SOW FOR BLDG 31 HVAC

View the file

Other files for this federal contract opportunity

Other files attached to HVAC ALTERATION/ RENOVATION, newest first.
File Type Posted
Sol_12438918Q0004_CLAUSES.docx DOCX document
SF_1442-12438918Q0004.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HVAC Alteration/Renovation Southeast Watershed Research Laboratory, Building 31

PURPOSE______________________________________________________________________

The HVAC system(s) of the Southeast Watershed Research Soils Lab functions to support a single-pass air arrangement. However, due to a change in the type of research being conducted in this lab, single-pass air is no longer required. Furthermore, the current HVAC equipment has exceeded its expected service life and performs inadequately causing difficulties to properly heat, cool, and dehumidify both lab and office spaces. This document details the requirements USDA-ARS will need to accept a successfully outsourced HVAC alteration/renovation at this lab.

SCOPE OF WORK________________________________________________________________

· Disconnect and remove 18-ton Addison package unit (Model: TRSA210BG4D3A, Serial: 100802801001) from NE corner of building, disconnect and remove all existing electrical and refrigeration connections and BACview controls

· Disconnect and remove 4-ton Goodman package unit (Model: PH048-1AB, Serial: 9808542558) from W side of building, disconnect and remove all existing electrical and refrigeration connections and associated controls

· Remove existing supply ductwork from attic above lab area and behind paneling wall as necessary on E side of building, paneling damaged while removing ductwork shall be replaced

· Provide and install (1) 3-ton package unit heat pump with heat strips, new pad, and simple digital/programmable t-stat/controller to serve E side of building lab area, install new hood/shroud, new insulated supply duct and supply grilles, new return duct with the addition of (2) new 24”x24” return grilles, (1) in each lab room. Lab area is approximately 1,400 - 1,600 ft2

· Provide and install (1) 2-ton package unit heat pump with heat strips, new pad, and simple digital/programmable t-stat/controller to serve W side of building office/kitchen area, install new hood/shroud, utilize existing ductwork, install reducers in supply duct lines, install reducers in return ducts lines. Office/kitchen area is approximately 700 - 900 ft2

· Relocate manual exhaust fan control switch from attic downstairs to lab floor level

· Seal exhaust ducts and associated roof penetrations above ceiling grid for (2) fume hoods and AA instrument, disconnect and remove (1) 4-foot fume hood and (1) 6-foot fume hood each to be placed in storage at site

LOCATION OF WORK_____________________________________________________________

United States Department of Agriculture Agricultural Research Service Southeast Watershed Research Laboratory, Soils Lab, Building 31 112 Bunny Run Road Tifton, Georgia 31793

PERIOD OF PERFORMANCE

Hours of operation at this location shall be 8:00am – 4:30pm Monday-Friday, excluding federal holidays, furloughs, or inclement weather site closures. The contractor shall coordinate any deviation from normal duty hours with the location POC at least 1 day prior. This project shall be completed within 30 business days from notification of award. Arrangements shall be made to temporarily vacate the lab as needed prior to work beginning. A contractor badge shall be signed out from and returned to either the administrative office or the maintenance shop each day work is performed.

MISCELLANEOUS

The contractor shall furnish all transportation, labor, tools, equipment, and materials to include all accessories and incidentals necessary to complete this job to governmental standards. All work shall be done in accordance with applicable regulatory codes and standards. All work shall be accomplished in a safe and professional manner in accordance with good workmanship and acceptable practices.

All tools, equipment, and materials stored in the work area shall be done so at the risk of the contractor. USDA will not be responsible for any contractor possessions, either inside or outside of the building at any time.

Quotes that propose alternative equipment, materials, and/or methods than those specified shall be of equal or higher quality. Contractors shall submit specification sheets for proposed equipment and materials to summarize performance and technical characteristics.

The contractor shall be responsible for complete removal, disposal, and cleanup of replaced material and debris to include natural and man-made as part of work performed. Property damaged on site during the construction process will be replaced at the expense of the contractor.

With adequate notice, the contractor shall coordinate with the location POC work having potential to disrupt research and/or support efforts of USDA-ARS personnel. Contractor shall notify the POC of any expected utility outages in advance.

The contractor shall provide all associated literature and documents for new equipment and materials to include, but not limited to: operation and maintenance manuals, installation instructions, technical data sheets, guarantee and warranty forms, etc.

All contractors must visit the site to acquaint themselves with the project condition prior to quote submittal. The point of contact on site will be Dustin Stinnett at (229) 387-2370 or (229) 646-1301. Site visits will be made by scheduled appointment 23 July 2018 – August 3 2018. Failure to visit the site prior to quote submittal will be grounds for quote rejection. Failure to become acquainted with the site will not relieve contractors from full responsibility for a complete job as specified.

PHOTOS_______________________________________________________________________