Sol: 12444322Q0057 ANF Muddy Fork Overlay Bridge Design & Fabrication

Questions and Answers

1) Please confirm prevailing wage rates are required for all on-site work. Wage Determination PA 2015-4247 Rev 19 6/27/2022

2) Page 3 lists some bullet points under the “Installation” heading and notes “place up to 100 ton of PA 2A material per side” and “Optional: Construct wing-walls utilizing pre-cast concrete blocks to minimize the amount of fill required.

Includes up to ten 2’x2’x6’ pre-cast blocks per side”. We are concerned that (1) those two requirements are ambiguous and (2) after reviewing the site in person, due to the fact that the hillside slopes away from the roadway somewhat steeply on the one side, it will likely take both the pre-cast blocks and nearly the entire quantity of 2A listed in order to create a reasonable transition on/off the bridge deck. We suggest the requirements be clarified as follows:

a. Bidder shall furnish a minimum of 24 – 2’x2’x6’ pre-cast concrete blocks for constructing the bearing surface and wing walls.

b. Bidder shall furnish/place no less than 80-ton of 2A material on either side of the bridge.