Soil Erosion and Sediment Control
158 Watering for Dust Control
200 Earthwork
202 Additional Clearing and Grubbing
203 Removal of Structures and Obstructions
204 Excavation and Embankment
205 Rock Blasting
206 Reserved
207 Earthwork Geotextiles
208 Structure Excavation and Backfill for Selected Major Structures
209 Structure Excavation and Backfill
212 Linear Grading
300 Aggregate and Base Courses
301 Untreated Aggregate Courses
302 Minor Crushed Aggregate
303 Road Rehabilitation
304 Full Depth Reclamation
314 Stockpiled Aggregates
407 Chip Seal
409 Micro Surfacing
411 Asphalt Prime Coat
412 Asphalt Tack Coat
413 Asphalt Pavement Milling
603 Structural Plate Structures
625 Turf Establishment
633 Permanent Traffic Control
648 Stream Simulation and Streambed Simulation
701 Cement
703 Aggregate
704 Soil
705 Rock
6.3 Operational Hours
The contractor is responsible for performing work between the hours of 6 a.m. to 6 p.m. Eastern Daylight Time, Monday through Friday, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Work outside of these hours or circumstances must be approved in writing by the CO in advance. The contractor shall always maintain an adequate workforce for the uninterrupted performance of all tasks defined within this Statement of Work when the Government facility is not closed for the above reasons.
Federal Holidays
1. New Year’s Day – January 1st
2. Martin Luther King Junior’s Birthday – Third Monday in January
3. President’s Day – Third Monday in February
4. Memorial Day – Last Monday in May
5. Juneteenth – June 19th
6. Independence Day – July 4th
7. Labor Day – First Monday in September
8. Columbus Day – Second Monday in October
9. Veteran’s Day – November 11th
10. Thanksgiving Day – Fourth Thursday in November
11. Christmas Day – December 25th
7.0 Reference Drawings/Plans
The following Ditch Culvert and Road Rehabilitation standard drawings are applicable to this project and are included in the plan set.
Sheet No. Title
1 Cover & Index of Sheets
2 General Construction Notes
3 Project Map, Page 1 of 2
4 Project Map, Page 2 of 2
5 Summary of Quantities
6 Summary of Activities, Page 1 of 2
7 Summary of Activities, Page 2 of 2
8 Work List, Page 1 of 7
9 Work List, Page 2 of 7
10 Work List, Page 3 of 7
11 Work List, Page 4 of 7
12 Work List, Page 5 of 7
13 Work List, Page 6 of 7
14 Work List, Page 7 of 7
15 Typical Sections
16 Brushing And Disposal Detail
17 Clay Plug Detail
18 CMP Culvert Detail
19 CMP Ditching Detail
20 Drop Inlet Detail
21 Headwall Detail
22 CMP Armor Detail
23 CMP Alignment Detail
24 CMP Band Detail
25 Rolling Dip Detail
26 Traffic Control Detail
27 Erosion Control Detail
8.0 Quality Control Plan
The Contractor shall submit to the CO, a Quality Control Plan (QCP) as part of their proposal that will detail the methods the Contractor will use to perform self-inspection to ensure the requirements of this contract are performed in accordance with the contract documents. The QCP shall at a minimum record the reference pay item, location, frequency, type of test and resulting outcome. QCPs shall be submitted with the Accomplishment Report and no payment will be made prior to receipt of these records and acceptance of the work performed.
At a minimum, the QCP shall contain:
• Inspection System. An inspection system must cover all of the services listed in the contract documents.
It must specify the work items to be inspected on either a scheduled or unscheduled basis, how often inspections will be accomplished, and the title of the individual(s) who will perform the inspection. The inspection system must provide for a written record of inspections and results.
• Methods. Identify the proposed methods for identifying and preventing defects before the level of performance becomes unacceptable.
Records. The contractor shall maintain on-site records of all inspections and necessary corrective action(s) taken. This documentation shall be furnished at the time payment is requested, or when requested by the Contracting Officer’s Representative during the term of the contract. Project inspectors reserve the right to check contractor’s Quality Control Inspections at any time during the life of the project.
9.0 Government Quality Assurance
The Government will monitor progress to ensure that the Contractor is providing the quality promised in their QC Plan and that work meets performance standards. Visual observation may be used. The Government reserves the right, if deemed necessary to ensure compliance with the contract, to make random or 100% full inspections of the work. Each road and culvert will be inspected separately.
Government inspections will be documented on Daily Diaries and placed in the contract file. If work in part of an area is not acceptable, a Notice of Non-Compliance will be issued to the Contractor. See attached for sample of form. The CO may issue other cure notices if work is not being performed in a timely manner or does not comply with contract specifications.
Upon completion of a culvert or road and notification by the Contractor, the COR or designated Inspector shall make an overall inspection of that/those culverts/roads. If a need for remedial work prior to acceptance is reflected by the COR/Inspector`s inspection, such remedial work will be performed before the Contractor moves to the next area(s). If the inspection results in acceptance of the area, the Contractor may immediately proceed with work on the next area(s).
Government inspections are for the sole benefit of the Government and do not:
• Relieve the Contractor of responsibility for providing adequate quality control measures;
• Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
• Constitute or imply acceptance; or
• Affect the continuing rights of the Government after acceptance of the completed work.
10.0 Contractor’s Key Personnel
At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly supervise the work or assign and have on the work site a competent superintendent who is satisfactory to the CO and has authority to act for the Contractor. The superintendent shall be designated in writing to the CO prior to the commencement of work.
11.0 Environmental Protection
The contractor shall instruct employees in environmental protection practices. The contractor shall be responsible for operating under conditions which preclude the waste of fuel or spoiling the environment which shall include:
• Disposal of Refuse: Contractor shall be required to remove all refuse from each respective work site every day work is performed and shall dispose of the refuse off of Government property.
• Fuel for equipment, trucks and vehicles shall not be wasted. Extended engine idling shall not be permitted.
• Machine fluids (fuel, oils, coolants, etc.) shall not be drained on the ground or allowed to enter any watercourse. Inadvertent spills shall be contained immediately, and the District Ranger, Project Inspector, and local authorities shall be notified immediately. Promptly remediate the spill unless otherwise directed by authorities.
The Contractor shall provide protective barriers to prevent soil erosion on all projects requiring excavation.
Also, included will be environmental protection to prevent sedimentation drainage of silts into storm drains.
All protective barriers will be continually maintained on the project until the project is completed and accepted by the Government.
12.0 Fire Protection
The Contractor shall comply with all policies and rules of the National Forests of North Carolina to prevent forest fires. The Forest Service Health and Safety Code Handbook (FSH 6709.11), National Wildfire Coordination Group Fireline Handbook, and Forest and District policies describe procedures to avoid the unintentional ignition and spread of wildfire. These include, but are not limited to:
• Use spark arrestors on fuel powered vehicles and machinery;
• Have onsite access to a fire extinguisher and/or other firefighting tools, such as shovels or rakes;
• Ensure proper storage and handling of flammable liquids;
• Ensure positive extinguishing of any open flames or burning materials, such as tobacco;
• Obtain COR and District approval for any open fires, and
• Completely extinguish all approved fires before departing worksite.
Attachments
• Attachment 1 - Terms & Conditions North
• Attachment 2 – SOW North Culverts
• Attachment 3 – SOI North Culverts
• Attachment 4 - FSSS Specs
• Attachment 5 – GeoRefMap
• Attachment 6 - Activity Summary
• Attachment 7 - Links North Culverts
• Attachment 8 - North Culv Rep_Plan
• Attachment 9 - Past Performance Questionnaire