12444022R4001 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ATLANTA GA 30309-2449
STE 876S
1720 PEACHTREE ST NW
USDA-FS CSA EAST 2
06/27/20220001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/21/2022
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to answer solicitation questions submitted by interested vendors and to provide an update list of schedule items.
no other changes.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
MARIAN W. FEIST
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
12444022R4001
Amended Schedule of Items
Solicitation# 12444022R4001
Item# Description Unit Estimated
Qty Unit
Price
Total
Price
5.1 Tree Planting - Manual
5.1.1 Plant Bare Root Pine 100-300 seedlings per Acre Acre 75 $ $
5.1.2 Plant Bareroot Pine Cluster of 1,740 seedlings per Acre Acre 1 $ $
5.1.3 Plant Containerized Pine 100-300 seedlings per Acre Acre 1 $ $
5.1.4 Plant Bareroot Hardwood - 25-50 seedlings per acre Acre 1 $ $
5.1.5 Plant Bareroot Hardwood Cluster - 100-300 seedlings per Acre Acre 1 $ $
5.1.6 Plant Bareroot Hardwood Cluster - 1,740 seedlings per Acre 1 $ $
5.2 Site Preparation - Chainsaw or Herbicide
5.2.1 Site Prep - Slashdown by Chainsaw Acre 175 $ $
5.2.2 Site Prep - Hack'n' Squirt Herbicide Acre 500 $ $
5.2.3 Stump Sprout - Streamline Basal Bark Herbicide Acre 50 $ $
5.2.4 Site Prep - Cut Stem Surface Herbicide Acre 1 $ $
5.2.5 Site Prep - Hack and Squirt and Foliar Spray Herbicide Acre 1 $ $
5.3 Thinning - Chainsaw
5.3.1 Midstory Chainsaw Slashdown – High Density Acre 300 $ $
5.3.2 Midstory Chainsaw Slashdown - Medium Density Acre 1000 $ $
5.3.3 Midstory Chainsaw Slashdown - Low Density Acre 1 $ $
5.3.4 Midstory Chainsaw Slashdown with Slash Treatment - High Density Acre 1 $ $
5.3.5 Midstory Chainsaw Slashdown with Slash Treatment - Medium Density Acre 1 $ $
5.3.6 Midstory Chainsaw Slashdown with Slash Treatment - Low Density Acre 1 $ $
5.3.7 Midstory Chainsaw Slashdown – Small & Medium Sized Trees Acre 1 $ $
5.3.8 Pre-commercial Thinning – 200 TPA Acre 1 $ $
5.3.9 Daylighting Roadsides or Wildlife Openings Acre 100 $ $
5.4 Midstory Control - Herbicide Single Methods
5.4.1 Midstory Thinline Herbicide - High Density Acre 1 $ $
5.4.2 Midstory Thinline Herbicide - Medium Density Acre 1 $ $
5.4.3 Midstory Thinline Herbicide - Low Density Acre 135 $ $
5.4.4 Midstory Hack n ’Squirt Herbicide – Low Density Rhododendron Acre 1 $ $
5.4.5 Crop Tree Release Chainsaw – Seedlings/Saplings – 300 TPA Acre 1 $ $
5.4.6 Crop Tree Release Chainsaw – Larger Trees – 75 TPA Acre 1 $ $
5.4.7 Midstory Hack n ’Squirt Herbicide – Higher Density Rhododendron Acre 1 $ $
5.5 Midstory Control - Herbicide Combined Methods
5.5.1 Midstory Thinline/Hack n’ Squirt Herbicide - Small & Medium Sized Trees Acre 1 $ $
5.5.2 Midstory Foliar & Hack and Squirt Herbicide - High Density Acre 1 $ $
5.5.3 Midstory Foliar & Hack and Squirt Herbicide - Medium Density Acre 200 $ $
5.5.4 Midstory Foliar & Hack and Squirt Herbicide – Low Density Acre 1 $ $
5.5.5 Midstory Foliar & Cut Stump Herbicide – High Density Acre 1 $ $
5.5.6 Midstory Foliar & Cut Stump Herbicide – Medium Density Acre 1 $ $
5.5.7 Midstory Foliar & Cut Stump Herbicide – Low Density Acre 1 $ $
5.6 Crop Tree Release - Chainsaw
5.6.1 Crop Tree Release Chainsaw - Seedlings /Saplings – 25 TPA Acre 1 $ $
5.6.2 Crop Tree Release Chainsaw - Seedlings/Saplings – 50 TPA Acre 1 $ $
5.6.3 Crop Tree Release Chainsaw – Seedlings/Saplings – 100 TPA Acre 1 $ $
5.6.4 Crop Tree Release Chainsaw – Seedlings/Saplings – 200 TPA Acre 1 $ $
5.7 Crop Tree Release - Herbicide Single Methods
5.7.1 Crop Tree Release Streamline Basal Bark Herbicide – 25 TPA Acre 1 $ $
5.7.2 Crop Tree Release Streamline Basal Bark Herbicide – 50 TPA Acre 1 $ $
5.7.3 Crop Tree Release Streamline Basal Bark Herbicide – 100 TPA Acre 1 $ $