This document is a Statement of Work (SOW) for a roof replacement project at the Clear Springs Campground in the Homochitto National Forest in Mississippi. The key details are:

The contractor shall provide all materials, labor, equipment, and other services to replace the existing roof, including removing and replacing the underlayment and shingles, removing and covering 4 skylights, and replacing any damaged decking. The work is to be performed on an approximately 26ft x 13.5ft roof at the group site bathroom. The contractor must also replace the existing asphalt fascia covering with painted metal fascia. The work is to be completed within 15 days after the notice to proceed. The solicitation is a Request for Quote (RFQ) that will result in a firm-fixed price contract, awarded to the lowest priced responsible offeror. The project is set aside 100% for small businesses under NAICS code 238160, Roofing Contractors. The tentative dates for the solicitation include a site visit, deadline for questions, and quote submittal deadline in July 2024.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE OF SERVICES

GROUP SITE BATHROOM ROOF REPLACEMENT

ITEM DESCRIPTION QTY UNIT TOTAL PRICE

0001 • Tear off existing roof & skylights which are causing the majority of leaks

• Replace skylight hole with 7/16” osb plywood, repair or replace any damaged decking

• Cover Decking with synthethic felt

• Nail new shingles (architectural 30-year

GAF brand) and use new ridge mount

• Replace existing facia covering with painted metal facia covering

• Cover skylight hole inside bathroom with ½” CDX plywood and replace rotten trim

Clear Springs Campground, 3888 Clear Springs Rd, Meadville, Ms 39653

1 Each

TOTAL $ ___________

FAC 2024-03

dated February 23, 2024

ATTACHMENT 0002

Statement of Work

National Forests in Mississippi, Homochitto Ranger District

Statement of Work –Group Site Bathroom Roof Replacement

A. GENERAL: Contractor shall provide all materials, labor equipment, tools, transportation, permits, licenses, supervision, and all to successfully replace underlayment and existing shingles with architectural 30 yr shingles on an approximate 26ftx13.5ft roof, remove 4 skylights and cover with 3/4 inch plywood. Replace any damaged or rotten decking. Replace existing asphalt facia covering with painted metal facia covering.

B. Clean up the site and dispose of materials off of the Forest Service property. This is the group site location. Work schedule will coincide with times the campsite is not occupied, Clear Springs Campground Pavilion, 3888 Clearsprings Rd, Meadville, Ms 39653.

B. WORK HOURS:

1. Normal Work Hours: 10:00am - 6:30pm, Monday through Saturday.

2. National Holidays: The ten (11) holidays observed by the Federal Government are: New Year’s

Day, Martin Luther King’s Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day and Christmas Day and any other day specifically declared by the President of the United States to be a national holiday.

C. SPECIFICATIONS:

1. Safety

a. The contractor shall barricade the entrance to the group site as work is being completed.

b. The contractor shall use necessary PPE to complete the job safely.

2. All tasks accomplished by the contractor personnel shall be done so as to preclude damage or disfigurement of outdoor structures, hardware, and signs. The contractor shall correct any damage caused by their employees to any part of the building, hardware or signs in any area covered by this contract at the contractor’s expense.

3. Frequency of Services Required:

None.

D. GOVERNMENT FURNISHED EQUIPMENT/SUPPLIES

E. QUALITY ASSURANCE: All work shall be completed using all best safety requirements. The

Government will receive and investigate complaints from various customers located at the Federal Agency location and other locations associated with this contract. All information received will be provided either verbally and/or in writing to the contractor for appropriate action. All incentives and penalties will be judged according to unannounced inspections, direct observations or inspections, and COTR review of submitted reports or substantiated complaints by building occupants.

FAC 2024-03

dated February 23, 2024

F.

1. Contractor Quality Control Program

a. The contractor shall have a quality control program to assure all requirements of the contract are met as specified. The program shall be detailed and provided in writing to the Contracting Officer or his/her designee. The program shall be continuously improved to keep in compliance with OSHA, Joint Commission, and Infection Control guidelines.

b. The contractor shall provide upon request all documentation regarding this Quality Control program including guidelines and inspection results.

2. Periodic Progress Meetings

a. The Contracting Officer, COTR, or other government personnel as appropriate and the contractor shall have periodic meetings to discuss the contractor’s performance. Items for discussion include, but are not limited to inspection results, customer complaints, opportunities to improve performance, steps taken by the contractor to prevent occurrences in the future. The contractor shall provide a summation of unsatisfactory findings and customer complaints and provide insight into any identified trends.

G. OTHER REQUIREMENTS: All items are contained in this subsection are required to be provided by the contractor by the listed deadline and are subject to penalties for delinquency.

Requirement Timeline/Deadline/Specification

Contractor Quality Control program Written submission of program no later than 5 days prior to starting date of contract

Provide Reports / Job related data upon request. Contractor is required to provide reports and job-related data within 3 business days of request.

Reports may include but are not limited to (for each location): hours worked, supplies consumed, accident reports, summary of quality assurance program results, summary of complaints, etc.

List of Employees Contractor shall provide comprehensive list of employees, by contract location, prior to the start of the contract. The employee list must include good contact phone numbers for each employee as well as all completed training as proof of compliance with all applicable laws and requirements.

Seamlessness of Service Contractor is responsible to provide replacement personnel immediately if any in their employment cannot complete the work assigned.

FAC 2024-03

dated February 23, 2024

There shall be no instances where work is not performed as required and in accordance with Work Hours (section B).

H. SECURITY ACCREDITATION PACKAGE

FAC 2024-03

dated February 23, 2024

FAC 2024-03

dated February 23, 2024

-----END OF SOW-----

Delivery FOB Destination to:

Clear Springs Campground, 3888 Clear Springs Rd, Meadville, Ms 39653

FAC 2024-03

dated February 23, 2024