This is Amendment 0001 to solicitation 12445225B0001 for the SRS Stoneville Sewer Main Repair project, issued by USDA Forest Service CSA East 12 in Atlanta, GA. The amendment provides responses to contractor questions about the sewer main repair work.
The responses clarify that only a couple feet of 6" PVC pipe need to be replaced where it connects to a clay pipe entering a manhole. The scope involves retapping the manhole and extending the PVC pipe directly into it with a sealed connection. The government notes that while the sewer line was reworked in the past 24-36 months, only one additional PVC utility line is known to be in the immediate vicinity, though contractors are responsible for locating any other utilities. The amendment includes a photo showing the exposed manhole and pipe requiring repair. The original solicitation due date of November 19, 2024 remains unchanged.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J3 - Stoneville Site Plan with Manhole.pdf | ||
| Sol_12445225B0001.pdf | ||
| J4 - Wage Determination WD 2015-5161.pdf | ||
| J2 - SOI_SRS Stoneville Sewer Main Repair.pdf | ||
| J1 - SOW_SRS Stoneville Sewer Main Repair.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12445225B0001 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ATLANTA GA 30309-2449
STE 876S
1720 PEACHTREE ST NW
USDA-FS CSA EAST 12
12/05/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
11/19/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project: SRS Stoneville Sewer Main Repair.
The purpose of the amendment 0001 is to:
1. Provide responses to RFI's that were submitted by potential bidders.
No other changes are made.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
KEISHA N. ROBINSON
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Project Name: SRS Stoneville Sewer Main Repair Solicitation: 12445225B0001
Government responses are in red:
1. Approximately how many feet of sewer line needs to be replaced?
Just a couple feet of pipe need to be replaced. The PVC pipe was joined to a clay pipe entering the manhole and that joint broke and caused the PVC pipe to settle (see picture in SOW). The scope is to retap the manhole and extend the PVC directly into the manhole and seal connection.
2. Approximately what size is the existing pipe that needs to be repaired?
The existing pipe is approximately 6" PVC. Contractor shall confirm all measurements.
3. Are the any other utilities next to the broken sewer line?
This sewer line was reworked within the last 24 to 36 months. The only known additional utility within the immediate vicinity of the manhole is an additional PVC line. See provided picture.
Contractor shall be responsible for locating any other utilities. Forest Service can provide utility contact information.
File details come from the government source that posted it. Updated .