This document is an Amendment (Amendment 0001) to Solicitation 12441925R0005 for the Blackwell Job Corps Center roofing rehabilitation project issued by the USDA Forest Service. The amendment extends the quotation deadline to 14:00 EST on 14 May 2025 and provides comprehensive responses to potential contractors' technical questions. Key clarifications include confirmation that the Superintendent, SSHO, and QC Manager do not need to be separate individuals, potential for time extension with material lead time justification, and details about the roofing work such as chimney demolition, existing roof framing (typically wood rafters/trusses), and roofing specifications (24-gauge metal roofing). The project involves roof rehabilitation for multiple buildings, including the Carpentry Building and several residences on Nowak Lane, with a desired start in summer 2025 and completion prior to 2026. The amendment also addresses site-specific details like lead-based paint assumption, occupied buildings, staging areas, and roofing manufacturer warranty requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12441925R0005 FNL.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5/9/2025
1 3
IAN K. BARNES
X
9A. SOLICITATION NUMBER
12441925R0005
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
The purpose of Amendment 0001 is to provide Government responses to Offeror questions and extend the quotation deadline. Quotations shall be submitted no later than 14:00 (2:00 PM) EST on 14 May 2025.
Quotations shall be submitted to both:
Nicholas.Bartolomei@usda.gov and Ian.Barnes@usda.gov
All other terms and conditions remain unchanged.
12441925R0005 Amendment 0001 Questions are in Black Answers are in Red:
Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
No
Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
Justification and supporting documentation from materials suppliers would be required prior to an allowance for a time extension/modification by the Contracting officer beyond the 150 day (after NTP issuance).
Please provide bidding quantities for deteriorated underlayment (roofing)/base course (paving).
There is no base course/paving on this roofing contract. The buildings are available for schedule site visits for bidding contractors to measure for quantities.
Please provide the site visit registration information.
I don’t have a site visit registration.
How far below finished floor do we need to demo the chimney?
To finished floor level – see specifications and drawings.
Does chimney demo below floor need to be infilled with concrete? If so, to what depth? Demo extends to finish floor level.
What is the existing farming system at the roof?
Typically wood framing – rafters/trusses.
Is lightning protection required for new metal roofing?
A lightning protection system is not specified.
Are existing gutters to be reused or replaced?
Review the specifications and drawings. Re-install gutters on 4212 Nowak Lane roof. Some specific items (antennas, chimneys) are designated for removal disposal (varies by roof) otherwise coordination with new roofing and/or removal reinstallation of components to allow for roof replacement is required.
Please provide bidding quantities for decayed roof sheathing, fascia, and adjoining siding.
Review the specifications, drawings, and schedule of items. Siding replacement will generally be limited to specific locations indicated (associated with chimney removal at 4208 Nowak) or when required for proper integration of new roofing flashing counterflashing – such as sidewall or headwall dormer flashing. The buildings are available for schedule site visits for bidding contractors to measure for quantities.
Please confirm the material of the existing siding. Is new siding to match existing?
Varies by building, close match specified but understand exact match may not be possible due to variety of age/type of siding.
Will insulation at the roof need to be replaced? If so, please provide type and quantity for bidding purposes.
Roof insulation is not being installed/replaced.
What gauge is preferred for the new roofing system?
See specification section 074113, 2.4B2 -> 24-gauge.
Please confirm the manufacturer of the existing roofing system and who carries the current warranty of the roofing system.
We don’t have this information.
Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation.
The Blackwell Facility Survey report indicates ACM surveys were conducted in 1998 and no ACM was present.
I’ve made a request for any available copies of the ACM surveys. B426 (Carpentry) was constructed in 1987. The houses were constructed in the 1960’s-1970’s, lead based paint should be assumed present.
Are any of these buildings occupied? How many people will be in the building? Are there any temporary heating/cooling requirements?
All buildings will be occupied. Number of people will vary by building. The contractor does not have any specific responsibility for the provision of heating/cooling inside the building.
Are there any phasing requirements?
No phasing is specifically required, contractor shall schedule and be responsible for protection of buildings during selective demolition until made weathertight.
Please provide a lay down/staging area for construction.
Lay down areas will be directly adjacent to work areas, staging areas will be available in the building 426 parking lot and adjacent to the Nowak Lane residential loop and will be coordinated with the selected offeror during prework meeting.
Is there an anticipated start date?
Desired start time is summer of 2025 with completion prior to 2026.
Is there a need for any third party testing?
There are material test standards. No specific third-party testing of installed roofing is specified, though contractors will be responsible of securing any roofing manufacturer inspections that may be required for the NDL warranties.