ScopeofWorkDivisionUpdated.docx
DOCX document 256 KB Posted
- Solicitation number
- 12445221Q0007
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Gate_contract2021_3 - Copy.pdf | ||
| Gate_contract2021_2 - Copy (2).pdf | ||
| Gate_contract2021_1 - Copy (3) - Copy.pdf | ||
| Questions and Answers to The construction and installation of 21 gates.docx | DOCX document | |
| Questions and Answers to The construction and installation of 21 gates.docx | DOCX document | |
| wagedetermiationsam.gov.pdf | ||
| Sol_12445221Q0007.pdf | ||
| Scope of Work_Division_gates_2021_.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL SPECIFICATIONS
Scope of Work – Talladega Division Gate removal and installation The project purpose is for the construction and installation of 21 new gates in accordance with the specifications and provisions of the contract. All gates shall be brown in color.
Description and Location Gates to be replaced or installed are within the boundaries of the Talladega & Shoal Creek Ranger Districts in Cleburne, Clay, & Talladega County, Alabama. A map of gate locations is attached. Gates are flagged.
TECHNICAL SPECIFICATIONS
Replacement or Installation Instructions All gates shall be installed using supplied gate specifications and drawings in addition to specifications detailed in this narrative.
Existing gates must be removed entirely from the site and the new gates installed in the Flagged location.
All gates shall be painted using the Standard color Sherman Williams color - SW6090 – Java Brown or approved equal.
The contractor shall drill one row of ½” holes ½” apart around the locking post one inch below the steel plate welded to the top of the pipe.
The contractor shall be responsible for the reflective metal signs on both sides of gates as illustrated in the specifications attached.
The contractor shall remove and dispose of all trash and debris generated by the removal and installation of the gates from the worksites before work can be approved. The contractor shall dispose of all trash and debris off Government property.
Timing of Work All gates shall be installed no later 60 days from the Notice to Proceed.
Government Furnished Items The Government will furnish no materials, labor, or equipment.
Contractor Furnished Items Contractor shall furnish all labor, materials, equipment, tools, transportation, supervision, supplies, and perform all work required for the removal existing gates and construction and installation of twenty-one (21) new gates in accordance with the specifications and provisions of the contract.
Sign and Stickers Instructions
• The contractor shall supply all signs, material and hardware and install all signage and stickers to the twenty-one (21) new gates.
• Each gate will require two (2) - 8”x24” GM-L-24 and two (2) – 8”x24” GM-R-24 12” wide reflective tape (SIGN 1 & 2). The signs shall be applied to each post as shown on drawing (DRAWING 1).
SIGN 1
OBJECT MARKERS
Object Marker Left Type 3 Red & White- OM3-L R/W or equal Object Marker Sign Left Type 3 OM3-L R/W
• PRODUCT DESCRIPTION • Reflective Sheeting on Aluminum
• Radius Corners
• 3/8" Prepunched Hole
High Intensity and Diamond Grade Meet DOT and MUTCD State and Federal Guidelines Type 3 Object Markers Red & White • OM3-L For Obstructions Adjacent To The Roadway
• MUTCD Guide Information
Sign 2 Object Marker Right Type 3 Red & White- OM3-R R/W or equal Object Marker Right Type 3 OM3-R R/W
PRODUCT DESCRIPTION
• Reflective Sheeting on Aluminum
• Radius Corners
• 3/8" Prepunched Hole High Intensity and Diamond Grade Meet DOT and MUTCD State and Federal Guidelines Type 3 Object Markers Red & White • OM3-R For Obstructions Adjacent To The Roadway
#1 Specs
PERFORMANCE ASSESSMENT METHODS
Inspection Contractor’s Self-Inspection – The Contractor shall be responsible for supervising his/her crew and self-inspecting his/her own work to insure compliance with contract specifications throughout the contract.
Gate Inspection Procedure - The Government will make periodic visits to the work site while work is in progress, to assure that the Contractor is familiar with contract specifications and that work is progressing satisfactorily.
Upon completion of a gate, and at the Contractor’s request, the COR or an Inspector may inspect the gate for compliance with specifications.
Acceptance
Acceptance of the work will be determined by visual inspection and will be based on adherence to the specifications and drawings identified for gate installation.
No credit will be earned until all gate installation requirements have been completed.
Performance Requirements Summary
Acceptable Quality Level for Gate Replacement or Installation – 100% compliance with stated specifications and drawings.
image1.emf image2.emf image3.png
File details come from the government source that posted it. Updated .