1. Statement of Work (SOW).docx
DOCX document 60 KB Posted
- Solicitation number
- 12444524Q0010
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for dam valve maintenance services for the Hoosier National Forest Tell City Ranger District. The solicitation number is 12444524Q0010 and is being issued by the United States Department of Agriculture Forest Service. The SOW requires maintenance and repair services for valves located at five dams in the Tell City Ranger District. Services include inspection, cleaning, lubrication, adjustment and replacement of valve components as needed. The period of performance is one base year with four option years. Bids are due by April 15, 2023 and it is anticipated the contract will be awarded by May 15, 2023. Pricing shall be fixed for the base year and option years. This is an unrestricted procurement open to small and large businesses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3. Perry County SCA WD 2015-4823.txt | TXT text file | |
| OM-RFQ 12444524Q0010.pdf | ||
| 2. Vicinity Map.pdf | ||
| 4. Experience Questionnaire.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents
| Project | 3 | |
| General Information | 3 | |
| 1.0 | Scope of Work | 3 |
| 2.0 | Background | 3 |
| 2.1 Dams Valve & Inlet Details | 3 | |
| Contractor Requirements | 4 | |
| 3.0 | Technical Requirements / Tasks | 4 |
| 3.1 | Celina Lake Dam Valve Inspection | 4 |
| 3.2 | Saddle Lake Dam Valve Inspection | 4 |
| 3.3 | U-38 Lake Dam Valve Lift-Stem Inspection | 4 |
| 3.4 | Inspection Report | 4 |
| 4.0 | Government Furnished | 4 |
| 4.1 Valve Structure As-Built Drawings | 4 | |
| 4.2 Access Keys | 4 | |
| 5.0 | Deliverables / Schedule | 4 |
| 6.0 | Contractor’s Key Personnel | 4 |
| 7.0 | Mandatory Contractor Training | 4 |
Project Dams Valve Inspection for Hoosier National Forest - Tell City Ranger District.
General Information
1.0 Scope of Work
The scope of work includes the inspection and reporting of the dam valve assemblies and structures at Celina Lake, Saddle Lake, and U-38 dams located on the Hoosier National Forest.
2.0 Background
The Hoosier National Forest has three earthen dams that have maintenance needs with their valve operations. These dams are located on the Tell City Ranger District (See attached maps for locations and directions). The valve systems for all three dams are different. Known equipment and diagrams for each dam has been included in attachments to this solicitation. A copy of the as-builts can be acquired upon request.
2.1 Dams Valve & Inlet Details
| Celina Lake |
| Elevation |
| Riser Crest – High Stage of Principle Spillway (Inlet Structure) |
| 542.75’ |
| Sluice Gate Invert |
| 489.75’ |
| Shaft depth (approximate) |
| 53.00’ |
*Note, the valve and lift are made by Hydro Gate Corporation, Commerce City, Colorado.
| Saddle Lake |
| Elevation |
| Riser Crest – High Stage of Principle Spillway (Inlet Structure) |
| 499.00’ |
| Sluice Gate Invert |
| 477.00’ |
| Shaft depth (approximate) |
| 22.00’ |
*Note, the valve, stem, and lift are provided by Coldwell-Wilcox Technologies dba. Cast-Fab Technologies, Inc., Cincinnati, Ohio.
| U-38 Lake |
| Elevation |
| Top of Inlet Structure |
| 512.00’ |
| Riser Crest – High Stage of Principle Spillway (Inlet Structure) |
| 505.00’ |
| Knife Gate Invert |
| 497.11’ |
| Shaft depth (approximate) |
| 15.00’ |
Note, the Valve, stem, and lift provided by Fuller, Mossbarger, Scott & May Engineers, Inc. dba. Stantec-Kleinfelder JV.
Contractor Requirements
Technical Requirements / Tasks
3.1 Celina Lake Dam Valve Inspection
The Celina Lake Dam Valve is seized. The Forest Service (FS) has assessed the gear box, and it appears to be free. We are interested in contracting the inspection of the valve and lift system to see what is keeping it from opening and closing.
3.2 Saddle Lake Dam Valve Inspection
The Saddle Lake Dam Valve will not close completely but does move freely. The FS is interested in contracting the inspection of the valve and lift system to see what is keeping it from closing completely.
3.3 U-38 Lake Dam Valve Lift-Stem Inspection
The U-38 Valve Lift-Stem system has come loose from the wall of the inlet structure. It appears to be within the top 6 feet of the riser; however, there could be additional issues below. The request for this dam is to inspect the entire inlet structure for proper operation of the valve, lift, and stem system.
3.4 Inspection Report
A written report that contains a detailed description of the repairs needed, a list of materials, and an itemized cost estimate to complete needed repairs. Any needed repairs will be funded under a future contract when funding becomes available.
Government Furnished
4.1 Valve Structure As-Built Drawings
A copy of the valve structure as-built drawings can be provided upon request.
4.2 Access Keys
Keys to access the dam valve structures will be provided.
Deliverables / Schedule A written report that contains a detailed description of the repairs needed, a list of materials, and an itemized cost estimate to complete needed repairs shall be submitted after completion of valve inspections. Any needed repairs will be funded under a future contract when funding becomes available.
Contractor’s Key Personnel Both Celina and Saddle Lake Inlet Structures have two chambers, one wet and one dry. The valves for both dams are located on the lake side in the wet chambers. U-38 has only one chamber. All work performed inside the inlet structures are considered a permit required confined space. Personnel entering the inlet structure shall be currently confined space certified and follow all OSHA 29 CFR 1910 regulations.
Mandatory Contractor Training
After award, the contractor must ensure their employees (including subcontractor personnel) complete the training course(s) listed below in the frequency identified. The contractor must maintain records of course completion and provide them to the Contracting Officer Representative upon request.
| Course Name |
| Frequency (Once, Quarterly, Annually, etc.) |
| Method of Training |
| Length of Training |
| Completion Date |
| Understanding and Interrupting Unconscious Bias |
| Annually |
| AgLearn |
| 90 minutes |
| 90 days after assignment in AgLearn |
| Anti-Harassment Training: Identifying and Preventing Workplace Harassment |
| Annually |
| AgLearn |
| 60 minutes |
| 90 days after assignment in AgLearn |
| Information Security Awareness |
| Annually |
| AgLearn |
| 60 minutes |
| 1 year since last completion date |
| USDA Records Management |
| Annually |
| AgLearn Or Paper- based |
| 60 minutes |
| 60 days after assignment |
| Section 508 |
| Annually |
| AgLearn |
| 60 minutes |
| 45 days after assignment |
If needed, add other courses as approved by the Contracting Officer
In accordance with DR3640-001 Identity, Credential, and Access Management (06/08/21) United States Department of Agriculture Office of Safety Security and Protection (OSSP) Version 3.0 June 2020 Frequently Asked Questions (FAQs)
A sponsor will decide if you need a LincPass/AltLinc through the process of a credential risk assessment using the USDA Credential Matrix to determine if a person requires a LincPass/AltLinc. Through the Risk Assessment, other determining factors for the requirement of a LincPass/AltLinc include:
· The Employee requires a Level 2 eAuthentication account, a USDA email address, or access another protected IT resource
· If the Employee has access to sensitive information,
· If the Employee requires unescorted access to areas within Mission Critical or National Capital Region (NCR) facilities or as determined by an agency’s local risk assessment process
Below is the USDA Credential Matrix that Sponsors use to determine the type of credential a person may require.
Table 1: USDA Credential Matrix
| IT and Physical Access Rights Required |
| LincPass |
| AltLinc |
| Site Badge |
| Visitor |
Badge No Badge
| IT & Unaccompanied Physical Access Required > 6 Months |
| X |
IT & Unaccompanied Physical Access Required < 6 Months
X
No IT Access Required & Unaccompanied Physical Access Required
X
No IT Access Required & Accompanied Physical Access Required
X
No IT or Physical Access Required
X image1.png
File details come from the government source that posted it. Updated .