Additional Questions and Answers 12444324Q0044 06-11-2024.pdf
PDF 120 KB Posted
- Solicitation number
- 12444324Q0044
About this file
This document contains a set of Additional Questions and Answers for Solicitation 12444324Q0044 for the Green Mountain National Forest Admin Site Security Camera Installation project.
The solicitation is for services to install security cameras at the Manchester and Rochester Ranger District offices. Key details include: the Manchester office requires 8 cameras, with wireless connection between the office and garage/workshop; the Rochester office has drop ceilings and a workshop with a sheetrock ceiling; cable routing should be through drop ceilings where possible, otherwise through walls per building code; 5MP cameras recording at 30FPS are required; and the award may be made to a single offeror for all locations or multiple offerors by location. Offerors can submit a single quote for all locations or individual quotes by location.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers 12444324Q0044
1. The Schedule and SOW call out 9 cameras for the Manchester Office, but I'm only seeing
8 cameras called out on the satellite image. I may be missing a ninth camera on the
PDF?
a. The arial image that shows 8 cameras is correct. Manchester Office is to have 8 cameras.
2. Do you know how the ceilings are finished at the Manchester and Rochester office buildings, such as a drop-ceiling or attic space? For example, my hunch is that the Manchester Office is a single story building with a drop-ceiling, while the Rochester Office looks larger, with multiple floors and may have an attic? I'm just trying to understand access for cabling.
a. The interior ceiling of the Manchester Office is drop ceiling. The garage is open trusses, except a portion that is enclosed with sheetrock.
b. Rochester Office has dropped ceilings and the workshop has a sheetrock ceiling.
c. The Supervisor’s Office has dropped ceilings.
3. To connect the main Office to the Garage or Workshop, is there a preference on how the buildings are connected? Trenching, wireless link, etc.?
a. Wireless link
4. I noticed in the SOW, the PELCO Sarix Value Bullet is listed as an example. I understand that it's an example, but wanted to verify that the minimum specs required are 5 MP at 30 frames per second? I believe the 5MP version of the PELCO Sarix Value Bullet will only record at 20 frames per second.
a. Provide 5 MP and 30 Frames per Second
5. We'd like to know how you would want us to run the cable, is it through conduit or PVC.
Do you have a drop ceiling in which we can run the wire? or do we need to drill a hole in the walls to run the camera cable?
a. See Question 2 for ceiling types. Run cable through drop ceilings where possible. As required, the contractor shall install cable through walls in accordance with building codes.
6. Is there an uplink cable from the Workshop to the Office in Rochester?
a. No
7. Is there an uplink cable from the Garage to the Office in Manchester?
a. No
8. Are you certain you’d like bullets inside. Typically, we install dome cameras internally.
a. Dome cameras are acceptable as long they meet the salient characteristics of the SOW.
9. To confirm, you’d like a single quote for both projects not individual quotes per location?
a. Per the solicitation, “Award may be made to a single Offeror for all items at all locations, or multiple Offerors based on location.”
b. If you are going to quote on all locations and all items please send one quote.
If you are only sending a quote in for one location for example then you may send a quote in for just that location.