12444524Q0096 SF 18 Scedule of Items Statement of Work Descrption Maps.pdf

PDF 2 MB Posted

Attached to
Hoosier National Forest, Brownstown RD Road Maintenance
Solicitation number
12444524Q0096
Issued by

About this file

This document contains a Statement of Work and related federal contract opportunity for a road maintenance project for the Hoosier National Forest in Brownstown, Indiana.

The key details are:

  • The project involves shoulder backing, grading, reshaping, ditch grading and cleaning, and aggregate placement on approximately 4 miles of roads in the Hoosier National Forest. The work includes maintenance on Hardin Ridge Road, Tower Ridge Road, Brooks Cabin Road, White Oak Campground, EADS Campground, and Holland Campground.
  • The contract is a firm fixed-price award anticipated to be under $50,000, with a period of performance from September 2024 to November 2024.
  • This is a 100% small business set-aside under NAICS code 237310. The government will evaluate offers based on technical approach, past performance, management, and cost/price.
  • The solicitation number is 12444524Q0096 and is being issued by the USDA Forest Service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12444524Q0096 Brownstown Roads

ITEM

NUMBER DESCRIPTION PAY

UNIT EST QTY Total Price 0001 Grading & Ditchwork Miles 1.66 0002 Aggregate #53 Tons 250 0003 Shoulder Backing -Harden Ridge Road Miles 1.41 0004 Aggregate #73 Tons 420 0005 Labor Hourly 40 0006 Mobilization LS 1

ITEM

NUMBER DESCRIPTION PAY

UNIT EST QTY Total Price 1001 Shoulder Backing - White Oak Miles 0.26 1002 Aggregate #73 - White Oak Tons 100 1003 Shoulder Backing - EADS Miles 0.31 1004 Aggregate #73 - EADS Tons 100 1005 Shoulder Backing - Holland Miles 0.35 1006 Aggregate #73 - Holland Tons 120

FILL OUT THE AREAS IN RED BELOW

SCHEDULE OF ITEMS

Hoosier National Forest, Brownstown RD

PROJECT TITLE: Brownstown RD Maintanance

SCHEDULE OF ITEMS

Period of Performance Base Year: 09/19/2024 -11/30/2024

Period of Performance Optional Work Items: 09/16/2024 -11/15/2024

US Department of Agriculture (USDA)

Statement of Work

Project Brownstown RD Road Maintenance

General Information

1.0 Scope of Work

Road Work on this project consists of Shoulder backing, grading and reshaping the road surface, ditch grading and cleaning and aggregate placement. The ditch grading and cleaning will be part of the Road grading and shaping work item.

2.0 Background

Provide a general description of the requirement, describing the acquisition history (if applicable), the current environment, and the vision of the future of the requirement. If information technology is a factor, provide pertinent technical facts.

The Hoosier NF has 500 miles of roads some are paved with many being aggregate based. A percentage of the roads are open year-round, and some require maintenance works to keep them in a condition for the user level classification. Some of the roads will get yearly maintenance to maintain the road usage needs. The forest standard road width is 12’, some roads may be wider, and some have turnouts along them. The Hardin Ridge Recreation Area has mostly paved roads with a few that are gravel surfaced. The area during operational period is ran by a concessionaire group which monitor the camping and use of the area. The main road also provides access to a private subdivision locate near the Boat ramp. Tower Ridge Road sections have been vacated to the Forest Service. Brooks Cabin Road provides seasonal access to the Brooks Cabin.

Contractor Requirements

3.0 Technical Requirements / Tasks

Describe the specific tasks or work the contractor must perform. Provide direction on any specific methodologies.

• Project work items list.

o Grading consists of grading the existing road surface and reshaping it to drain. The work includes pulling aggregate back onto the roads from the shoulders and ditches. Road scarification will be required on roads with potholes and wash-boarding. Road scarification will be done in a method to remove the pothole and repack material to return it to the existing road surface. Most of the FS roads have a crowned template. FS must approve gradings prior to any aggregate placement.

o Ditch grading and cleaning consist of cleaning debris and/or reshaping the ditch to drain. Excessive sediment needs to be removed to ensure proper drainage. If excessive debris needs a disposal location work the COR on marking locations for it. Ditch work should be done is a manner to not contaminate the surface aggregate. Contractor needs to be aware of culverts, culvert catch basin, outlet ditches and drainage dips to not damage or fill/obstruct the structure. Ditch grading and cleaning must be completed prior to final grading and aggregate placement.

o Roadway Mowing consist of mowing the roads from the backside of the existing road ditch or 5’ past the edge of gravel. The mowing includes the road surface as needed. Mowing to the backside ditches includes around culverts along the road within work area. Vegetation to be mowed to a height of 6” or less. Mowing must be completed prior to grading activities starting.

o Roadway Clearing consist of Mowing/cutting and removal of trees, shrubs and brush from the roadway and cut and fill slopes of the roadway. Clearing includes the areas around culverts, bridges and storm structures. Existing fallen trees are to be removed and scattered on the downhill side of roads. Vegetation to be cut to a height of 6” or less.

Debris from clearing must be removed from road surface to prevent any damage to vehicle using the road. Clearing must be completed prior to grading activities starting.

o Aggregate consists of provided aggregate type/size described and placing in the locations described in the project or directed by the COR. The processing includes grading it to the road’s width, depth and equipment compaction of full road width unless otherwise stated. The contactor is required to control the aggregate placement and quantities. Stockpiling is not permitted on this project. Grading and ditch work must be completed prior to aggregate placement with COR’s approval. Compaction is required as noted in Description of Work. Equipment compaction requires full width of aggregate by hauling and or on-site equipment. Equipment compaction requires a least two passes to ensure compaction. When Roller - vibratory steel drum is required, it would be equal to a Cat CS433 with a minimum of two full width passes. Other roller – vibratory steel drum must be approved by COR.

o Mobilization will be a separate work item; Mobilization includes the cleaning of all equipment to be used on the project with inspections of equipment required prior to unloading the equipment.

o Road maintenance projects follow Special Project Specifications and Federal Standard Specifications FP-14.

• Project work “Shoulder backing”.

o Shoulder backing consist of placing aggregate material as describe along the road edge to protect the road surface from cracking and support the surface from breaking away. The process will be done using equipment designed to place the shoulder aggregate.

o The aggregate will be placed at a width of 18” with an approximate depth of 2”. Some locations will be less, a few could be more. The contractor is required to control the width, depth and quantities of the aggregate to keep it uniform along the road.

o The roads for the project have existing features (signs, utilities, etc.) the contractor are required to protect all existing features. It damaged it will be the contractors responsibly to repair damaged features at their cost. Existing manholes and utilities along the road will not be covered with aggregate.

o Equipment and labor hours for this project are all included in the Shoulder Backing cost. Separate labor hours would be for road traffic control.

o The placed aggregate cannot be higher than the existing asphalt edge and sloped away from the road to allow for proper drainage off the road.

o Intersection transitions will go back 10’ or to the gate location, whichever is shorter.

o After placing the aggregate, it must be compacted. Compaction methods can range from a smooth tracked equipment (2 passes minimum) to a roller compactor (1 pass minimum). A portable compaction plate-style will also be acceptable (1-2 pass minimum). The entire placed area must be compacted during the compaction.

o This project does not allow aggregate to be dumped along the road and bladed/pushed/swept off for placement.

This type of work can cause asphalt damage it will not be an acceptable method.

o Aggregate stockpiling will not be allowed on this project. No stockpile areas are available due to the project location.

o Contractor much ensures all aggregate material is placed off the paved surface. Any over dumping in the machine ben or loose material on or along the road must be removed off the road.

o Mobilization will be a separate work item. Mobilization includes the cleaning of all equipment to be used on the project with inspections of equipment required prior to unloading the equipment.

o Road maintenance projects follow Special Project Specifications and Federal Standard Specifications FP-14.

• Project equipment requirements. The following equipment is what is anticipated to complete the project. The project work should be completed using the appropriate equipment for the task.

o Grading work requires grading equipment (Grader, Skid-steer with grading attachment, etc.) Tractor with grader blade and Dozers will not be acceptable for the project.

o Ditch grading and cleaning requires equipment designed for the work (Grader, skid-steer, mini-excavator, etc.).

Manual Labor may be required around Culverts inlets and outlets.

o Clearing and Mowing requires equipment designed for the work (excavator w/attachment, tractor with A-boom mower, tractor with mower, etc.). Manual labor me be required around signs, guardrail, culverts inlet and outlets.

• The following are the roads to have work completed on this project. A detailed description of work will be attached for starting and stopping locations for each roads project work.

o FS Road 4725.000 Hardin Ridge Road (1.41 miles of work) o FS Road Tower Ridge Road (1.50 miles of work) o FS Road 4731.020 Brooks Cabin Road (0.164 miles of work) o FS Road 4725.020 EADS Campground (0.31 miles of work) o FS Road 4725.040 Holland Campground (0.35 miles of work) o FS Road 4725.080 White Oak Campground (0.26 miles of work)

• Project Timeframe, work hours and work area.

o Project timeframe will be between Monday and Friday (workweek) between the hours of 0630 to 1700 EST. No work will be done on weekends or Federal holidays.

o Work areas will require standard construction signs to warn traffic. Harden Ridge Road may require a flagman if the traffic is heavy, and the work is cause delayed to traffic flow.

o Equipment may be stored onsite during the project but are required to removed when the project is completed and accepted. Storage locations will be agreed upon prior to starting the project as the project area is a working Campground and some areas are gated/locked, and others have recreation activities.

4.0 Government Furnished

• The project will require access behind closed gates on the Forest. The contractor will be provided a contractor key for accessing closed areas for the use on the project.

• Forest Service will make site visits for inspections and monitoring the progress. A final inspection will be completed once the contactor has completed all the project work and request a final inspection of the completed work.

5.0 Deliverables / Schedule

• Contractor will notify the COR 48 hours prior to starting the project. This allows schedule time for equipment inspections and any staking needed for the project.

• Project areas that have aggregate to be placed will require “Aggregate Weight Tickets” to document the aggregate amount placed.

• Request the Final Inspection when all project work has been completed allowing the COR time for completing the inspection.

6.0 Contractor’s Key Personnel

The contractor will inform the Forest Service COR of the “Point of Contact” for the project prior to starting and work.

7.0 Security Requirements

Contractors are responsible for securing their equipment and supplies for the project. The FS will not provide special parking areas and/or storage areas for the contractors and or sub-contractors equipment and/or supplies. Equipment storage will be onsite in existing parking areas or locations that are acceptable to the FS.

8.0 Performance Requirement Measures

Performance Work Statement/Quality Assurance Plan

Requirement Required Task or Deliverable Performance Standard Method of Surveillance Grading with ditch cleaning

Provide safe, smooth roadway surface free of standing water. Includes ditches free of material and free flowing of water.

Shape and maintain the road per specifications.

Ensure not water is standing on the road and ins the ditches. Ensure all aggregate has been placed on the road surface area and shaped to provide and even placement.

Visual 100% measurement

Roadway Mowing and Clearing

Clear and cut vegetation, removed debris as designated. Ensure proper cutting height.

Vegetation is treated as shown on the task order.

Ensure the height standard is followed and designated areas are mowed/cut. Including around culverts, bridges, and other structures.

Roads with Aggregate and Paved surfaces must have mowing debris removed off them to prevent visitor automobile damage.

Visual 100% measurement

Aggregate Provide designated amounts and placement per Task Order

Placement and thickness as designated.

Quantities based on Task Order

Visual 100% measurement, with aggregate tickets for quantities.

Equipment & Labor

Provide and operate equipment as described in the project

Equipment cleaned and inspected, meets OSHA and Industry standards.

Visual 100% measurement, Track time and production 100%

Shoulder Backing

Provide and operate equipment as described in the project

Equipment cleaned and inspected, meets OSHA and Industry standards. Perform the work described in the task order. Compaction based on the task order.

Visual 100% measurement, measure aggregate placement width and check for compaction.

Attachment If applicable, include an Attachment stating Evaluation Factors and significant Subfactors representing the key areas of importance and emphasis to be considered in the source selection decision.

Project locations have pin drop coordinates and adjacent road for basic locations.

Hardin Ridge Recreation Area (4725.000) = 39° 0'36.31"N, 86°25'42.62"W, off S Chapel Hill Road 1.8 miles west of the intersection of Highway 446 Tower Ridge Road = 39° 0'53.68"N, 86°24'2.26"W, off 446 0.067 miles east of the intersection.

Brooks Cabin (4731.020) = 39° 0'55.23"N, 86°23'48.76"W, off Tower Ridge Road 0.25 miles east of the intersection of 446 White Oak Campground Loop (4725.080) = 39° 1'10.46"N, 86°26'45.08"W, off Harden Ridge Road 1.23 miles north of the intersection of S Chapel Hill Road.

EADS Campground Loop (4725.020) = 39° 0'46.57"N, 86°25'52.66"W, off Harden Ridge Road 0.26 miles north of the intersection of S Chapel Hill Road.

Holland Campground Loop (4725.040) = 39° 0'56.69"N, 86°26'15.76"W, off Harden Ridge Road 0.66 miles north of the intersection of S Chapel Hill Road.

Evaluation factors, in order of descending importance:

1. Technical

2. Past Performance/Current Workload

3. Management

4. Cost/Price

The non-cost factors (1 through 3), when combined are less than cost/price.

• Technical - The contractor shall provide a technical description that clearly states how the Government’s requirements contained within the Statement of Work will be met.

• Past Performance/Current Workload –The summaries of up to three relevant projects performed in the last five years including and current project obligations:

o project name, contract and/or task order number;

o contract dollar value;

o period of performance;

o customer point of contact (including name, work number, cell number, or email address);

o description of work performed;

o roles and responsibilities;

o the results achieved

Customers may be Federal, State, or Local Government, corporate, university, association customers.

• Management - All subcontracted tasks should be stated with a description of how subcontracted work will be monitored.

Description of Work Brownstown Road Maintenance FY 2024

F.S. Roads 4725.000 Hardin Ridge Road, 4725.020, 4725.040, 4725.080, Tower Ridge Road & 4731.020

Milepost Description of Work for Tower Ridge Road

0.00 Junction with HWY 446 (reference only).

0.067 Begin Grading and reshaping road to drain (1.5 miles)

Begin Ditch Grading and Cleaning (1.5 miles)

0.58 Blackwell Horse Camp (reference only).

0.87 Cope Hollow Trail Crossing (reference only).

1.50 Todd Cemetery Entrance

End of Project (EOP) End Grading and reshaping road to drain.

End Ditch Grading and Cleaning

Contractor will supply, place and process 250 tons of #53 aggregate as directed by the Forest Service COR. Aggregate will be used for surfacing, compaction is required by hauling or onsite equipment.

Milepost Description of Work for 4731.020 Brooks Cabin Road

0.00 Junction with Tower Ridge Road (reference only).

Begin Grading and reshaping road to drain (0.16 miles) Begin Ditch Grading and Cleaning (0.16 miles)

0.16 Tie back into loop road.

End of Project (EOP) End Grading and reshaping road to drain.

End Ditch Grading and Cleaning

Contractor will supply, place and process 80 tons of #73 aggregate as directed by the Forest Service COR. Aggregate will be used for surfacing, compaction is required by hauling or onsite equipment.

Milepost Description of Work for 4725.000 Hardin Ridge Road

0.00 Junction with S. Chapel Hill Road (reference only).

0.06 Gatehouse wide area (reference only).

0.26 FSR 4725.020 Eads Campground Right (reference only).

0.27 FSR 4725.010 Dump station Road Left (reference only).

0.31 FSR 4725.010 Dump station Road Left (reference only).

0.50 FSR 4725.0x0 Recreation House Left (reference only).

0.60 FSR 4725.0x0 Warehouse Left (reference only).

0.65 FSR 4725.040 Holland Campground Right (reference only).

0.74 FSR 4725.060 South Point Campground Left (reference only).

Begin Shoulder Backing (1.41 miles)

1.01 FSR 4725.060 Blue Gill Campground Right (reference only).

1.25 FSR 4725.080 White Oak Campground Right (reference only).

1.35 FSR 4725.100 Amphitheater Right (reference only).

1.41 FSR 4725.100 Amphitheater Right (reference only).

1.58 FSR 4725.070 Access Road Left (reference only).

1.68 FSR 4725.120 Pine Campground Right (reference only).

1.86 Overlook left (reference only). Contractor will place Shoulder Backing along the edge of the turnout parking for the overlook area.

1.88 Overlook left (reference only).

1.93 FSR 4725.140 Access Road Right (reference only).

1.99 Begin Guardrail Left (reference only). Contractor will place shoulder backing along the backside of the existing asphalt curb.

2.06 End Guardrail Left (reference only).

2.15 FSR 4725.090 Access Road Left (reference only).

End Shoulder Backing End of Project (EOP)

Contractor will supply and place 340 tons of #73 aggregate for shoulder backing.

“Optional Work Item” Milepost Description of Work for 4725.080 White Oak Campground

0.00 Junction with Hardin Ridge Road 4725.000 (reference only).

Begin Shoulder Backing (0.26 miles)

0.26 Turn around loop, Shoulder backing will be on both sides of the loop, inside and outside (reference only).

Contractor will supply and place 100 tons of #73 aggregate for shoulder backing.

Milepost Description of Work for 4725.020 EADS Campground

Begin Shoulder Backing (0.31 miles)

End Shoulder Backing End of Project (EOP)

Contractor will supply and place 100 tons of #73 aggregate for shoulder backing.

Milepost Description of Work for 4725.040 Holland Campground

Begin Shoulder Backing (0.35 miles)

Contractor will supply and place 120 tons of #73 aggregate for shoulder backing.

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Contractor’s Key Personnel
7.0 Security Requirements
8.0 Performance Requirement Measures
Attachment