This document outlines a statement of work for a gravel supply project on Hiawatha National Forest. The contractor will furnish all materials, equipment, trucking, labor, transportation, MDOT 23A gravel, and miscellaneous supplies to haul and spread a minimum of 400 tons per day and maximum of 600 tons per day of aggregate on Forest Route 2473. The contractor must provide weight slips for each load delivered and make all slips available to the forest service daily. Work will take place between 7:00 AM and 3:30 PM Monday through Thursday. The location of FR 2473 is provided. The contractor must limit operations to the defined construction area and prevent damage to surrounding natural features, restoring any damaged areas at no additional cost.

The related federal contract opportunity is solicitation number 12444524Q0020 for the West Zone Gravel Contract for Hiawatha National Forest. The work consists of furnishing all materials, equipment, trucking, labor, transportation, weight slips, MDOT 23A gravel, and miscellaneous supplies to complete aggregate hauling and chain drop spreading on FR 2473. The agency is the US Department of Agriculture Forest Service.

View the file

Other files

File Type Posted
1. Maps.pdf PDF
2. Delta County SCA WD 2015-4871.txt TXT text file
OM-RFQ 12444524Q0020.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 302

FR 2473 Gravel Supply Project - Hiawatha National Forest

SUMMARY of work summary Name of Project: FR 2473 Gravel Supply Project Work for this project consists of: Furnish all material, equipment & trucking, labor including wages, supervision, transportation, weight slips, MDOT 23A gravel, and misc. materials necessary to complete aggregate hauling and chain spreading/unloading on FR 2473 as stated in the specifications and attachments.

Forest Service will provide traffic control signage. These signs will warn the public of “Road Construction Ahead”. The Contractor will follow all Safety requirements on the Forest Service Road system. The roads will be open to the Public during project activities.

Contractor shall supply, haul, and place MDOT 23A aggregate.

Contractor shall unload gravel using spreader chains in locations designated by Forest Service personnel.

The Contractor shall deliver at a minimum of 400 tons/day and no more than 600 tons/day.

The Contractor shall deliver aggregate between 7:00 AM and 3:30 PM, Monday through Thursday.

Contractor shall provide weight slips (date/time) for every load of gravel delivered. All weight slips at the end of each day shall be provided to the Forest Service Representative.

location FR 2473 is located approximately 2.5 miles Southeast of the M-94 and FR2268 (Buckhorn road) intersection in Alger County.

USE OF PREMISES

General: The Contractor shall limit his operations to the construction limits within the defined area of FR 2473.

Preservation of Natural Features: Contractor shall confine all operations to work limits of the project and prevent damage to natural surroundings. Contractor shall restore damaged areas at no additional expense to the Government.